ctcLink Project Update ctcLink Executive Leadership Committee
March 21, 2019 Jan Yoshiwara – SBCTC Executive Director, ctcLink Executive Sponsor & cELC Co-Chair Joyce Loveday – Clover Park Technical College President & cELC Co-Chair Grant Rodeheaver – SBCTC Deputy Executive Director of IT and ctcLink Project Sponsor Choi Halladay – District Vice President for Administrative Services, Pierce College, ctcLink Steering Committee Chair Christy Campbell – SBCTC ctcLink Project Director
2
Agenda Item Description Minutes Facilitator 1. Welcome Joyce 2.
1. Welcome Joyce 2. Approval of Minutes & Quorum Discussion 5 3. Steering Committee Decisions & Governance Update Deployment Group Alignment Continuing Education Approach Training Approach Security Redesign ctcLink College Roles Recommendations 15 Choi 4. ctcLink Program Status Budget Top Program Risks Moran QA Report OCIO Conditions / Technology Pool Status 20 Christy 5. Remediation & Deployment Group Status Remediation (CCS, TCC Updates) Replacement Solutions Deployment Group 2 Deployment Group 3 Deployment Group 4 Deployment Group 5/6 6. Key Messages for WACTC Business Meeting 7. Adjourn
3
celc Minutes – Approval
October 4, 2018 November 7, 2018 December 13, 2018 February 14, 2019 October, November and December minutes were tabled at past meetings due to lack of quorum.
4
steering committee decisions & governance update
Deployment Group Alignment Continuing Education Approach Training Approach Security Redesign ctcLink College Roles Recommendations
5
ctcLink college Roles & Alignment
The ctcLink Steering Committee: Adopts the College ctcLink Roles Alignment document (with the agreed-upon changes) as the recommendation to Washington State Community and Technical Colleges for the roles necessary to successfully implement ctcLink as well as the required ongoing personnel needs once the ctcLink system is in place. Requests that the cELC recommend to all WACTC Presidents that the necessary roles as outlined in the ctcLink Roles Alignment document are in place at their college prior to their college's DG implementation, and sustained post-GoLive. Steering committee approved on 3/12/19
6
Deployment group alignment
Deployment Changes Bellevue: DG4 to DG5 Columbia Basin: DG4 to DG6 Shoreline: DG5 to DG6 requested
7
“Wait and see” phase is over
8
ctcLink Program Status
Budget Top Program Risks Moran QA Report OCIO Conditions
9
Budget Status – as of Feb. 28, 2019
10
Top Risks # Risk Description Mitigation Deployment Focused 1.
College Project Manager/Executive Sponsor Engagement Hire a Project Manager Identify Engaged and Supportive Executive Sponsor Deployment Group 5 Deployment Group 6 2. College Resource Availability Other College and System wide Initiatives Daily Operations Staff Retention (Retirement/Role Changes) Create ctcLink resource plan Backfill or add additional staff as needed for your College All Deployment Groups 3. College leadership understanding of ctcLink project methodology and resource participation requirements Pre-implementation Implementation Post Implementation ctcLink Project Management Office to provide detailed resource plan to Colleges for implementation College Project Managers need to account for additional College tasks
11
Y ctcLink Quality Assurance Scorecard Overall Status
Moran Technology Consulting Report: February 2019 Overall Status Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 STATUS PROJECT AREA DESCRIPTION / NOTES G SBCTC/Governance Governance framework continues to work as expected. On 2/28 Steering Committee approved moving two colleges from DG 4 to later deployment groups. Project Management Project Management Office (PMO) is fully staffed, working well together and continuing to address improvements in project management processes. Y Phase Scope QA concerned about implementation schedules for replacement solutions. Impacts to scope and schedule for DG2 and DG3 will be more defined once solutions are selected. Schedule Status DG2/DG3/DG4 schedules and resource constraints now directly impact all deployment groups. Schedule compression and key project resources are heavily allocated to tasks. R Training This work stream is red, but is trending yellow. PMO taking appropriate actions (reallocating leadership and working with vendor on development support) to recover the schedule. Testing This work stream is yellow, but is now trending green due to changes made by the PMO. DG2 Testing work stream relies heavily on availability and expertise of functional project staff. Configurations / Data Conversion DG2 colleges have completed Cycle 3. Cycle 4 planning and technical preparation are in progress. Chart of Accounts has been configured. FirstLink colleges (FLCs) need to take ownership over their data management. Organizational Change Management (OCM) OCM is actively engaged in multiple areas, all focused on getting DG2 and DG3 colleges ready for deployment. DG4 preliminary activities have started and remaining Common Process Workshops (CPWs) are scheduled for completion by August 2019. Project Staffing Staffing is adequate at this time, contract scope has been extended for all 3 pillars. Overlap of DG2, DG3 and DG4 may require additional resources. Technical Environment A number of recent problems with the environments have surfaced that impact the DG2 project schedule and are currently being addressed. LEGEND GREEN YELLOW RED Risk Description: Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost.
