Earned Value $$$
2
Earned Value Measure of Project Performance Overall for All Activities
Measured at Particular Point in Times 13
3
Computing Earned Value
EV = (% Completed Work) (Planned Cost) E.G. EV = .75 x 100 = 75 EV Also Known as: Budgeted Cost of Work Performed to Date (BCWP) 13
4
Using Earned Value Cost Variance (CV) = EV (BCWP) – Actual Cost of Work Performed (ACWP) E.G. CV = 75 – 100 = -25 (Over Budget) Schedule Variance (SV) = EV (BCWP) - Budget Cost of Work Scheduled (BCWS) E.G. SV = 75 – 125 = -50 (Costs behind Schedule) Time Variance (TV) = Scheduled Time Work Performed (STWP) – Actual Time Work Performed (ATWP) E.G. TV = 20 – 25 = -5 (Behind Schedule) 13
5
Example: Problem 3.8 EV = (% Completed) (Planned Cost)
EV = (Actual Progress/Scheduled Progress) (100) CR = (Actual Progress/Scheduled Progress) (Budget Cost/Actual Cost) CR = (EV/100) (100/Actual Cost) CR = EV/Actual Cost 13
6
CR for A: Over 6 Days Day A:EV A:Cost A: CR 1 90 95 .947 2 92 98 .939
13
7
CR for B: Over 6 Days Day B:EV B:Cost B: CR 1 90 95 .947 2 88 94 .936
13