Minuteman Vocational Technical Regional High School Progress
February 25th 2019 – March 18th 2019
2
March 18th View of Area A+B – Upper Level
Ceramic wall tile installation in progress.
3
March 18th View of Area G – Upper Level
FRP wall protection installation in progress. March 18th View of Area G – Upper Level Lab Casework installation in progress.
4
March 18th View of Area G – Lower Level
March 18th View of Area D – Upper Level Ceiling grid installation in progress. Borrowed Light Glass installation complete. FRP wall protection installation to commence. March 18th View of Area G – Lower Level Interior wall framing and in-wall MEP installation in progress in Locker Room Areas.
5
March 18th View of Area D – Gymnasium
Rough-In of Overhead Electrical in Progress. Light fixtures being hung. Borrowed light installation complete.
6
March 18th View of Area D – Mechanical Room
Electrical & Control Wiring to equipment is in progress. Installation of insulation in progress through out room.
7
March 18th View of Area E – East Elevation
Masonry Stone Veneer in progress on Upper Level. Metal Panel Wall Panels Complete, Soffits in Progress. March 18th View of Area E – East Elevation Skylight Framing & Glazing being hoisted to the roof level.
8
March 18th View of Area E – Bridge Level
Prime & Finish painting substantially complete. Ceiling grid installation to commence. March 14th View of Area E+F – Lower Level Kitchen Hood and Gas Train delivered. Installation to commence 3/19.
9
March 18th View of Area E+F – Cafeteria
Installation of wood blocking and sheetrock activities are in progress.
10
March 18th View of Area F – Lower Level
Sheetrocking walls in progress. Taping activities in progress.
11
March 18th View of Area C – Theater
Interior framing on all levels in progress. Rough-in of in-wall MEP’s to commence. March 18th View of Area C – Lower Level Interior Framing substantially complete. Rough-in of in-wall MEP’s in progress.
12
March 18th View of Area E – Courtyard
Excavation and subgrade prep in progress. March 18th View of Area A+B – West Roadway Excavation and shaping of drainage swale in progress at perimeter of roadway.
13
March Construction Schedule Look Ahead:
Area A+B Continue installation of Lights, Registers and other MEP devices in ceiling grid Continue Millwork & Casework installation on Lower B Continue Installation of Ceramic Wall Tile Area G Continue Casework installation on Upper G Commence Installation of Ceramic Wall Tile Area D Complete Ceiling Grid Installation Continue Electrical & Control Terminations to equipment in Mechanical Room Area E Complete Sheetrocking & Taping activities on all levels Complete Prime Painting on all levels Commence Ceiling Grid on Bridge & Lower Levels Area F Complete Sheetrocking & Taping activities Commence Prime paint activity Commence Kitchen Hoods & Gas train installation Area C Complete interior wall framing activities. Commence rough in of in-wall MEP’s Commence Sheetrocking activities Exterior/Sitework National Grid to commence gas line installation on 3/21, approx 3 week installation duration Continue shaping the swales at the perimeter of the building Commence drainage and parking island development in Faculty parking lot