ESS RFQ CEA CONTRIBUTION 19/03/2019

Similar presentations


Presentation on theme: "ESS RFQ CEA CONTRIBUTION 19/03/2019"— Presentation transcript:

1 ESS RFQ CEA CONTRIBUTION 19/03/2019
Chauveau Anne-Catherine /03/2019

2 Overview of CEA WP content
TABLE OF CONTENT Overview of CEA WP content WP content Tenders status RFQ status Part list Documentation Non conformity Review of installation Plan changes CEA installation planning CEA installation team CEA installation team planning CEA tools requirements CEA services requirements CEA installation RAM Transportation 19/03/2019 RFQ IRR

3 OVERview of WP content 19/03/2019 RFQ IRR

4 CEA WP CONTENT Partial RFDS system Conditioned RFQ on it’s support
5 RFQ sections Partial RFDS system Pick-ups (x22) Tuners x60 Cooling system SKID and Control PLC Power couplersx2 Cooling plates x80 RFQ support Conditioned RFQ on it’s support MAIN Requirements: Bunch the proton beam at the frequency of MHz Accelerate the beam from the exit of the source from 75 keV up to 3.6 MeV Pulsed operation at 4% duty cycle Transmission > 90% 19/03/2019 RFQ IRR

5 CEA TENDERS STATUS Almost 30 tenders and numerous orders.
4 tenders still on-going Part Company Copper Carlier 5 RFQ sections Mécachrome (MKA) RFQ auxiliaries (brazed on the RFQ sections) Atelier Mécanique de Deuil (AMD) 60 tuners ACE 3 Power couplers PMB 28 pick-ups Solcera IO plates RFQ support MGR, DKER, Court SA, Sermo Mécanique Sections Transport chassis RFDS support Sominex Bead-Pull instruments COURT, SEL, Sominex RFQ cooling system (SKID + soft hoses) Technitub Various assembly/tests tools Various tenders Miscellaneous (blank flanges, seals, screws…) Various orders Tender on-going Tender closed 19/03/2019 RFQ IRR

6 At Saclay CEA RFQ STATUS TODAY 1/2
3 power couplers received – Leak tested – Conditioned. At Saclay RFDS support received – Assembly done 60 tuners received – Partial Leak & assembly test RFQ support received – Assembly done. 19/03/2019 RFQ IRR

7 S1 assembled on RFQ support
CEA RFQ STATUS TODAY 2/2 S1 Brazing at Annecy S1 after brazing Section 1 delivered at CEA – tested – assembled. Section 2 delivery due today. Section 3 brazed – BP2 done – 1st Leak test done. Section 4 on-going machining. Section 5 on-going machining. S1 assembled on RFQ support At Saclay 19/03/2019 RFQ IRR

8 CEA WP Part list FBS with associated documents (on-going)
19/03/2019 RFQ IRR

9 360 files sent already CEA DOCUMENTATION General documentation
General documentation Design (Blue prints - 3D) Manufacturing (FAT - Materials) Assembly and integration Test at Saclay Materials and Conformity reports RFQ_SUPPORT na Need translation RFQ S1 (leak) S2-S5 S1 POWER_COUPLERS TUNERS On-going PICK-UPS IO_PLATES RFDS_SUPPORT Delivered Needed for installation Not yet available at Saclay na Not applicable 19/03/2019 RFQ IRR

