One-Touch Make-Ready Toolkit
May 23, 2019
2
McLean Engineering, Est. 1936
About Us McLean Engineering, Est. 1936 Pole Attachments Power Engineering Design Inspection
3
Agenda Wireless Pole Attachments Pole Attachment Q&A
PA 365 Requirements OTMR Process Overview OTMR Toolkit Documents Permit Application Approved Contractor Application
4
Wireless Pole Attachment Overview
5
Smartphones will surpass four-fifths of mobile data traffic
Small Cell Growth driven by demand for Mobile Data and Video Smartphones will surpass four-fifths of mobile data traffic by 2021 86 percent 86% Mobile data has grown 18-fold over the past 5 years 83% 63% 60% 2021 2017 2016 Graphics courtesy of Ross Manire, Former CEO ExteNet By 2021, 83% of Mobile Data Traffic will be Video Slide Courtesy of Alden Systems
6
Small Cell Deployments
Graphics courtesy of Ross Manire, Former CEO ExteNet Slide Courtesy of Alden Systems
7
Internet of Things – connected devices
Think of it as the Things that use Small Cells
8
“Infrastructure” things and other.
IoT “Infrastructure” things and other. Global Ericsson 2018 Mobility Report Slide Courtesy of Alden Systems
9
Change is inevitable. Struggle is optional.
The New Normal More devices providing connectivity. More structures begin utilized. More devices connecting. More types of structures being utilized. Change is inevitable. Struggle is optional. Inevitable
10
PA 365 Requirements For Municipally-Owned Electric Utilities:
Non-Discriminatory Pole Attachment Agreements (if required) Rental Rate based on FCC Formula (opportunity to cure) Make-Ready Process (by June 10)
11
In Case of Emergency
12
MMEA Resources Standard Pole Attachment Contract
Standard Wireless Addendum OTMR Toolkit
13
OTMR Intro Need for pole access What is OTMR? Guidelines governing use
Simple vs. Complex work Guidelines governing use FCC Guidelines Michigan Senate Bill 637/PA 365 Voluntary to Implement
14
OTMR Process Conduct Survey (New Attacher) Notify Utility
Application Review (Utility) Make-Ready Notifications Make Ready Work Post Make-Ready Notifications Post Make-Ready Inspection (All Parties) Post Make-Ready Remedy
15
OTMR Process – Key Differences
Conduct Survey New Attacher Make-Ready Needed? Simple Complex Application Review Utility Deadlines 10 days – completeness 15 / 45 days – approval (standard / large permits) Conduct Survey (New Attacher) Notify Utility Application Review (Utility) Make-Ready Notifications Make Ready Work Post Make-Ready Notifications Post Make-Ready Inspection (All Parties) Post Make Ready Remedy
16
OTMR Process – Key Differences
Make-Ready Notifications Before & after OTMR work 15-day advanced notice 15 days for completion of work notice Post Make-Ready Inspection 30 days for utility and all attachers Conduct Survey (New Attacher) Notify Utility Application Review (Utility) Make-Ready Notifications Make-Ready Work Post Make-Ready Notifications Post Make-Ready Inspection (All Parties) Post Make-Ready Remedy
17
OTMR Process – Key Differences
Post Make-Ready Remedy Affected party can: Bill new attacher for repairs OR Require new attacher to repair damage Conduct Survey (New Attacher) Notify Utility Application Review (Utility) Make-Ready Notifications Make-Ready Work Post Make-Ready Notifications Post Make-Ready Inspection (All Parties) Post Make-Ready Remedy
18
Permit Application – OTMR Modification
19
Permit Application – OTMR Addendum
20
Approved Contractors Engineering Construction Vegetation Management
Engineering Field Surveys PLA Make-Ready Engineering Application Review/Submittal OTMR Construction OTMR-related Transfers Shared Vegetation Management Tasks
21
Approved Contractor List
Attachers must select from list of qualified contractors for OTMR Utilities that opt in to OTMR should maintain approved contractor list Approved Certification Program Ensures only qualified contractors become approved Non-Discriminatory, In Writing, Publicly Available
22
Approved Contractor Suggested Minimum Requirements
Safety Follow published safety and operation guidelines Legal Follow all applicable local, state and federal laws and regulations Reliability EMR 1.0 No Reliability incidents completing OTMR work Insurance Adequately insured/able to establish a performance bond Attachers responsible for ensuring insurance meets joint use/pole attachment agreement Engineering Read and follow all licensed-engineered pole designs
23
Approved Contractor Certification Process
Contractor seeking approval completes application and submits to utility for review Utility notifies contractor of application status Utility reviews application for approval (15 business days) Utility notifies contractor of decision in writing Approvals added to Approved Contractor list; can begin OTMR work immediately
24
Approved Contractor Certification Process
Contractor completes and submits application for review Application should be publicly available Utility reviews for completeness Complete: moves on to review for approval Incomplete: returned to contractor Incomplete applications can be resubmitted Contractor seeking approval completes application and submits to utility for review Utility notifies contractor of application status Utility reviews application for approval (15 business days) Utility notifies contractor of decision in writing Approvals added to Approved Contractor list; can begin OTMR work immediately
25
Approved Contractor Certification Process
Utility reviews application for approval 15 business days suggested response deadline Utility notifies contractor of decision In writing Denials should be given with just cause Denied applicants can resubmit after correcting issues responsible for denial Contractor seeking approval completes application and submits to utility for review Utility notifies contractor of application status Utility reviews application for approval (15 business days) Utility notifies contractor of decision in writing Approvals added to Approved Contractor list; can begin OTMR work immediately
26
Approved Contractor Certification Process
Approvals are added to the list Can begin OTMR work immediately Approved Contractor list Publicly available Regularly updated Contractor seeking approval completes application and submits to utility for review Utility notifies contractor of application status Utility reviews application for approval (15 business days) Utility notifies contractor of decision in writing Approvals added to Approved Contractor list; can begin OTMR work immediately
27
Contractor Application for OTMR Approval
28
Key OTMR Takeaways Voluntary Communicate to: Community Tool for:
Attachers Contractors Community Tool for: Internal Depts Economic Development Local Govts/EcDev Broadband Deployment Chamber of Commerce Managing Mass Deployments On a regular basis – at least annually
29
Pole Attachment Q&A