Minuteman Vocational Technical Regional High School Progress

Similar presentations


Presentation on theme: "Minuteman Vocational Technical Regional High School Progress"— Presentation transcript:

1 Minuteman Vocational Technical Regional High School Progress
February 25th 2019 – March 18th 2019

2 March 18th View of Area A+B – Upper Level
Ceramic wall tile installation in progress.

3 March 18th View of Area G – Upper Level
FRP wall protection installation in progress. March 18th View of Area G – Upper Level Lab Casework installation in progress.

4 March 18th View of Area G – Lower Level
March 18th View of Area D – Upper Level Ceiling grid installation in progress. Borrowed Light Glass installation complete. FRP wall protection installation to commence. March 18th View of Area G – Lower Level Interior wall framing and in-wall MEP installation in progress in Locker Room Areas.

5 March 18th View of Area D – Gymnasium
Rough-In of Overhead Electrical in Progress. Light fixtures being hung. Borrowed light installation complete.

6 March 18th View of Area D – Mechanical Room
Electrical & Control Wiring to equipment is in progress. Installation of insulation in progress through out room.

7 March 18th View of Area E – East Elevation
Masonry Stone Veneer in progress on Upper Level. Metal Panel Wall Panels Complete, Soffits in Progress. March 18th View of Area E – East Elevation Skylight Framing & Glazing being hoisted to the roof level.

8 March 18th View of Area E – Bridge Level
Prime & Finish painting substantially complete. Ceiling grid installation to commence. March 14th View of Area E+F – Lower Level Kitchen Hood and Gas Train delivered. Installation to commence 3/19.

9 March 18th View of Area E+F – Cafeteria
Installation of wood blocking and sheetrock activities are in progress.

10 March 18th View of Area F – Lower Level
Sheetrocking walls in progress. Taping activities in progress.

11 March 18th View of Area C – Theater
Interior framing on all levels in progress. Rough-in of in-wall MEP’s to commence. March 18th View of Area C – Lower Level Interior Framing substantially complete. Rough-in of in-wall MEP’s in progress.

12 March 18th View of Area E – Courtyard
Excavation and subgrade prep in progress. March 18th View of Area A+B – West Roadway Excavation and shaping of drainage swale in progress at perimeter of roadway.

13 March Construction Schedule Look Ahead:
Area A+B Continue installation of Lights, Registers and other MEP devices in ceiling grid Continue Millwork & Casework installation on Lower B Continue Installation of Ceramic Wall Tile Area G Continue Casework installation on Upper G Commence Installation of Ceramic Wall Tile Area D Complete Ceiling Grid Installation Continue Electrical & Control Terminations to equipment in Mechanical Room Area E Complete Sheetrocking & Taping activities on all levels Complete Prime Painting on all levels Commence Ceiling Grid on Bridge & Lower Levels Area F Complete Sheetrocking & Taping activities Commence Prime paint activity Commence Kitchen Hoods & Gas train installation Area C Complete interior wall framing activities. Commence rough in of in-wall MEP’s Commence Sheetrocking activities Exterior/Sitework National Grid to commence gas line installation on 3/21, approx 3 week installation duration Continue shaping the swales at the perimeter of the building Commence drainage and parking island development in Faculty parking lot

14


Download ppt "Minuteman Vocational Technical Regional High School Progress"