10 NON CONFORMITIES Criticity L1, L2, L3 Author date Description
Component Piece ID L2 ACE déc-17 Tuner seizure UAC QB-1001 Tuner UAC QB-1001 L1 CEA juil-17 Power couplers seals – not adapted support on pick-up coupler Coupler NA nov-17 Drilling through for hydraulic channels S1-S2-S3 work anticipated before mock-up delivery RFQ S1-S2-S3 MKA juin-18 Section 1 right minor vane too short. => vane discarded D1 Section 1 left minor vane missing copper on vane => vane discarded G1 Section 1 low Major vane drilled through not reusable => vane discarded B1 janv-18 Section 1 low Major vane: drill broken in pick-up port repaired by electro erosion. => vane discarded H1 juil-18 Section 1 low Major vane: snached copper on vane because of programming error. => vane discarded Section 2 right minor vane: increase of the diameters for tightening rods for brazing and pins. D2 avr-18 Section 2 high Major vane: Increase of the “big circle” diameter. H2 août-18 Section 1 left minor vane: shift of the cooling plates fixings + specific plates. oct-18 Shift of the relaxing groove for the specific cooling plates on section 1 left minor vane + Impact on the vane discovered during assembly. S1 PMB Swagelock connector leaking repaired then replaced Couplers All sept-17 Few dimensional deviations before assembly of power couplers. L2? New: Impact on the outside of section 2 New: Impact on the section vane end S2 19/03/2019 RFQ IRR

11 Review of INSTALLATION
19/03/2019 RFQ IRR

12 Installation changeS (1/2)
ESS RFQ Installation change: Regarding RFQ sections manufacturing, ESS requested CEA to optimise the delay for delivery. A new scenario was presented by CEA and chosen by ESS end of November 2018. Main impacts of this change: Less than 3 months for IRR preparation Only 3 sections assembled at CEA (2 others sections will be delivered with no previous assembly tests.) No tuning of the RFQ prior to delivery in the tunnel. First delivery in Lund happens before the RFQ tender is closed, therefore main documentations from manufacturer is not yet available. Installation scope is described in Installation Binder. 19/03/2019 RFQ IRR

13 Installation changeS 2/2
ESS RFQ Installation change 2: An other change compared to what was initially planned is the fact that the drop hatch is not available for downloading the equipment. Therefore it was decided that ESS would handle the necessary tooling needed to download the RFQ girder in place. ESS RFQ Installation change 3: Last modification to the installation plan is the unavailability of the Tungalift. All the procedure was initially worked on with the assumption of Tungalift used for lifting. This has been replaced by use of forklift trucks handled by ESS operators. 19/03/2019 RFQ IRR

14 CEA Installation PLANNING
T0 depends on the arrival of section 3 at Saclay and on the readiness of ESS tunnel, tools, services and beam. Actual Planning foresees transport end of April with arrival beginning of May. Detailed planning in Installation Binder. Detailed installation sequences follow in dedicated presentation from A. Dubois 19/03/2019 RFQ IRR

15 CEA Installation TEAM CEA contact Function Bruno POTTIN
RFQ WP project leader Anne-Catherine CHAUVEAU RFQ WP project leader deputy Augustin DUBOIS RFQ WP Installation responsible Gabrielle PERREU RFQ WP Installation responsible deputy Olivier PIQUET RFQ WP Instrument scientist and RF expert Alain FRANCE Bead-Pull measurement expert Pierrick HAMEL Yannick LE NOA Bead-Pull control expert Michel DESMONS Conditioning and RF expert Didier CHIRPAZ-CERBAT Vacuum responsible Maryam OUBLAID Vacuum responsible deputy Nicolas MISIARA Coupler Mechanical engineer Yannick SAUCE Hydraulic technician 19/03/2019 RFQ IRR

16 CEA Installation TEAM PLANNING
Detailed team planning in installation binder. Dark green mandatory. 19/03/2019 RFQ IRR

17 CEA TOOLS REQUIREMENTS LIST
Before arrival Downloading Girder installation S1 installation S1 alignment S1 equipments S1 leak tests S2 Assembly S2 leak tests S3 Assembly S3 leak tests S4 iAssembly S4 leak tests S5 Assembly S5 leak tests BP tool and tuners ass BP1 fingers Coupler assembly Coupler leak tests BP2 cpl + tuners Hard pipes assembly RFDS assembly ESS vacuum ass&test BP3: Final BP Final leak test Soft hooses After work duration 1d 0.5d 1,5d 2,5d 2.5d 2d 3d 5d 2d  10d date Support feet fixing rods Plastic indicator strips dumpsters offices with an internet acces changing rooms lockers strong table   few chairs  Electric sockets RBS and alcoohol 1 forklift truck (fenwick type) or Tungalift crane 1 forklift truck operator or Tungalift crane operator chain host (non electric) 3 wood Pallet  800*1200 Wood blocs Slings 1 hand pallet truck Mobilev Mobilev operator leak detection equipment with primary pump Helium Nitrogen water buckets Compressed air 2 table for the laptops Detailed tool list in installation binder. 19/03/2019 RFQ IRR

