Buildings Entrance Tunnel. 5th Review Committee October 4th, 2004 Buildings, Facilities and Schedule C. Sanelli.

Similar presentations


Presentation on theme: "Buildings Entrance Tunnel. 5th Review Committee October 4th, 2004 Buildings, Facilities and Schedule C. Sanelli."— Presentation transcript:

1 5th Review Committee October 4th, 2004 Buildings, Facilities and Schedule C. Sanelli

2 Buildings Entrance Tunnel

3 Entrance Tunnel

4 Entrance Tunnel

5 Works for Chimney (VVFF request)

6 Works for Chimney (VVFF request)

7 SPARC HALL, Laser Nave

8 SPARC HALL Clean Room

9 Electric power distribution system:
Public Tender: Published on the Italian Official Bulletin on September 21, Documentation to be sent before October 11, 2004.

10 Electric Distribution Lay-out

11 Laser Clean Room: Installed
Note: Anti-chamber (power supply room) ready to be ordered.

12 Water Cooling and Air Conditioning System:
Detailed Design: Completed Public Tender: Directors’ Board Authorization Requested on September 17, 2004

13 Cooling System Lay-out

14 Fire protection system: Tender Completed, Order ready, Works near to start.
Radiation protection system: Tender authorized and under way

15 next argument: Schedule Just a moment…..