V12.00.00 Retail Market Release (ROI & NI)
Detailed Co-Ordinated Cutover Plan – Walkthrough Thursday 4th April 2019
2
Agenda Topic Element Organisation Presenter Intro Intro & Status RMDS
Lindsay Sharpe Coordinated Cutover Plan Overview Detailed Walkthrough Key Considerations Schema Upgrade Self Service Re-Fresh ATOS Enda Maguire IPT Lessons Learned Hyper Care Hyper Care Arrangements Patrick Moran Post Cutover Eircode Batch Update Process Market Documents Publication Summary AOB, Q&As All
3
Retail Market Release v12.00.00 (ROI & NI) Update
Thursday 4th April 2019
4
Market Release V12.00.00 – Scope
MCR Description Status MCR0175 New Reject Reasons for Address Change Rejection MCR1173 Vulnerable Customer Implementation in ROI of SI 463 MCR1167 Facilitate energy efficiencies in Local Authority Public Lighting MCR1140 Introduction of Eircodes into the Retail Market Design in Ireland MCR1169 Addition of Postal Code to two Downloadable Meter Point Details Files MCR1175 Provide Market Participant Business Reference (MPBusinessReference) for Reading MCR1180 New Registration Default Supplier MCR1184 Cooling Off for COS CoBLCR015 New RM Code MCR1183 010 Customer Validation Agreement (NI) MCR1154 New Unmetered Tariff for NI (NI) Other (ROI Only) Comment Status Smart Enablement SAP IS-U Enhancement Pack (8.0) SMART Enablement for Meter Installation SAP Hana
5
Market Release v.12.00.00 (ROI & NI) - Plan
2018 2019 Q1 Q2 Q3 Q4 16th 7th 7th 4th 3rd 30th 27th 25th 29th 3rd 13th 5th Dec 16th Jan 6th Mar 1st May 26th June Publication of v Schema Mon 28th Jan (ROI & NI) - Design/Build/Test Final RA Engagement IPT Prep IPT Exec Go Live Easter 2019 v Go live Aug B/H Other (ROI Only) Market Assurance Unicode Conversion SAP Hana Go Live Easter 2019 SAP IS-U Enhancement Pack (8.0) Go Live Easter 2019 Smart Enablement for Meter Installation Go Live Easter 2019 Market Engagement Apr 2019
6
Market Release V12.00.00 (ROI & NI) – Status
IPT IPT Execution Completed – Friday 15th March 2019 IPT Exit Reports issued to RAs – Friday 5th April 2019 No concerns raised by Market Assurance bodies based on outcome of Market Assurance Engagement Co-Ordinated Cutover Co-Ordinated Detailed Cutover Plan published via ReMCoDS Friday 29th March Schema Instruction Guides (Cutover and Rollback) shared by ATOS – Wednesday 3rd April 2019 Cutover Workshop with Market Participants – Thursday 4th April 2019 Cutover/Go-Live Final RA engagement prior to Cutover – Monday 8th April (ROI & NI) Cutover Commences Thursday 18th April (ROI) & Friday 19th April (NI)
7
Cutover Weekend - Overview
V12.00 Retail Market Release – Co-Ordinated Cutover (ROI &NI): The Cutover weekend schedule will be managed through a detailed list of planned tasks that will progress through a number of key milestones along the way Critical Cutover activities involving ESB Networks, NIE Networks, ATOS and all Market Participants are planned over the course of the weekend including: Message Reconciliation activities pre Outage Self Service EMMA Schema upgrades MP Backend system updates A co-ordinated and aligned Cutover approach is critical to ensure a successful outcome All communication between ESB Networks, NIE Networks and Market Participants throughout Cutover Execution will be managed via ReMCoDS
8
When will it happen? Cutover will be take place over four distinct stages: In Month Before (i.e. Up To Fri 12th Apr) 2. Week Before (i.e. Mon 15th Ap – Thu 18th Apr (ROI)/Fri 19th Apr (NI)) 3. Cutover Weekend (i.e. From Thu 18th Apr (ROI) and Fri 19th Apr(NI) Until Mon 23rd Apr) 4. Post Cutover
9
Tasks – In Month Before Key Market Tasks Additional Notes:
