Northwestern | Facilities
Key Performance Indicators 24 January 2019
2
Facilities Key Volume Indicators
Note: There was a change this month to subcategories for Number of Open Projects and Value of Open Projects. As a result the change in subcategories cannot be used this month to sum to the overall change.
3
Key Performance Indicators
Business Metrics will be included quarterly.
4
F1. Capital Project Cash Flow Execution
Measurement: Actual Expenses vs. Budget or F/C from 11/16 Note: The Projected Cash Flow Target is based off planned cash flow associated with the Capital Investment Priorities, not off-cycle capital projects. The December planned cash flow was $31.7 million. Actual cash flow for the month totaled $24.9 million. YTD cash flow of $86.9 million and YTD variance of $30.3 million under planned cash flow. The November planned cash flow was $36.0 million. Actual cash flow for the month totaled $13.4 million. YTD cash flow of $62.0 million and YTD variance of $23.8 million under the planned cash flow. KPI goal is to spend capital at a rate of +/-5% of committed capital cash flow plan f(timely contractor invoicing, unforeseen project conditions, accurate budgeting, scope changes, weather, institutional prioritization, accessibility to work areas/equipment) Initiatives: develop and implement process improvement; improve accuracy of cash flow plan; drive timely contractor invoicing; improve reporting; establish and execute project manager cash flow plan Facilities Leader: Liz Schaps
5
F2. Facilities Operating Budget Execution
Measurement: Cost vs. 3+9 Forecast for Dept. and Service Line We are still looking into how to include net position information. Fund 110 in December was ~$1.25 million over the forecasted expenses. The main driver of the overage was utilities billings (steam was over ~$660K, water/sewer ~$500K, and electricity $600K). There was duplicate billing for water/sewer that occurred in December, and the ~$500K in expense will be reversed next month. KPI goal is to spend Facilities division operating expenses at a rate of +/- 5% of budget f(accurate budgeting of Operations and Maintenance, Administration, Planning, Design and Construction, Sustainability, HR, campus growth, unanticipated factors) Initiatives: develop and implement process improvement; improve reporting; adhere to preventative maintenance plan; manage overtime expenses Facilities Leader: Liz Schaps
6
F3. Utility Budget Execution
Measurement: Cost vs. 3+9 Forecast (with overhead) Note the totals for September and October do not reflect the changes that will need to be made for the boiler decentralization/satellite boiler installation project. Totals include all intra-FM billings – double counts of gas, water and steam that are billed to CUP. KPI goal is to manage utility expenses with overhead at a rate of +/- 5% of budget f(accurate budgeting, utility commodity costs, campus growth, usage) Initiatives: adhere to sourcing strategy; improve reporting Facilities Leader: Liz Schaps
7
F4. Invoices: Number of Days to Pay
Measurement: Average Days to Pay December 2018: Paid Within 30 Days: 72.3% Paid 30 to 45 Days: 9.3% Paid 45 to 60 Days: 4.7% Paid 61 to 90 Days: 4.9% Paid Over 90 Days: 8.8% KPI goal is to process 90% of invoices from receipt to voucher/ACH within 30 days f(accurate invoicing, Facilities timely invoice processing, accounts payable, staffing ) Initiatives: develop and implement process improvement; improve reporting Facilities Leader: Liz Schaps
8
OE1. Preventive Maintenance work as Percent of Total Closed Work Orders
Measurement: Monthly; Preventive Maintenance W/O as percent of Total Completed Work Orders As of 1/11/18 5,848 open service work orders 2,658 open standing work orders KPI goal is to have a yearly average of 35% of our work orders closed be preventative maintenance tickets f(service work orders, preventative maintenance work orders) Initiatives: expand the preventative maintenance program to more shops, eliminate the use of standing work orders, revise task instructions, optimize work order frequency Facilities Leader: Samantha Westerhof
9
OE2. Recordable Injury Incident Rate (TRIR)
Number of Injuries Dec: 0 YTD: 9 Measurement: OSHA Definition KPI goal is to reduce OSHA Recordable Injury Incident Rate by 20% from prior year rate f(equipment, training, behavior, personal protective equipment use) Initiatives: inspect equipment and environment; manage personal protective equipment inventory; track personal protective equipment use; train staff; enact monthly safety talks, near miss incident program, hearing conservation program Facilities Leader: Rachel Gunn
10
OE3. Injury-Related Lost Workday Rate
Measurement: Days away, restricted, or transferred per 100 full time employees KPI goal is to achieve an injury-related lost workday rate of less than 1.34 lost workdays (days away, restricted, or transferred) per 100 full time employees f(equipment, training, behavior, personal protective equipment use) Initiatives: inspect equipment and environment; manage personal protective equipment inventory; track personal protective equipment use; train staff; enact monthly safety talks Facilities Leader: Rachel Gunn