Fermi Lab – 2019 CMB-S4 Workshop
Schedule and Cost Overview Kathy Bailey – ANL 3/14/2019
2
Schedule Cost Rules of Engagement Current Rollup WBS
Outline Schedule WBS Milestones/Critical Path Cost Rules of Engagement Current Rollup
3
WBS Level 2 Updates Updates Moved Systems Engineering to WBS 1.01 PM
Split Detectors and Readout (1.03 Detectors & 1.04 Readout & System Testing) Created Site Specific WBS for Chile (1.09) and the South Pole (1.10) Moved Sites/Integration and Commissioning to a level 3 WBS Moved DAQ deployment into Chile/South Pole WBS elements
4
WBS Levels for 1.01 PM & Systems Engineering
Added Systems Engineering to the PM WBS Captured all PM IPO/L2 CAM/Travel support through FY2021
5
WBS Levels for 1.02 R&D Added Project Specifics
6
WBS Levels for 1.03-1.04 Detector- Readout/System Test
Awaiting Task Force guidance
7
WBS Levels for 1.05 Large Telescope
No changes
8
WBS Levels for 1.06 Small Telescope
Significant update in SATs Added Crate and Ship WBS Lvl 4 Added detailed Review schedule
9
WBS Levels for 1.07/1.08 DAQ & DM Moved DAQ deployment to the sites
DM unchanged
10
WBS Levels for 1.09 Chile and 1.10 South Pole
Significant structure change Similar layout at WBS Lvl 3 with site specific levels/activities lower Ready for cost updating
11
Schedule Milestones: 1.01 Project Management
Unchanged Current efforts are concentrated on relationships within the WBS level 2s Interfaces are being defined and will be documented in the schedule Updates to the critical path dependent on Detector/Readout Schedule
12
Cost CMB-S4 Planning Document Issued
Launched project planning standards Isolated pre-CD-1 efforts in WBS 1.01 (PM) and 1.02 (R&D) Defined # of reviews/types Removed duplication support areas (Sys Eng, Quality, Safety, Controls) Defined per trip travel cost Defined calendars for US/Chile/South Pole Identified assumptions for “in-kind” and costed resources Defined Information Flow P6 Schedule > Google Docs (for cost/BOE entries) > P6 Schedule > Cobra for Costing
13
Current Cost Estimate – Not for distribution
Current bottom up cost and contingency estimate: Preliminary, not for distribution Added time-phased IPO/R&D costs to align with budget request SAT has updated, lower costs Chile/South Pole DSR review $ separated but not validated Duplication of Sys Eng support removed
14
Next Steps from DSR Review
TOOLS Deploy Risk Management Tool COST Evaluate labor/non-labor inputs for reduction opportunities Review BOE/Contingency values Overlay funding profile Normalize Project Office/SE/Quality planning Rates Model University Rate Structure – create appropriate resources Determine In-kind resources for project exclusion Refine Chilean support resources Finalize escalation rates for labor/non-labor SCHEDULE Deploy unique Resource Calendars for South Pole and Chile Further define “Need”/”Avail” Usage