ESS MEBT Quadrupole magnets

Similar presentations


Presentation on theme: "ESS MEBT Quadrupole magnets"— Presentation transcript:

1 ESS MEBT Quadrupole magnets
J.L. Muñoz Bilbao, 27 March 2019

2 ESS MEBT Quads – Bilbao, 27 March 2019
Contents Quads requirements and specifications Tender/fabrication process review Design details Magnets characterization Box Incident Power supplies Some simulations Conclusions ESS MEBT Quads – Bilbao, 27 March 2019

3 MEBT line includes 11 quadrupole magnets, with integrated dipolar correctors
All magnets share the same design and are identical, although operating gradients and F/D characteristics depend on position in line

4 Quadrupole magnets requirements
Relevant documents in CHESS: MEBT Quadrupole magnet TDR Quad main drawing Quads DOORS L4 check Characterization of pre-series magnet

5 Tender and contract timeline
24Feb2016: PDR at Bilbao. Preliminar design presented Comments and improvements noted 19Sep2016: Tender process launched Based on PDR design + L4 + improvements 1+10, pre-series thorough characterization 13Feb2017: Contract awarded to Danfysik 25Apr2017: Kick-off meeting (admn. delays) 01Jun2017: PDR #1 (based on 3D model) 14Jun2017: PDR #2 (based on 3D model). PASSED.

6 Tender and contract timeline
01Ago2017: First set of documentation for FDR (drawings, assembly prodecures, cable sketches) 06Oct2017: Final set of documentaion for FDR 17Oct2017: FDR PASSED, with actions open 08Feb2018: First measurements of pre-series magnet Concerns on: Center-height of magnet (corrected) Mechanical-magnetic axis offset 16Apr2018: All measurements of pre-series magnet accepted, magnet sent to ESS-Bilbao premises. 02May2018: Pre-series magnet arrives at ESS-Bilbao (magnet 1/11)

7 Tender and contract timeline
11May2018: Local tests ran, report issued Visual inspection issues (labels, weldings) IP2X cover Magnet accepted with minor corrections for series 03Oct2018: Fabrication and tests for next set of 4 magnets, delivery after data package is accepted. 11Oct2018: Reception of 4 magnets (2-5/11) 08Nov2018: Incident with transport of remaining magnets. New assembly, tests and correction actions 14Dec2018: Final data package for incident magnets 21Dec2018: Magnets arrive to ESS-Bilbao (6-11/11)

8 Tender and contract timeline
(Data package)

9 Design details

10 Design details Pole tip design

11 Design details Coils

12 Design details Coils

13 Design details Mechanical

14 Design details Mechanical (Industeel XC-06)

15 Design details Mechanical

16 Design details Mechanical

17 Characterization Documentation available for all magnets
More than 600 files and 600 Mb of data

18 Pre-series magnet Tests done at Danfysik

19 Pre-series magnet Dimensional check

20 Pre-series magnet Thermo-switches tests (2 per coil) All coils tested:
Dimensional control, resistance, insulation Before and after impregnation Pdf docs of all tests documents sent

21 Pre-series magnet After opening+assembly (3 times)

22 Pre-series magnet Complete magnet test document
Visual inspection (paint, brazing, screws,photo) Dimensions Coil numbering Dissasembly/assembly test Resistance, insulation, hydraulic leak Full power test (250A+steerers 6.6A, during 1 hour)

23 Pre-series magnet Complete magnet test document

24 Pre-series magnet Target position and mech-mag offset doc

25 Pre-series magnet Target position and mech-mag offset doc
“Resistance based” measurements: Offset is measured in the SW bench First, magnetic center is found Then wire is moved in X and Y steps until electric contact is detected This measures mechanical aperture Process is repeated for all poles, and overall offset computed

26 Pre-series magnet Excitation curve measured with Hall probe

27 Magnetic measurements
Integrated gradient and hamonics Measured with SSW device, rotating a wire in a 19.5 mm radius circle, evaluating at 15.0 mm radius Higher order harmonics are measured for different quadrupolar and dipolar coils excitation Excel files of all measurements provided

28 Magnetic measurements
Summary of results, extracted from raw data

29 Magnetic measurements
Summary of harmonics measured at I=10A (L4<1 %)

30 Magnetic measurements
Summary of harmonics at I=250A (L4 < 1%)

31 Additional tests Local tests: one of the magnets was measured in CFAA (UPV/EHU) facility (Model built with poles interpolated from metrology)

32 Box incident On 1/11/18 Danfysik reported an incident with the box containing the last batch of six magnets

33 Box incident The box contained magnets numbered 17034, 17035, 17036, 17040, and A comparison of measurements (pole gap and shoulder) after reassembly was done. Problems (values worse than previous ones) found in three magnets (17035, and ). In particular, magnet presented values which are outside the required tolerances according to magnet specification. Magnet stands were also slightly bent from the laterals. Danfysik pointed out that this could be corrected when bolting the stand to the magnet support, straightening the stand this way.

34 Box incident The strategy that was devised to cope with this was to:
1. Start with the operation of opening/closing of the magnet. 2. Repeat all complete measurements of the magnets. 3. Deliver an updated complete data package for each magnet. ESS (JS) was informed and participated in all Skype meetings between ESS-Bilbao and Danfysik

35 Box incident 17034 17035 17036 17040 17043 17044 Just after box incident Before opening After opening After 1st opening After 2nd opening time

36 Box incident Some correction was needed for magnet # The foot was re-machined and this has corrected the mechanical problems. After receiving all mechanical and magnetic measurements, we have found that all magnets are within specifications and that there is no significant difference between magnets before and after the incident. Anyway, this delayed quite a bit the magnets delivery to Bilbao

37 Simulations Extensive simulations activities have also been done

38 Power Supplies

39 Conclusions 11 magnets were build and tested
All magnets are within L4 requirements All mechanical restrictions (BPM, length, etc) are also met Fabrication has suffered several delays and incidents All the documentation has been collected and sent