Multi-Family Fourplex Apartment
ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’
2
Purpose The purpose of this project is to show that I can complete a construction project using all aspects of the construction process. This project will exercise the skills and abilities learned from the Construction Engineering Technology program.
3
Pre-Design and Design Phase (First Semester)
Preliminary Drawings Rough Estimate Economic Feasibility Report Site Assessment and Selection Decision on Building Layout Building Codes
4
The Building Wood Framed Concrete Foundation
Estimated 3,826 sq. ft. for each building Estimated 957 sq. ft. for each unit.
5
Preliminary Drawings Drawings will be used for a rough estimate and budget. One story layout. Two story layout. Each building will have 4 units. Three bedrooms Two Bathrooms Kitchen Utility Living and Dining Room
6
Two Story Fourplex First Floor
7
Second Floor
8
One Story Fourplex
9
Economic Feasibility Assessment
Cost/Benefits Analysis Do the Benefits outweigh the Costs for the owner? Will it be a profitable business ? How long will it take for the business to pay itself off?
10
Site Assessment and Selection
Location will be in the Hammond area. The owner would like a site big enough for future expansion, if desired. Once the land is chosen it will be surveyed. Building codes will be acquired. The location, size, and cost of property will determine: The building layout that will be used. The number of buildings that can be built on the property.
11
Conclusion The completion of the activities this semester will allow the full completion of the pre-construction documents for next semester.
12
Pre-Construction Documents (Second Semester)
The construction documents will include: Final Drawings (using AutoCad): Floor plan Electrical Plumbing Elevations Schedules and Details of Construction Overall Site Drawing (parking included)
13
Pre-Construction Documents Cont.
Building specifications Building Permits Project budget and financing A complete estimation of labor, costs, and materials Detailed materials and equipment list Planning and scheduling of the project using Primavera Project Planner.
14
Timeline (First Semester)
Aug-20-Aug 22 Meet with advisor to discuss topic Aug 25 - Aug 29 Cont. Sept1 - Sept 5 Sept 8 - Sept 12 Select a Project Sept 15 – Sept 19 Begin Research Sept 22 – Sept 26 Prepare Proposal and Presention Sept 29 – Oct 3 Preliminary Drawings Oct 6 – Oct 10
15
Timeline cont. (First Semester)
Oct 13 – Oct 17 Economic feasibility assessment of Costs and Benefits Oct 20 – Oct 24 Cont. Oct 27 – Oct 31 Rough Estimate and Budget Nov 3 – Nov 7 Site Assessment and Selection Nov 10 – Nov 14 Nov 17 – Nov 21 Decide on Building Layout Nov 24 – Nov 28 Building Codes Dec 2 – Dec 5 Begin Final Drawings/ End of Classes
16
Timeline (Second Semester)
Jan 20 – Jan 23 Construction Documents: Floor plan/ Electrical/ Plumbing/ Elevations/ Overall site plans/ Jan 26 – Jan 30 Cont. Feb 2 – Feb 6 Feb 9 - Feb 13 Feb Feb 20 Project Budget and Financing Feb Feb 27 Mar 2 – Mar 6 Building Specifications Mar 9 – Mar 13
17
Timeline cont. (Second Semester)
Mar 16- Mar 20 Estimation of materials, costs, and labor Mar 23 – Mar 27 Cont. Mar Apr 3 Building Permits Apr 6 – Apr 10 Planning and scheduling using Primavera Apr 13 - Apr 17 Apr 20 – Apr 24 Apr 27- May 1 Prepare for final presentations May 4 – May 8 Present Project
18
QUESTIONS??????