12
WA State Office of the Chief Information Officer (OCIO) Oversight
WA State Office of the Chief Information Officer (OCIO) Oversight as of March 2019 Overall Status Y WA State Office of the Chief Information Officer (OCIO) Oversight WA State Office of the Chief Information Officer (OCIO) Oversight OCIO Conditions to new ctcLink Investment Plan Approval Status G 1 Project must remain in line with SBCTC and OCIO policies Ongoing 2 QA (Moran) to report to ctcLink executive sponsor and State CIO Complete 3 Follow pre-determined OFM funding gates and approvals 4 Monthly status reporting 5 Continue reporting on Remediation items in Integrated Work Plan Y 6 OCIO approval of the 4 remediation solutions: Budgeting tool, Continuing Education Application, Online Admissions Application In Progress 7 OCIO must be notified prior to use of contingency funds N/A 8 Perform a post-implementation review (lessons learned) after each deployment and post on the OCIO dashboard within 30 days of go-live Planned as Activities in Project Work Plans 9 Process and timeline for filling the SBCTC CIO position by 1/31/2018 ctcLink Technology Pool Gate# Status G Pre-IT Pool Implementation, Stability & Remediation Approved 1 Planning & Remediation 1/1/2018 2 DG2 – Initiation & Structure Phase 3 DG2 – Construct Phase DG3 - Initiation & Structure Phase In Progress 1/1/2019 4 DG2 – Transition & Deploy Phase DG3 – Construct Phase DG4 - Initiation & Structure Phase Future 7/1/2019 5 DG3 – Transition & Deploy Phase DG4 – Construct Phase DG5 - Initiation & Structure Phase 1/1/2020 6 DG4 – Transition & Deploy Phase DG5 – Construct Phase DG6 - Initiation & Structure Phase 7/1/2020 7 DG5 – Transition & Deploy Phase DG6 – Construct Phase 1/1/2021 8 DG6 - Transition & Deploy Phase 7/1/2021 9 Contingency Deployment N/A 1/1/2022 Note: New ctcLink Investment Plan approved by OCIO, with above conditions, on Jan. 19, 2018. Updated: 2/26/2019
13
Ctclink Remediation status
Remediation (CCS, TCC Updates) Replacement Solutions Online Admissions Application Budget Planning Solution Asset Tracking Solution Accessibility Testing Chart of Accounts Other
14
ctcLink Remediation Status Reports – March 1, 2019
Solution Status Due Date Campus Solutions 13 of 45 remain open Dependent on OAA/CE Financial Management 14 of 39 remain open Dependent on FY Human Capital Management 9 of 25 remain open TBD Faculty Workload Migrated to Production Complete DRS Redistribution Development in Progress March 2019 Absence Management Security Audit Controls Security Redesign Mapping Framework FLC / DG2 Student Statement QA – SIT Third Party Billing Budget Planning Form Work Group Jan 2020 Online Admissions App With Governance DG2 Continuing Education Vendor Negotiations DG3 Chart of Accounts Due Date Status FirstLink Adoption / OCM Workshops Jan. 31, 2019 Complete Establish New CoA Development Environment Jan. 31, 2019 New Departments/Programs and old department mapping from CCS Feb. 15, 2019 Configuration Complete / Functional Unit Testing Feb. 28, 2019 System Integration Testing / Parallel Close April 12, 2019 Not Started Complete College Configuration Review Sessions COA Training April 22, 2019 Configure Remaining CoA Related Updates in the CoA Development Environment April 30, 2019 User Acceptance Testing May 1, 2019 Readiness Gate / Go-No Go Decision June 1, 2019 Production Cutover July 1, 2019 New Solution Status RFP Publish Solution Decision Continuing Education Vendor has been contacted to begin Negotiations to Contract 10/15/2018 Subgroup assisting with final negotiations Online Admissions Application Work Group to Review feedback from College discussions to provide recommendation to Governance. TBD January 2019 February 2019 March 2019 Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution If needed, develop RFP Physical Inventory (Asset Tracking) Vendor Solutions being evaluated Evaluate new PS Functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/2018 DG3 (February 2020)
15
Overall Project Status – March 1, 2019