START FINISH JURISDICTION RESPONSIBLE 1 Market Participants confirm their availability for the agreed EMMA upgrade slot. Mon 08/04/19 09:00 Mon 08/04/19 17:00 Coordinated All MPs Additional Notes: Market Participants (ROI & NI): Market Participants to ensure any Business continuity mechanism is in place for Outage MPs submit any queries on v12 Schema Self Service pack to ATOS by – Friday 12th 17:00 ReMCoDS Each MP will be provided their respective SFTP login details to download their Self Service pack – Monday 8th April RMDS website - v Detailed Cutover Plan on RMDS website
10
Tasks – Week Before Key Market Tasks 2
# KEY MARKET TASKS START FINISH JURISDICTION RESPONSIBLE 2 MPs to complete MM reconciliation on a daily basis up to cutover(ROI) Thu 11/04/19 09:00 Thu 18/04/19 10:00 ROI ROI MPs 3 MPs to complete MM reconciliation on a daily basis up to cutover(NI) Fri 12/04/19 09:00 Fri 19/04/19 10:00 NI NI MPs 4 ReMCoDS receive final confirmation of all MP contacts for cutover weekend Mon 15/04/19 09:00 Mon 15/04/19 17:00 Coordinated ReMCoDs 5 MPs to stop requests for De-Energisations (ROI and NI) All MPs RMDS website - v Detailed Cutover Plan on RMDS website
11
Cutover Weekend – Plan on a Page
……. 8 AM 9 AM 10AM 12PM 6 PM 7 PM 8 PM 9 PM 10 PM 11PM …. Thursday18th Friday 19th Saturday 20th Sunday 21st Monday 22nd System Isolation - RoI System Isolation - NI 2 4 1-5 Pre-Cutover Tasks 6 7 19 Central Hub Update Suppliers Apply V12 Schema 5 7 Point of No Return 8 9 Supplier STOP MM / RoI 6 Supplier STOP MM / NI 11 NI SUPPLIER – 602 Reconciliations 3 10 13 RoI SUPPLIER – 602 Reconciliations Cutover Completed 12 1 8 Key Market Task - (KMT) Key Market Milestone – (MS) RMDS website - v Detailed Cutover Plan on RMDS website
12
Tasks – Cutover Weekend
Key Market Tasks (Thursday 18th April) # KEY MARKET TASKS START FINISH JURISDICTION RESPONSIBLE 6 Mandatory confirmations of completed reconciliations required via (ROI) Thu 18/04/19 10:00 ROI ROI MPs 8 Stop sending Market Messages 18:00 hrs (ROI) No further MMs until confirmation of resumption of Services Thu 18/04/19 18:00 Mon 22/04/19 23:59 10 MPs commence reconciliation on receipt of 602 (ROI) Thu 18/04/19 21:00 Thu 18/04/19 22:30 12 MPs confirm to ReMCoDS that reconciliation is complete (ROI) 14 Milestone 1 - Reconciliation is complete (ROI) ReMCoDs RMDS website - v Detailed Cutover Plan on RMDS website
13
Tasks – Cutover Weekend
Key Market Tasks (Friday 19th April) # KEY MARKET TASKS START FINISH JURISDICTION RESPONSIBLE 15 Milestone 2 - Confirmation of Central Market Systems isolation complete (ROI) Fri 19/04/19 08:00 ROI ReMCoDs 7 Mandatory confirmations of completed reconciliations required via (NI) Fri 19/04/19 10:00 NI NI MPs 9 Stop sending Market Messages 18:00 hrs (NI) No further MMs until confirmation of resumption of Services Fri 19/04/19 18:00 Mon 22/04/19 23:59 11 MPs commence reconciliation on receipt of 602 (NI) Fri 19/04/19 19:30 Fri 19/04/19 21:00 13 MPs confirm to ReMCoDS that reconciliation is complete (NI) 16 Milestone 3 - Reconciliation is complete (NI) RMDS website - v Detailed Cutover Plan on RMDS website
14
Tasks – Cutover Weekend
Key Market Tasks (Saturday 20th April) # KEY MARKET TASKS START FINISH JURISDICTION RESPONSIBLE 17 Milestone 4 - Confirmation of Central Market Systems isolation complete (NI) Sat 20/04/19 08:00 NI ReMCoDs 18 Milestone 5 - Notification that Central Hub upgrade is complete Sat 20/04/19 10:00 Coordinated 19 MPs commence EMMA upgrade as per agreed schedule (Do not start this task until Milestone 5 has been confirmed) Sat 20/04/19 18:30 All MPs 20 Milestone 6 - Notification that all EMMAs upgraded successfully RMDS website - v Detailed Cutover Plan on RMDS website
15
Tasks – Cutover Weekend
