Download presentation
Presentation is loading. Please wait.
1
Detailed Design Review (Phase 4)
P18044 – Tremor Mitigation 2 Detailed Design Review (Phase 4)
2
Agenda Overview of tasks this phase Updated risks
Control logic test rig Design updates Magnet and brake testing and outcomes Revised Fritzing diagram, battery draw calculations Updated control logic Updated BOM and test plans Goals and plans for rest of semester, beginning of MSD II Vision for Imagine RIT
3
Phase 4 Summary / Goals Increase detail in device design and CAD model. Performed experiments with electromagnetic brake set up from last year. Created a test rig so that control logic can be tested at the beginning of MSD II. Made a hand component prototype. Discovered new risks for our current design that need to be addressed. Ordered critical build materials. Planning for MSD II
4
Updates to Risk Analysis
5
Rig to Test Control Logic
6
Rig to Test Control Logic
7
CAD Model
10
Mackie Elbow Brace – Ortho Innovations
11
Hand Mock-up
12
Electromagnet – Temperature test
13
Temperature Test - Outcomes
Determined that brake housings will provide enough surface area to safely dissipate heat Is not direct skin exposure to brake housing Repeat test when circuit is optimized, switching magnet on and off at ET frequency
14
Electromagnetic brake – Slip force test
Theoretical Value Slip force: 25 N Experimental Value Slip force: ±1.78 N
15
Slip force test – Outcomes
Experimental value was 56.4% percent of theoretical value. Magnets can be doubled up per brake line (Feasibility High) Frictional coefficient of brake material can be increased. (Feasibility Moderate) Thickness of air gap can be decreased. (Feasibility Low). Current feeding magnets can be increased. (Feasibility Moderate).
16
Updates to Fritzing Diagram
17
Changes in draw calculations with more magnets
One electromagnet V = 8.8V R = 40Ω I = 8.8/4 = .22A P = 1.936W Five electromagnets I = 1.1A P = 9.68W ADD BATTERY LIFE TO THIS SLIDE
18
Control logic – coding update
19
Updates to Test Plans
20
Updates to BOM
21
Goals for rest of semester
Prepare for and complete gate review. Remain in contact with our new EE, make sure he will be up to speed before semester begins. Order remaining long lead items Finalize project plan, build and assembly plan, and meeting schedule Address outcomes of this review
22
Goals for first phase of MSD II
Completed project plan for all of MSD II Implemented problem tracking Completed build and assemble plan All of remaining purchases have been made Brace has arrived Test plan is finalized, test bench is set up.
23
Vision for Imagine RIT Best case:
Device working and robust enough to be worn by public Video of tremoring patient with and without device side by side, perhaps with displacement tracking Our poster and project overview are available. Be situated near the other tremor teams.
24
Questions?