Presentation is loading. Please wait.

Presentation is loading. Please wait.

Richard Hislop Construction Safety Coordinator

Similar presentations


Presentation on theme: "Richard Hislop Construction Safety Coordinator"— Presentation transcript:

1 Richard Hislop Construction Safety Coordinator
LCLS SAFETY Richard Hislop Construction Safety Coordinator

2 LCLS Safety Management
“LCLS Directorate ISEMS Plan” defines the roles and responsibilities of the Project Management Team (PMT) and holds the PMT responsible for the safe execution of the project. “LCLS ES&H Plan” defines the standards and requirements for safe construction. All project work is to be based on the process of job hazards analysis and documented work authorizations. No work is so important on this project that it need be done without due consideration for safety.

3 Construction Activities
46K contractor hours without injuries Contracted work at Sector 20 and the Magnet Measurement Facility was completed 6/06. SLAC deconstruction of FFTB and assorted buildings was completed 8/27/06. Turner site work commenced 8/28/06. Tunneling operations will start 10/06. Objective: Outline extent of contracted work done to date and envisioned. Development: R. Hislop was retained in April to begin developing the LCLS construction safety structure. Working with SLAC – Chapter 42 LCLS Conventional facilities group Developed the LCLS ES&H Program Process: Execution of Work: Construction safety is a process Work planning: David Saenz “Sign Off Form” Review: Technical and SLAC Safety Committee (CC) review of design Authorization: LCLS Director Oversight: Contractor, LCLS (CFG, ESH, Mgt), SLAC ESH Division, DOE-SSO

4 Surprise Configuration
FFTB SLAB REMOVAL Surprise Configuration FFTB Demolition Removal in Progress Broken Windshield Value of PPE

5 PROJECT INJURY EXPERIENCE TO DATE
Lost Time Injury Rate SubContractors 46 K Hours worked (08/28/2006) Zero Injuries LCLS Collaboration 626 K Hours worked (08/28/2006) Shoulder & back strain 96 Days Worked Without Injuries (05/11/2006) Note: Injury rates based on 200 K hours (100 man years) of effort.

6 Technical System Installations
Detailed installation schedule Authorization to perform work is preceded by management and safety reviews Daily tailgate meetings prior to work starting and closeout meeting at end of shift. Standardized use of PPE among Lab and Contractor personnel.

7 OUTREACH Management Safety Walks Lab-wide Communications

8 DOE Stanford Site Office Inspection Report
LCLS Safe Performance Observations

9 WORK IN PROGRESS Emergency / Crisis Management Coordination
Tunnel Rescue Training Safe Performance Observations Injector Safety Assessment Document Fire Hazards Analysis

10 Thank You


Download ppt "Richard Hislop Construction Safety Coordinator"

Similar presentations


Ads by Google