Download presentation
Published byBrice Harley Modified over 10 years ago
1
MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION
WHERE WE ARE – WHERE WE ARE GOING NOVEMBER 20, 2013 PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT
2
RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM
3
PROGRAM YEAR 2013 TASK CONTRACT VALUE MBE 1
Runway 15R-33L Standards Compliance Earthwork Project $21,800,000 25% 2 Runway 15R Deicing Pad Pavement Rehab. And Stnds. Compliance $14,169,000 30% 3 Low Maintenance Grassing Test Plots $133,000 4 General Aviation Pavement Rehabilitation $994,000 20% 5 RSA Program Environmental Stream Restoration Project $2,079,000 26% 6 Runway 15L-33R Runway Safety Area Improvements $4,960,000 7 Runway 15R-33L RSA, PMP and Standards Compliance Project $83,235,000 8 Runway and 15R-33L Obstruction Clearing Project $413,000 4% 9* Runway 15R-33L NAVAIDS Project $5,409,000 13% *Graphic location same as Task 7
4
15R 33L EARTHWORK CONTRACT VALUE: $ 21,756,470
Contract Completes – Summer 2014 MBE: 25% PROJECT OVERVIEW: Clearing and grubbing. Storm drain installation. Box culvert installation. Sanitary sewer and underground fire hydrant relocation. Mass earthwork, grading and retaining wall.
5
RUNWAY 15R DEICING CONTRACT VALUE: $ 14,168,409
Contract Completes – November 2013 MBE: 30% PROJECT OVERVIEW: Removal of existing pavement. Installation of new glycol drainage infrastructure, lighting, diversion vaults. New concrete pavement and pavement markings.
6
ENVIRONMENTAL STREAM RESTORATION
CONTRACT VALUE: $ 2,078,771 Contract Completes – July 2014 MBE: 26% PROJECT OVERVIEW: Grading of stream channels and placement of fill. Construction of in-stream structures. Removal of invasive vegetation and plantings.
7
RUNWAY 15L 33R RSA CONTRACT VALUE: $ 4,959,398
Contract Completes – Spring 2014 MBE – 14% PROJECT OVERVIEW: New vehicle service road and airfield equipment access road. Drainage pipe, box culvert and structure installation. Preparation of site and infrastructure for future relocation of existing NAVAIDS.
8
RUNWAY 15R 33L RSA CONTRACT VALUE: $ 83,235,000
Proposed Schedule – September 2013 to April 2015 PROJECT OVERVIEW: Comprehensive Pavement Rehabilitation. Runway Safety Area Grading and Improvements. NAVAID Relocations and Infrastructure Improvements. Runway and Taxiway Lighting Improvements. Taxiway Realignments. Runway Incursion Prevention Elements.
9
PROGRAM YEAR 2014-2015 2014-2015 PROGRAM ELEMENTS
6 Runway Navaids & Runway 28 Displacement 15A New T/W “Uniform” & T/W “Uniform 1” And South Portion De-ice Pad 15B Runway 4-22 Conversion To Taxiway “Papa” 15C New Taxiway Construction (EB-75) 15D Old Taxiway “Delta” Demolition PROGRAM VALUE M 15B 15A 15D 15C 6
10
CORRIDOR WIDTH IN ORIGINAL PORTIONS OF CONCOURSES INADEQUATE
EXISTING TERMINAL CORRIDOR WIDTH IN ORIGINAL PORTIONS OF CONCOURSES INADEQUATE SECURITY CHECKPOINTS IN THE THROAT OF THE CONCOURSES RESTRICT EGRESS/ EVACUATION CAPACITY
11
NEW CHECKPOINTS BETWEEN CONCOURSES
LONG TERM TERMINAL PLAN UPPER LEVEL PLAN NEW CHECKPOINTS BETWEEN CONCOURSES BEHIND SECURITY CONNECTORS ALLOW FOR LOAD BALANCING AND CONNECTING FLIGHTS
12
LONG TERM TERMINAL PLAN PHASING PLAN
CONCOURSE D ORIGINALLY FIRST BECAUSE DEFICIENCIES WERE GREATER DUE TO THE NUMBER OF GATES SERVED. E SWA / AIRTRAN MERGER AND CONSOLIDATION ON CONCOURSES A/B/C SHIFTED PRIORITIES TO BC CONNECTOR C A B
13
TWO CONSTRUCTION PROJECTS
BC CONNECTOR PROGRAM TWO CONSTRUCTION PROJECTS CONCOURSE C WIDENING B/C CONNECTOR
14
BC CONNECTOR FINAL UPPER LEVEL PLAN 9 LANE CHECKPOINT
15
BC CONNECTOR CONTRACT VALUE: $ 43,937,000 MBE: 20% PROJECT OVERVIEW:
Secure passenger corridor connecting Concourse B and C. Nine (9) Lane Security Checkpoint. Observation Deck improvements. Concessions and Office Spaces.
16
BC CONNECTOR
17
NEW BC SECURITY CHECKPOINT
18
NEW BC CONNECTOR
19
CONCOURSE C WIDENING CONTRACT VALUE: $ 28,799,512
Completion Date – January 2013 MBE: 31% PROJECT OVERVIEW: Renovate Concourse C to include larger passenger hold rooms and a wider corridor and exit. New passenger boarding bridges. New baggage handling system. New public restrooms. Modify mechanical & electrical systems.
20
DE CONNECTOR CONTRACT VALUE: $ 75-100M
Proposed Design Schedule: September September 2014 Proposed Construction Schedule: January November 2016
21
DE CONNECTOR
22
DE CONNECTOR ARRIVAL LEVEL PLAN
23
DE CONNECTOR DEPATURE LEVEL PLAN
24
NEW DE SECURITY CHECKPOINT
25
DE SECURITY CHECKPOINT
VIEW FROM TERMINAL D
26
DE SECURITY CHECKPOINT
VIEW FROM TERMINAL E
27
DE CONNECTOR
28
DE CONNECTOR VIDEO OF PROJECT OVERVIEW: BWI CONFORM.wmv
29
Contract Number & Title
Proposed Date Project Value MAA-CO Parking Access and Revenue Control System (PARCS) ***May 2013 $8M-$11M MAA-CO Airfield Capacity Enhancement Project **April 2014 $80M MAA-CO International Building Expansion **December 2013 $7M MAA-CO Comprehensive Interior/Exterior Modification 2014 **November 2013 $25M MAA-CO Long Term Parking Lot B Pavement Rehabilitation $1.7M MAA-CO Pedestrian Walkway from CRCF to the East Tenant Lot *October 2013 $.5M MAA-CO Public Parking Area Pavement Rehabilitation $1M MAA-CO Central Terminal Third Floor Elevator Upgrades MAA-CO Air Cargo Drive Pavement Rehabilitation *February 2014 *Program **Advertised ***BidsDue ****Bid Opening
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.