Project Success: Expansion of Maximo Across the ONEOK Partners’ Footprint September 23, 2016 Alexi Powell & Kylie McMains

2 Agenda : ONEOK, Partners Introduction
ONEOK’s Natural Gas Pipelines Business Segment Project Team Project Objectives Deployment Strategy Data Collection, Validation & Migration Sustainability Successes

3 ONEOK, Partners ONEOK's headquarters are located in Tulsa, OK.
ONEOK is a Fortune 500 company and is included in Standard & Poor's (S&P) 500 Stock Index Approximately 2,400 employees ONEOK Partners operations are conducted through the following three business segments: Natural Gas Gathering and Processing Natural Gas Liquids  Natural Gas Pipelines  

4 Natural Gas Pipelines Assets

5 Project Team Steering Team Committee
VP of Natural Gas Pipelines Operations Regional, Business System & Technical Directors Business System Owner Project Functional Lead Maximo SAS Product Project Technical Lead Project Managers Project Team Members Maximo Business Partners Operations Representative Pipeline Representatives IT Report Developer

6 Project Objectives Successfully migrate the Natural Gas Pipeline’s assets, work management data and users from the current asset management software to Maximo Have minimal impact on the current business operations during implementation To ensure all data met Compliance & Regulatory Requirements Provide Maximo training to all new administrative support and end users before Go Live. Project driven by ONEOK Partners Key Drivers Meet target deadline

7 Deployment Strategy Interstate Pipelines Intrastate Pipelines
3 Companies / Regions 31 Teams Intrastate Pipelines 2 Companies / Regions 19 Teams

8 TOOLS Python Script – provided by our OnTracks Consultant
Location, Assets, Route & PM Load Sheet MxLoader SSRS Reports PM Review By Department Report Backlog Report Open Work Order Report

9 Data Load Sheet

10 Reports

11 Data Collection, Migration & Validation
Location & Assets Route Load Sheet PM Load Sheet LOAD INTO PRODUCTION Python Script Operation Mgrs & Sup. Operation Mgrs & Sup Operation Mgrs & Sup Operation Mgrs & Sup LOAD LOAD LOAD

12 Sustainability Administrative Support
Provide Monthly Reports to Management / Stakeholders PM Review By Department Report Backlog Report Daily End User Support Trouble Shooting, WO Mgmt Solicit feedback from end users

13 Successes Completed project ahead of schedule
Completed project under budget Completed project without requiring additional resources User buy-in Met all business requirements Maintained business segment processes Did not disrupt day to day operations Managed to hit all of ONEOK’s Key Drivers

14 Questions Project Success: Expansion of Maximo Across the ONEOK Partners’ Footprint