1 Information Technology Virtualized Server Proposal
Bob Engmark, IS Rusty Scott, ACNS UTFAB Supplemental Request March 1, 2011

2 Original Proposal (Dec. 2010)
Replace 10 (two generations old) IBM servers with 2 current generation IBM servers Possible by using “Virtual Machine” technology Original proposal cost estimate: $128K What These Servers Do Aries SIS test and development Tivoli file backup and restore services Used for virtually all centrally managed systems Other misc. central IT service -Talk to you in December about planned project to replace several older servers with two new boxes deployed in a clustered format and using virtualization to maximize the investment by reducing environmental costs, maint costs while providing an exponential improvement in processor capacity -The systems being upgraded in this project support several areas used by students and used to support the ARIES SIS UTFAB Supplemental Request March 1, 2011

3 Original Proposal was Approved
Provost funded $64K Central IT (IS and ACNS) funded $54K UTFAB funded $10K This project was funded through a partnership UTFAB Supplemental Request March 1, 2011

4 Subsequent IS-ACNS Discussions:
Why stop there?? Test and development activities are indeed critical to maintaining maximum uptime, but… Test/Dev environments should replicate, to the extent possible, the production systems they shadow UTFAB Supplemental Request March 1, 2011

5 What the Data Shows People in system – 719,204
Students Fall 2010 Census - 29,932 RAMweb logins, 2010 – 3,894,939 ARIESweb logins 09/ ,831 Grades input for Fall ~ 128,000 Sections Fall 2010 of classes – 7,101 Major changes processed 09/ ,074 Financial Aid disbursed 09/10- ~$235,000,000 Official Academic Transcripts produced 09/ ,010 Degree Audits run RAMweb/ARIESweb 09/10 – 189,662 Document pages imaged – 1,706,010 So… UTFAB Supplemental Request March 1, 2011

6 Ramweb Logins UTFAB Supplemental Request March 2, 2011

7 Virtualized Server Proposal, v2
Extends original concept to include production systems (in addition to test & dev systems) Replaces 19 (generations-old) IBM servers with four current, very capable servers As before, using “Virtual Machine” technology 84% of these 19 servers support student apps Application and Database Servers Other auxiliary services also included As we begin to plan the upgrade with technical staff the question that kept coming up was why not include production systems in the mix – Originally we were looking at replacing oldest systems Took a look at what that would mean to replace servers supporting other services as well and re-purposing those systems to continuity planning efforts – so we began looking at the configuration and considered what flexibility it would provide us in going forward and it presented some promising options So we asked our vendor partners to take another look and recommend a solution to that would allow us to accomplish more UTFAB Supplemental Request March 1, 2011

8 Revised Hardware Cost Estimate
$378K total cost, includes all four servers $128K already funded $64K from Provost $54K from IS/ACNS $10K from UTFAB $250K remains unfunded UTFAB Supplemental Request March 1, 2011

9 Current Funding Request
$150K, In addition to $10K committed in December $378 project total; UTFAB’s portion is 42.3% of total 84% of systems related to Student Support Applications There is a central funding commitment for the balance $100K IS/ACNS (40%) UTFAB Supplemental Request March 1, 2011

10 Benefits Increased system robustness Cost efficiencies
Flexibility = less downtime during maintenance & upgrades Provides scalability, allowing the system to grow to meet increasing demand Positions us to provide auto failover capabilities in the future Cost efficiencies HW and SW maintenance $130K less than traditionally configured hardware over a 5-year period Substantial savings in electricity and cooling “Green” activity also recognized by City Utilities Offering ~$4K rebate for virtualization effort Most of replaced hardware repurposed for backup and disaster recovery -Hardware and software maintenance w/o considering inflation, so this is a conservation estimate -The newer hardware is much more energy efficient and virtualization provides an opportunity for energy rebate UTFAB Supplemental Request March 1, 2011

11 UTFAB Funding Criteria
1. Benefit as many students as possible All CSU students benefit 2. Ability to effectively utilize the fee Your decision 3. Not funded by CFT Correct 4. Adherence to budget and accountability 5. Potential for direct student use Without question 6. Effort, thought & clarity in the plan 7. Quantitative usage data See slides 5 & 6 8. Financial co-sponsorship 57.7% Central, 42.3% UTFAB 9. Central/distributed balance 10. Cost/benefit ratio 11 UTFAB Supplemental Request March 1, 2011

12 Discussion Is most welcome UTFAB Supplemental Request March 1, 2011