Key Market Tasks (Sunday 21st April) NO KEY MARKET TASKS START FINISH JURISDICTION RESPONSIBLE 21 Milestone 7 - Network Operator Testing commences (POINT OF NO RETURN) Sun 21/04/19 15:00 Coordinated ReMCoDs 22 Milestone 8 - Notification that cutover is complete. Resumption of normal services Mon 22/04/19 23:59 Additional Notes (Sunday) ESBN and NIE Networks: After Milestone 7 has been achieved, activities are undertaken in the following sequence ESBN and NIE Networks Business Validation Testing ESBN and NIE Networks confirm the completion of cutover to ReMCoDs RMDS website - v Detailed Cutover Plan on RMDS website
16
V12.00.00 Retail Market Release (ROI & NI)
Summary
17
Summary The dates and timings of individual Key Market Task and Milestones are subject to change based on progress of Cutover Flexibility is required from all market participants to ensure a successful cutover and resumption of normal market services as planned by Mon 21st 23:59 During cutover all Market Participants are required to update their EMMA via the agreed self service approach in order to be able to send and receive messages Do not send market messages using Schema Version v after the following times: Key Market Task 8 - Stop sending Market Messages (ROI) – Thu 18th Key Market Task 9 - Stop sending Market Messages (NI) – Fri 19th Market Participants are requested to be contactable until formal notification of successful Cutover Completion has been confirmed by ReMCoDS ReMCoDs will inform Market Participants when they can start sending MM’s following achievement of Milestone 8 - Notification that cutover is complete. Resumption of normal services
18
Contingency Approach Contingency approach for cutover will be to fix any issues encountered until a specified cut-off time whereby a decision will be made to roll back In the unlikely event of a rollback being required: ATOS will provide an instruction guide to MPs to roll back their EMMAs to Schema v Market Participants will need to roll back their EMMA upgrade, and any associated changes made to their respective backend systems. A rollback scenario can only be invoked up to: Milestone 7 - Network Operator Testing commences (POINT OF NO RETURN) Sun 21st Apr The contingency approach after this milestone is a “Fix and go Forward” strategy ESBN and NIE Networks will collaborate closely with ReMCoDS throughout the cutover period and should the need for a rollback scenario arise, this will be flagged as appropriate via ReMCoDS ESBN & NIE Networks cutover approaches have been proven via IPT and multiple Dress Rehearsals in their internal testing MPs EMMA upgrade to V Schema in Cutover mirrors that validated via IPT
19
V12.00.00 EMMA Self Service Upgrade
Refresh & Lessons Learned from IPT
20
IPT – Schema Upgrade - Lessons Learned
Issue # Details Solution Comments 1 User cannot execute the script as the PowerShell policy is set to not allow any scripts to run. Run this command in PowerShell "Set-ExecutionPolicy -ExecutionPolicy Unrestricted". Instructions will be provided in a known issues section of the Production upgrade guide. 2 When trying to run the script the user is prompted with the error "Access is denied" The user needs to run PowerShell as administrator before executing the script The Production upgrade guide will be updated so that the supplier must run PowerShell as administrator before executing the upgrade script 3 Additional ROI CustomerServiceDetailsCode not appearing in WebForms Drop the updated Collated.txt file into required location and restart the two WebSphere windows services. New Collated.txt file will be uploaded to the SFTP site and instructions will be provided in the known issues section of the guide.
