Download presentation
Presentation is loading. Please wait.
Published byKároly Zsigmond Németh Modified over 5 years ago
1
LCLS Global Controls Overview August 10, 2004
Goals Status update Resources / Budget Design Slides for Global Systems Task descriptions Next 12 months Conclusions
2
LCLS Control System Goals
Provide a fully integrated control system to support the construction, test, installation, integration, operation and automation of the LCLS Accelerator Standardize on all devices and components across all subsystems. Identify all data either by pulse id, beam pulse related time stamp, or 500 msec rough time stamp. Full integration with the SLC – timing, use of LCLS data in SLC high level applications, and use of SLC data in LCLS Work with SLAC Control System Departments to provide an upgrade path for the SLC Philisophy is to build new designs only when we cannot find a solution commercially or at other laboratories.
3
Progress: May 2004 – August 2004 Most Physics Requirements Documents Completed In Progress ESD LCLS Control System Requirements DONE PRD LCLS Controls Feedback Requirements (to be signed) PRD LCLS Timing System Requirements (to be signed) PRD LCLS High Level Software Application Requirements (to be signed) PRD LCLS Electron Beam Diagnostics Requirements (to be signed) PRD LCLS Personnel Protection System Requirements (to be signed) PRD LCLS Machine Protection System Requirements (to be signed) PRD LCLS Control Room Requirements DONE PRD LCLS Beam Position Measurement System Requirements Completed technical review of the Global Control System (FAC) Began development on the SLC-aware IOC Began development of the PNET timing hardware required Recruitment of critical personnel Dayle Koturri, Stephanie Allison, Till Straumann, Kristi Luchini, Linda Hendrickson, Chris Allen Mario Ortega, Matt Stettler, John Power, John Dusatko, Timo Korhonen Completed a management review of the Global Control System (EIR)
4
Budgeted Cost of Work Scheduled
Manpower and Equipment Budget for LCLS controls is adequate Manpower is heaviest design and development in ’05 and ’06 Procurement is heaviest in ’06 and ‘07
5
Integration with the SLC Control System
Alpha All High Level Apps EPICS W/S Distributed Applications EPICS W/S Distributed Applications Xterm EPICS W/S Distributed Applications Xterm Xterm EPICS W/S Distributed Applications Xterm EPICS WS Distributed High Level Applications SLC Net (Data Communication) KISNet (fast closed loop control data) PNet (Pulse ID / User ID) MPG Ethernet (EPICS Protocol) micro E V G Micro emulator I/OC (SLC-aware) Design Provides: SLC Data available to EPICS EPICS data available to SLC PNET timing info into EPICS Camac I/O RF reference clock
6
Global Buses Meet LCLS Requirements
EPICS W/S Distributed Applications SLC Alpha Apps EPICS W/S Distributed Applications EPICS W/S Distributed Applications Xterm Xterm EPICS W/S Distributed Applications Xterm Xterm EPICS WS Distributed High Level Applications Fast Feedback over Ethernet? SLC-Net over Ethernet Channel Access over Ethernet C P U E V G E V R LLRF HPRF I/O Boards C P U E V R Diag C P U E V R Pwr Supply Ctrl C P U Vacuum Ctrl IOC IOC IOC 16 triggers 16 triggers Drive Laser Off Single Bunch Beam Dumper Machine Protection Beam Code + EPICS Time + EPICS Events
7
First Article Delivery Dates
May RF Conditioning start – injector Timing LLRF Vacuum Gateway operational from Alpha to EPICS August 06 - First UV on cathode Power Supply Control BPMs and Wire Scanners Personnel Protection – Injector Area May First Beam on Linac Axis SLC aware IOC June Start Undulator Commissioning Machine Protection System Personnel Protection – LTU and Undulator Area
8
Organizational Chart – Draft TBD’s are mostly identified
John Galayda – Project Director Mark Reichenadter – Chief Engineer Steve Milton – ANL Project Director Richard Bionta – LLNL Project Director Technical Coordination TBD – Global Controls Leader 1.1.3 Bob Dalesio – Control System Design 1.1.3 Patrick Krejcik – Controls Physicist Helen O’Donnell – Administration Jeff Chan – Finance/Cost/Budget/Schedule Ian Evans – ES&H, QA, Documentation Chris Jamison - Procurement 1.2 Injector Manager Dave Dowell 1.2.2 Controls Dayle Kotturi 1.3 LINAC Manager Eric Bong 1.3.2 Controls Dayle Kotturi 1.4 Undulator Manager Steve Milton 1.4.2 Controls Joshua Stein 1.5 XRay ODT Manager Richard Bionta 1.5.2 Controls TBD 1.6 End Station Manager John Arthur 1.6.2 Controls TBD 1.9 Building Manager D. Saenz 1.9.2 Controls TBD SLC Integration Stephanie Allison Dave Brown (PNET Board) Timing Kristi Luchini TBD Power Supplies LLRF Team Ron Akre TBD Dayle Koturri MPS/BCS/PPS TBD E1 TBD E2 TBD E3 High Level Applications Linda Hendrickson TBD - Prog RDB - TBD Sys Admin – TBD Diagnostics Team: TBD E1 TBD E2 TBD E3 Till Straumann Zen Szalata Josh Stein (APS) Vacuum/Thermal Mauro Gianchini Low Level Applications Till Straumann Installation / Wire Plant Mario Ortega TBD T1 TBD T2 TBD T3 TBD T4
9
Risks / Issues Acquire Control Team Minimize the number of solutions across injector, linac, undulator, XRay beamline transport, end stations, and facility control Provide timing, LLRF, BPMs, and power supply control hardware by in FY06 Provide SLC integration in FY07
10
Next 12 Months Acquire team and contract out or steal designs
Prototype/test: PNet, Timing, LLRF, Power Supply Control and BPM efforts SLC-Aware IOC Development Prototype for video diagnostics Prototype for position controllers Integrate Facility Controls, XRay Transport, Experimental Hall into the control system. Complete the detailed designs per subsystem
11
Conclusions Physics requirements are complete.
Engineering specifications derived from them and a technical review of the global control system has been completed. Baseline budget adequately supports the design. Our key risks are: Implementation of an SLC-aware IOC and SLC to EPICS timing that will allow us to intermix the SLC and EPICS front-ends Hardware acquisition/development for BPMs, Timing, Power Supply Control, and LLRF in FY06 We need to acquire some key resources to get the critical designs well in hand before they are needed.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.