Overall Project Status Summary Category Status Comments Overall Y Program is on track, per timeline, scope and budget DG2 Training content development and UAT framework are behind and at risk to delivery Schedule Analyzing overlap between DG2 and DG3 tasks Monitoring scope and timing of Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Scope RTM needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Budget G Currently tracking under budget due to delayed hiring, timing of re-implementation of solutions (Continuing Education, Online Admissions Application, Budget) Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment continues due to the rework of key solutions. Deployment Group 2 is in the Construct Phase/Gate 3, focused on Functional Unit Testing of Configuration and delta changes, Data Conversion, and prep for SIT, UAT and UAT Training. Deployment Group 3 colleges are in the Structure Phase/Gate 2, focused on Business Process Fit/Gap sessions (BPFG). Deployment Group 4 is in the Initiation Phase/Gate 1 and is performing public status-reporting on Initiation Phase activities. Contract negotiations are in progress for the new Continuing Education solution. The Online Admissions Application (OAA) work group is actively pursuing an OAA replacement, while also implementing some interim fixes to the current OAA tool. Overall Status Summary per Deployment Group DG# Status Comments DG2 Y DG2 Training content development and UAT framework are behind and at risk to delivery DG3 G College resources have been engaged in GDA Courses and BPFG Workshops. PMs have started reporting their college status DG4 DG4 status reporting has begun with the ctcLink Initiation Phase Overall Timeline (All Deployments)
16
Deployment groups 5 and 6 Mitigation to Engage Later Deployments
Colleges to Hire Project Managers Colleges to begin the pre-work prior to implementation ctcLink Project Team to schedule OCM and Readiness campus visits May PM Summit to have a day focused on Deployment Group 5 and 6 pre-work activites
17
Questions & WRAP-UP
18
College INITIATION engagement schedule
This chart shows when each deployment group (DG) begins its first phase (initiation) and estimated Go-Live date. Dates subject to adjustment. Activity DG3 DG4 DG5 DG6 Begin Initiation Phase Work (Identify project manager, create project schedule, begin readiness efforts) Feb 2018 March 2018 July 2018 March 2019 Start Public Reporting (status reports, risks & issues) Dec 2018 Jan 2019 Nov 2019 Gate 1: Implementation Readiness July 2019 Oct 2019 July 2020 Implementation Phase Jan 2019 – Feb 2020 (Depends on DG2 Go-Live) Jan 2020 (Depends on DG3 Go-Live) Sept 2020 (Depends on DG4 Go-Live) Go-Live Feb 2020 Oct 2020 Feb 2021 Oct 2021 Revised 2/20/2019
19
Ctclink quality gates & milestones
INITIATION STRUCTURE CONSTRUCT TRANSITION DEPLOY Project Planning (Checklists & Templates) Global Design Adoption (GDA) Determine Exception Solutions Production Cutover Planning Go/No Go Decision Business Process Fit/Gap (BPFG) Update BP Flows Production Environment Prep Pre-User Acceptance Testing Training Start Change Impact Analysis & Change Action Plan Update BP Flows Update CEMLIs User Acceptance Testing Production Cutover Local Configuration Update Configuration Chart of Accounts Redesign (DG2 only) End-User Training Production Validation Training Materials Analysis/Build Convert and Validate Data Build PeopleSoft Environments Security Matrix Mapping UAT Test Definition Performance Testing Milestone Sign-Off Functional Testing Security Redesign (DG2 only) UAT Materials Build Legacy System Shutdown Procedures in Place Finalize Local Configuration Guides Prepare QA Environment Identify Exceptions Organizational Change Management Assessments Begin Prepare Parallel Environment Design Extensions Cutover Mitigation Planning GO LIVE System Integration Testing Prepare or Update Test Scripts GATE 1 PEER REVIEW Production Go/No Decision Map Supplemental Systems Data Parallel Testing Lessons Learned OCM Assessment, Activities & Deliverables for Colleges & SBCTC College Project Charter Resource Plan & Budget Plan Deliverables Legacy BP Mapping Initial Supplemental Systems Analysis Change Impact Analysis 25% GDA and BPFG Participation Supplemental Systems Data Mapping Initial Config Guides Sign-Off UAT Definition Sign-Off Change Impact Analysis 50% Design Requirements Sign-Off Security Matrix Mapping Data Validation Sign-Off Change Impact Analysis 75% OCM Readiness Checklist UAT Sign-Off End-User Training Policy/Procedures Updated Cutover Plans, Legacy Shutdown Procedures Change Impact Analysis 100% College Cutover Plan Go/No Go Sign-Off Milestone Sign-Off Config Guides Sign-Off College Lessons Learned Rev