21
Schema Upgrade Steps Market participants need to follow the following steps as part of the upgrade - Pre upgrade check Download upgrade script from the SFTP site Running the schema upgrade script as administrator Upload the upgrade script output log to the SFTP site for Atos to review Post upgrade check (TIBCO and Additional webforms codes) Send 999 test message Confirm that the version number of the 999 message is version Confirm that the 999 message sent successfully Send an to ATOS to confirm completion of all the EMMA upgrade tasks above
22
Self Service – Schema Update Guide
Walkthrough of Market Participant Self Service Schema Upgrade – Instruction Guide Note: In the unlikely event of a Schema rollback being required, a Schema Roll Back Guide will be provided by Atos.
23
Self Service – Schema Update Guide
Support will be provided by ATOS to Market Participants throughout the Schema Cutover window Schema Cutover Approach used during Cutover mirrors that used in IPT Lessons learned from IPT have been incorporated into the cutover plan and Instruction Guide It is recommended that the same resources who executed the IPT Schema update on the Test EMMA do the same for Production EMMA at Cutover Support will be provided, if required, by ATOS Market Participants should not carry out any changes to any EMMA in relation to the v Retail Market Release in advance of formal instruction via ReMCoDS i.e. Milestone 5 - Notification that Central Hub upgrade is complete – Sat 20th Apr MPs commence EMMA upgrade as per agreed schedule – Sat 20th Apr Note: Do not start this EMMA upgrade task until Milestone 5 has been confirmed by ReMCoDS On completion of EMMA Upgrade MPs should ATOS to confirm 999 sent and Log uploaded
24
V12.00.00 Retail Market Release (ROI & NI)
Hypercare Arrangements
25
Hyper Care - Overview What is Hypercare?
Hypercare is the stabilisation period after cutover which focuses support for the v Retail Market Release (ROI & NI) implemented over Easter Weekend Purpose of Hypercare is to ensure and support resumption of normal BAU market operations following cutover When is it? Hypercare begins immediately after cutover and runs for a period of up to 2 weeks
26
Hyper Care - Arrangements
Week 1 Post Go-Live – Tue 23rd to Fri 26th April ReMCoDS will schedule two conference calls in the first week with Market Participants, to provide a general status update and discuss any items raised or queries that Market Participants may have: Wed 24th April – Time TBC Fri 26th April – Time TBC Week 2 Post Go-Live – Mon 29th April to Fri 3rd May TBC – based on checkpoint on Fri 26th April
27
V12.00.00 Retail Market Release (ROI & NI)
Post Cut Over
28
Market Release v12.00.00 - Published on RMDS Website
Facilitate energy efficiencies in Local Authority Public Lighting Market Release v Published on RMDS Website The Schema Release v is due to be published on the RMDS website on Tuesday 23rd April 2019. This release will implement the following Schema and Non Schema items. MCR Ver. Description Schema / Non-Schema MCR0175 V7.0 New Reject Reasons for Address Change Rejection Schema MCR1173 V4.0 Vulnerable Customer Implementation in ROI of SI 463 MCR1167 V5.0 Facilitate energy efficiencies in Local Authority Public Lighting MCR1140 V3.0 Introduction of Eircodes into the Retail Market Design in Ireland MCR1169 Addition of Postal Code to two Downloadable Meter Point Details Files MCR1175 Provide Market Participant Business Reference (MPBusinessReference) for Reading MCR1180 New Registration Default Supplier MCR1183 V2.0 010 Customer Validation Agreement (NI) MCR1154 New Unmetered Tariff for NI MCR1184 Cooling off for CoS Non Schema CoBLCR015 V1.0 New RM Code
29
Eircodes Batch Update Process
30
Eircodes – Batch Update Process
Approach ESB Networks plan to process the set of 1.5 Million Eircodes This approach has been validated by ESB Networks performance testing Update Period Update Schedule will commence on Wed 1st May and run for a period of 12 weeks Schedule & Volumes Weekdays - Monday to Friday From: 8.00 p.m. Until : 9.00 p.m. Estimated Volumes: ~ 15K MPRNs/Day Weekends - Saturday to Sunday From: 6.00 a.m. Until: 7.00 a.m. Estimated Volumes: ~ 50K MPRNs/Day Refer to the v Market Release FAQ page on the RMDS website for further details. Link here
31
Cutover Weekend Contacts
32
Cutover Weekend Contacts
# Organisation Contacts Phone Id 1 ReMCoDS Tracy Caffrey 2 Patrick Moran 3 Lindsay Sharpe 4 ATOS Enda Maguire 5 David Peover
33
Questions?
