Sector 29 PS Systems Stability Tests for LCLS
Antonio de Lira Power Conversion Department May 22, 2005
2
Sector 29 PS Systems Stability Tests for LCLS
Purposes: Test a QE PS System over Sector 29 Check PS Stability vs. time and temperature Measure Boost PS stability at 15 A Measure Buck PS stability at 10 A
3
Sector 29 PS Systems Stability Tests for LCLS
Boost PS under test Data acquisition system: Precision Zero-Flux Current Transducer (DCCT) 61/2 precision multi-channel DVM Boost PS units 30V/20A
4
Sector 29 PS Systems Stability Tests for LCLS
Bulk PS under test Data acquisition system: Precision Zero-Flux Current Transducer (DCCT) 61/2 precision multi-channel DVM
5
Sector 29 PS Systems Stability Tests for LCLS
Booster Quad 501 PS stability results Mean: A Minimum: A Maximum: A Variation: 0.12 % ∆ Temp. : 11.4 °C Note: Measurements taken on May 13, 2005
6
Sector 29 PS Systems Stability Tests for LCLS
Booster Quad 501 PS Reference stability Mean: A Minimum: A Maximum: A Variation: 0.009% ∆ Temp. : 11.4 °C Note: Measurements taken on May 11, 2005
7
Sector 29 PS Systems Stability Tests for LCLS
LGPS 1 (Bulk Quad) PS stability results Mean: A Minimum: A Maximum: A Variation: 0.9 % ∆ Temp. : 11.4 °C Note: Measurements taken on May 13, 2005
8
Sector 29 PS Systems Stability Tests for LCLS
LGPS 1 (Bulk Quad) PS stability results #2 Mean: A Minimum: A Maximum: A Variation: 0.65 % ∆ Temp. : 11.4 °C Note: Measurements taken on May 13, 2005
9
Sector 29 PS Systems Stability Tests for LCLS
Next steps: Measure Boost PS Stability at 10A & 20A Measure the ripple of the Boost PS Measure the current monitor output signal out of the Boost PS Measure the Bulk PS Stability at low current: 20A Measure the ripple current on the Bulk PS