A Watershed Approach to Environmental Restoration in Mecklenburg County David A. Woodie, PE, CPSWQ Mecklenburg County Land Use & Environmental Services Agency Special Thanks to: Emily G. Reinicker, PE, CFM Jason Claudio-Diaz, PE, CFM Wildlands Engineering, Inc. Kimley-Horn and Assoc., Inc.
2
WATERSHED / BASINS 330± miles of FEMA streams330± miles of FEMA streams 32 watersheds32 watersheds All water in Mecklenburg County (except Catawba River) originates in Mecklenburg CountyAll water in Mecklenburg County (except Catawba River) originates in Mecklenburg County
3
Presentation Overview Early Planning Process Funding Partners and Stakeholders Overview Map Project Reaches Monitoring Program Mecklenburg County Water Quality Making a difference
4
Early Planning Process Master Plan Set in Motion after flooding in 1997; FEMA Buyouts 2000 Little Sugar Creek Master Plan adopted by BOCC 2004 Stakeholders Mecklenburg County Park & Recreation Charlotte-Mecklenburg Storm Water Services Funding Partners FEMA Buyout Grants Clean Water Management Trust Fund NCDOT Ped Grants NC Ecosystem Enhancement Program NC Division of Water Resources Charlotte DOT
5
WATERSHED / BASINS Little Sugar Creek Little Sugar CreekWatershed Collects East side of GreaterCollects East side of Greater Uptown Charlotte.Uptown Charlotte. Over 43% imperviousOver 43% impervious
6
Little Sugar Creek Watershed Overview Map Nine Projects in the Ground over Twelve Years.
7
Little Sugar Creek Watershed Project Reaches Hidden Valley Ecological Park Cullman Avenue Water Quality Enhancement Project 7 th Street Reach at Central Piedmont Community College Elizabeth Reach of the Little Sugar Creek Greenway Midtown Reach of the Little Sugar Creek Greenway Kings Drive Reach of the Little Sugar Creek Greenway Liz Hair Nature Trail Freedom Park Mitigation Project Westfield Environmental Restoration
8
Little Sugar Creek Hidden Valley Ecological Park Project Overview Drainage area 1.5 sq miles 3,500 LF and12 BMP cells Floodplain buyout 17 homes Project Goals Improve WQ Habitat Restoration Primary Sponsor: CMSWS with CWMTF Design date 2001-2002 Construction date 2003-2004 Construction Cost $3.1M
9
Little Sugar Creek Hidden Valley Ecological Park Site photos
10
Little Sugar Creek Hidden Valley Ecological Park Site photos
11
Little Sugar Creek Hidden Valley Ecological Park
12
Site photos
13
Little Sugar Creek Cullman Avenue Project Overview Drainage area 3.4 sq mi 1,100 LF and Bioretention BMP Project Goals Water Quality Enhancement Habitat Restoration Primary Sponsor: CMSWS Design 2010-2011 Construction 2011-2012 Construction Cost $260K
14
Little Sugar Creek Cullman Avenue
17
Little Sugar Creek Greenway Urban Reaches ELIZABETH REACH MIDTOWN REACH KINGS DRIVE REACH
18
Little Sugar Creek Greenway: Elizabeth Reach Project Overview Drainage area 10.2 sq mi 3,500 LF and BMP Pond Project Goals Habitat Restoration Water Quality Primary Sponsor: CMSWS Design 2007-2010 Construction 2010-2012 Construction Cost $450K
19
Site photos Little Sugar Creek Greenway: Elizabeth Reach
20
Little Sugar Creek Greenway: Midtown Reach Project Overview Drainage area 10.6 sq mi 3,500 LF and BMP Pond Project Goals Habitat Restoration Water Quality Primary Sponsor: CMSWS Design 2005-2007 Construction 2007-2008 Construction Cost $130K
21
Little Sugar Creek Greenway: Midtown Reach Before Demolition 1999 Aerial
22
Little Sugar Creek Greenway: Midtown Reach
24
Little Sugar Creek Greenway: Kings Drive Reach Project Overview Drainage area 11.5 sq miles 2,000 LF and Wetland BMPs Project Goals Habitat Restoration Water Quality Greemway Primary Sponsor: CMSWS Design 2006-2007 Construction 2008-2010 Construction Cost $1.35M
25
Site photos Little Sugar Creek Greenway: Kings Drive Reach 1999 Aerial 2005 Aerial
26
Site photos Little Sugar Creek Greenway: Kings Drive Reach
28
Little Sugar Creek Liz Hair Nature Trail Project Overview Drainage area 12.0 sq mi 3,400 LF Project Goals Habitat Restoration Primary Sponsor: CMSWS Design 2003 Construction 2004 Construction Cost $130K
29
Little Sugar Creek Liz Hair Nature Trail
30
Little Sugar Creek Freedom Park Mitigation Project Project Overview Drainage area 13.6 sq mi 4,400 LF Project Goals Mitigation Credit Primary Sponsor: NC EEP Design 2002 Construction 2003 Construction Cost $1.8M
31
Little Sugar Creek Freedom Park Mitigation Project
34
Little Sugar Creek Westfield Environmental Restoration Project Overview Drainage area 15.0 sq mi 5,200 LF and 7 BMP cells Project Goals Habitat Restoration Water Quality Greenway Primary Sponsors CMSWS, Park & Rec Design 2003 Construction 2004 Construction Cost $2.49M
35
Site photos Little Sugar Creek Westfield Environmental Restoration
36
Site photos Little Sugar Creek Westfield Environmental Restoration