Feasibility & Design Study Report by CBT January 28, 2011
2
Library Overview Stoughton Public Library opened in 1969
as a well built facility of 22,000 sq. ft. with two floors on a corner lot constructed of steel and concrete in a contemporary style centrally located within walking distance of the center of town, public transportation and several public schools.
3
Current Library
4
Project Goals This proposed project is designed to expand and renovate the current structure to approximately 39,000 sq. ft. update and/or replace all systems with energy efficient components ensure that this public building is fully accessible to all
5
Project Objectives Preserve or increase existing parking spaces
Provide full handicap accessibility Offer a variety of meeting spaces for Library and public use Expand Children’s Area to offer enclosed craft and story hour space New design will not require additional staff to manage safely
6
Current Conditions Original freight elevator is not handicap accessible
7
Story Hour in Children’s Area
Parents sit on floor in open area
8
Children’s Craft in Open Area
Lack of separate meeting space for childrens’crafts
9
Monday Night Homework Center
Full to capacity with 50 students every Monday from 6-8 pm
10
Adult Literacy Pot Luck Dinner
Large Meeting room is overbooked
11
Students meet in Library
Lack of quiet meeting space
12
Adult Literacy Tutor & Student
Need for small study rooms
13
Limited Access to Public Computers
Computers clustered around pillars with electric outlets.
14
Building Concerns Replace roof warranty expired in 1999.
15
Replace Outdated HVAC Equipment
16
Replace 5 Sets of Automatic Doors Replace 32 6’x2’ Glass Panes with Safety Glass at Front and Rear Entrances
17
Exterior Cracks and Deterioration
18
Interior Cracks
19
Hazardous Materials Survey
Reported that the building contains asbestos in floor tile mastic, window glazing and wall board joint compound; small amounts of lead paint and radon, which, if left undisturbed are not currently a threat to safety, but may become so over time. Abatement costs have been included in the construction estimate.
20
Boiler Room
21
Sound Control Difficult in Open Space Design
22
Increase in Services Over the Past 6 Years
Service % change Items borrowed 134, ,846 16% increase Patron visits 146, ,698 25% increase Program attendance 5,200 6,703 29% increase Computer use 13,000 18,460 42% increase
23
Proposed 1st Floor
24
Proposed 2nd Floor
25
Proposed Elevation Views South & West
26
Proposed Elevation Views North & East
27
Proposed Design Viewed from Park
28
Proposed Design Viewed from Southeast
29
Proposed Design Model