1
InfoWorks CS Enables Design of Hybrid Pressure/Gravity Sewer Systems
2
Background InfoWorks CS has been used for the functional design of proposed residential and industrial hybrid sewer systems. Pipeline sizing, pump selection and storage requirements were all determined using InfoWorks CS. The aim of today’s presentation is to show how the dynamic modelling capabilities of InfoWorks were utilised in functional design.
3
Agenda Definition of Hybrid System Advantages of using InfoWorks CS
Case Study 1: Yarra Valley Water – Wonga Park Case Study 2: Barwon Water – Industrial Estate Conclusions Questions / Discussion
4
What is a Hybrid System ? GRAVITY SEWER PRESSURE SEWER
5
Advantages of Using InfoWorks CS
Allows both analysis of pipe-full flow and part-full flow, so that pressure pipes and impacts on gravity systems can be assessed in one model. Integration with existing gravity system models. Data import / export tools Pump controls Reporting tools
6
Case Study 1: Wonga Park Yarra Valley Water
Existing residential area currently not sewered. Approximately 500 properties with a mix of gravity connections and pressure pump units Area is low-density with lot sizes approximately 4000 sq m
7
Modelling Issues Considered
In addition to the usual design criteria the following issues were considered in modelling: Initial starting conditions Headloss in property connections and sensitivity analysis considering varying lot control requirements Peak flows generated from the system upon resumption of power following a prolonged outage
8
Initial Starting Conditions
9
Random Initial Starting Conditions (Reality)
11
Uniform Initial Starting Conditions
12
Uniform Initial Starting Conditions
14
Applying Random Starting Conditions
15
Applying Random Starting Conditions
16
Allowance for Headloss in Property Connections
Wonga Park has very large lots with steeply sloping topography and potentially long property connection pipes. To improve the efficiency of the model, property connection pipes were not modelled, however the headloss was still allowed for.
17
Hydraulic Grade Line Outlet Property Connection Friction Head
Static Head Property Connection
18
Static Head Taken into account by ensuring the pump well levels and pump cut in/cut out levels are accurate
19
Friction Head Allowed for by subtracting friction loss from pump curve
22
Consideration of Property Control
24
Consideration of Property Control
Solution: two models Partial Lot control – pump levels and pump curve based on location of existing property Full Lot control – pump levels and pump curve based on worst case
26
Power Outage Scenarios
27
RTC Rules
28
Typical Flows
29
Depth to Spill
31
Summary Random initial tank level created using inflow hydrograph
Pump curves and pump levels altered to account for headloss in property connections Two models built to consider different lot control scenarios RTC utilised to model power outage scenario and report on freeboard to spill
32
Case Study 2: Industrial Estate – Barwon Water
64 Properties. Each with own pressure pump discharging to gravity sewer. Two main catchments each discharging to an outfall pump station GRAVITY SEWER
33
Issues Considered Sizing of gravity pipe
System requirements to cater for peak flows following a power outage
34
Pipeline Sizing Barwon Water recognised the importance of dynamic modelling in determining pipe sizing given that: Under normal operating conditions only a small number of pumps operate simultaneously However there are circumstances where pumps can operate simultaneously. Pipelines were sized based on the flows and velocities predicted by InfoWorks CS, considering usual design criteria
35
Results
36
Results
40
Power Outage Scenario Differences from Case Study #1
All pumps discharge into gravity sewer, there is no head restriction limiting pump operation at the resumption of power. Discharge rates are potentially higher – potential for inflow volume to exceed tank volume during a prolonged power outage
41
Node Spill Model Where the wet well is predicted to fill during a power outage it is important to consider the node spill model adopted for the node representing the pressure pump well. Two applicable options: Lost Stored
42
Lost Once the node representing the pressure pump well fills any additional flow is lost from the system.
43
Stored Once the pressure pump well fills any additional flow is stored and is returned to the system as the well empties.
44
Lost vs Stored – Difference in Results
46
Which Spill Model to Adopt ?
Requires understanding of: Likely operation of customers Rules applied to customers For example, if customers don’t have additional storage, the lost model would be more appropriate.
47
Summary Barwon Water recognised the importance of dynamic model in the efficient design of a hybrid system. InfoWorks CS was used to determine peak flows and size pipelines. The different node spill models available in InfoWorks allow the modelling of different operational scenarios following resumption of power. Modelling of the power outage scenario enabled additional storage requirements to be determined.
48
Conclusions The following aspects of the functional design of hybrid sewer systems were modelled using InfoWorks: Hydraulic analysis of both part-full flow and pressurised pipes allowing pipeline sizes to be determined Randomisation of initial starting conditions Variable lot control scenarios System outflows following a power outage and associated storage requirements Consideration of various system operating scenarios by use of a choice of node spill models.
49
Acknowledgements Yarra Valley Water – Chris Saliba
Barwon Water – Mircea Stancu
50
Questions / Discussion