34
Thank You
35
Appendix
36
ROI Market Release 2019 – Schema MCRs
Description Change Details Comments MCR0175 Version 7.0 New Reject Reasons for Address Change Rejection Nine New code values are being added (I.e. AD1->AD9) Market Message (MM): 014R 9 New Data Codes – Appendix – MCR0175 refers MCR1173 Version 4.0 Vulnerable Customer Implementation in ROI of SI 463 Change existing Code 0008 to be valid in ROI & Two new code values (I.e & 0010) Market Messages (MM): 010, 013 , 016 & 017 3 New Data Codes for ROI CoBL, 2 of which will be added to schema – Appendix – MCR1173 refers Data Code values will now be used on Extranet and Downloadable files – not the Central Market System Codes as per current design – Appendix – MCR1173 refers Code 0010 should not be used at this time – it’s being introduced for future proofing and will be rejected. Rejection reasons and associated rejection messages will be communicated at a future IGG. The codes will appear in confirmation messages in line with current market rules Modified downloadable files will be available to Suppliers from May 2019 – Appendix MCR1173 refers ROI Webforms :code will be selectable, not display only as originally communicated – Appendix MCR1173 refers MCR1167 Version 5.0 Facilitate energy efficiencies in Local Authority Public Lighting Eleven New code values are being added (I.e. U13->U23) Market Messages (MM): 591, 700, 700W, 701 & 701W 11 New Data Codes & 11 New Standard Profiles – Appendix MCR1167 refers 25 New Burn Hour Calendars – Appendix MCR1167 refers Effective wattage for every lamp type will be published by ESBN (when available) CoBLCR changes will be raised, as needed Downloadable file with new data values and structure will be available to Suppliers from May 2019 – Appendix MCR1167 refers MCR1183 010 Customer Validation Agreement (NI) NI Requirements NI Schema changes are covered in ReMCoWG/CDA MCR1154 New Unmetered Tariff for (NI)
37
ROI Market Release 2019 – Non-Schema MCRs
Description Comments MCR1140 Version 4.0 Introduction of Eircodes into the Retail Market Design in Ireland Eircodes can be submitted on MMs in the existing Postal Code field : 010, 012, 012W,013 & 021 Eircodes where available will be returned in the existing Postal Code fields on MM: 014R, 101, 101P, 101R, 102, 102P, 102R, 105, 105L, 110, 112, 112R, 112W, 114, 301, 301N& 330 ESBN will agree schedule for mass uploads of Eircodes into the Meter Point Address Postal Code field in the Central Market System at a future IGG. ESBN intend to update these in batch – mechanism and schedule to be discussed at a future IGG Once the Postal Code field has been populated it will be visible on the Retail Market Participant Extranet – Appendix MCR1140 refers Note: Existing Market Defect originally intended to go-live with MCR1187 will now be implemented alongside this MCR. MCR1169 Version 3.0 Addition of Postal Code to two Downloadable Meter Point Details Files Modified downloadable files will be available to Suppliers from May 2019 – Appendix MCR1169 refers However, population of field will be determined by the Eircode upload schedule for MCR1140 ESB Networks intend to discuss the upload schedule for these two files at future IGGs MCR1175 Provide Market Participant Business Reference (MPBusinessReference) for Reading The Market Participant Business Reference (MPBusinessReference) on the 300MM will be populated with that from the associated original 210MM (i.e. where it populated a periodic meter reading order) Read Reason 95/’Not for COS’ is the only case for which the above applies If the customer reading which populates the open Meter Reading Order is implausible and is estimated populate the MPBusinessReference on the corresponding 305MM If the customer reading which populates the open Meter Reading Order is withdrawn populate the MPBusinessReference on the corresponding 300WMM MCR1180 New Registration Default Supplier For sites with MIC <30kVa, the Customer must now register with a Supplier The 010MM must be received by the Central Market system before a connection point can be energised