Download presentation
Presentation is loading. Please wait.
Published byΑταλάντη Κρεστενίτης Modified over 5 years ago
1
When you link tasks: Project automatically applies a Finish-to-Start task dependency The start of the second task depends on the completion of the first task
2
Linking tasks Select the tasks
On the Task tab, click the Link Tasks button Or: Press Ctrl+F2
3
Change a task’s predecessor
In the Sheet pane, double-click the task whose predecessor you want to change Click the Predecessors tab In the ID column, enter the task ID of the task that you want to set as the predecessor Click OK
4
Lag time A delay that adds time after the completion of a task
Example: “Install trim” If you add lag time to its predecessor, “Paint,” the paint will have time to dry before the trim installation begins
5
Lead time The overlap between dependent tasks (when a task can start before its predecessor finishes)
6
Apply lead time or lag time
Double-click a task in the Sheet pane Click the Predecessors tab To apply lag time, enter a positive value in the Lag field for the predecessor To apply lead time, enter a negative value Click OK
7
Insert a recurring task
In the Task Name field, select the cell below where you want to insert the task Click the Task arrow and choose Recurring Task Enter a name for the recurring task Enter the duration Select a time interval Enter the dates across which the recurring task will occur Select a calendar for scheduling the task Click OK
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.