18 CEA SERVICES REQUIREMENTS LIST
Before arrival Downloading Girder installation S1 installation S1 alignment S1 equipments S1 leak tests S2 Assembly S2 leak tests S3 Assembly S3 leak tests S4 iAssembly S4 leak tests S5 Assembly S5 leak tests BP tool and tuners ass BP1 fingers Coupler assembly Coupler leak tests BP2 cpl + tuners Hard pipes assembly RFDS assembly ESS vacuum ass&test BP3: Final BP Final leak test Soft hooses After work duration 1d 0.5d 1,5d 2,5d 2.5d 2d 3d 5d 2d  10d date marking of the feet dirty work finished RFQ zone in the tunnel cleaned instal. enveloppe: LEBT commissioning tank removed Waves guides connected o the wall ESS teams and equipment for downloading No dust (area protected and over pressured) no working in this part of the tunnel site should be secured Electric sockets humidity level of up to 75% ESS surveyor alignment equipment ESS vacuum system ESS vacuum team leak detection equipment with primary pump Test envelope: LEBT solenoid and diag. removed 15˚C to 27˚C temperature change of 5˚C per 24 hours no vibrations Workshop for tube cutting Space and transport in RATS of remaining equipment Detailed service list in installation binder. 19/03/2019 RFQ IRR

19 CEA INSTALLATION RISK (RAM)
No. Activity Hazard Who might be harmed and how? Action to Mitigate Risk- Controls  Residual Risk Rating   S L Risk 1. Girder installation Lifting of heavy objects - Falling objects Manual handling Everyone around Mandatory PPE on site - Correct installation of tools Min resources around - Fencing of work area 5 1 M 2. TungaLyft installation Rolling object Lifting Mandatory PPE on site - Min resources around Signaling of work area 2 3. Section X installation Lifting - Manual handling - Moving Mandatory PPE on site -Min resources around 4 4. Section X equipment assembly Manual handling - Hand crushing - Back/muscle strains Mandatory PPE on site 15. Wave guide support installation Rolling object - Hand crushing - Work at height Mandatory PPE on site - Platform 16. Couplers installation Manual handling - Work at height- Back/muscle strains Platform 17. Helium leak tests Inert gas, pressure Everyone around work Correct storage ? 18. Cleaning of parts Chemical hazard/Waste generation Gloves - Waste management 20. Box opening Cut from utility knife/scissors Falling objects 21. Tripping on objects on the floor Waste management 22. Connection of utilities (power for gauges and pumps) Electrical hazard - Tripping on cable Cable management - Electrical management Main risk is handling of heavy equipment No Hot-work No cutting No Electrical work (except plugging laptops, BP and cooler) Document Risk Assessment and Method Statement in installation binder. 19/03/2019 RFQ IRR

20 CEA TRANSPORTATION SPECIFICATION
One Dedicated standart truck with very extremely careful handling for RFQ sections and Power couplers (shock sensors, air suspension…) A second standart truck for all other equipment. Box dimensioning and weighting is still on-going. Some boxes are still under manufacturing. Document needs further working….. Draft document in installation binder. 19/03/2019 RFQ IRR

21 CONCLUSION In order to assemble the RFQ, all the tools and services listed in the document 05_RFQ_Lund_Installation_requirements.pdf in Binder 06 need to be ready and available. Even though conditioning is not part of this review, the beam should be characterised before the RFQ is connected to the LEBT. If the beam is not characterised, if any issues arises during commissioning it will be very difficult to know if the problem is on the BEAM or on the RFQ. CEA will come for a pre-visit of the tunnel state about 10 days before the departure of the RFQ from CEA. 19/03/2019 RFQ IRR

22 Thank you for your attention