1
Positioning, alignment strategy and assembly steps
CRYOGENICS IS OUR PASSION Wroclaw CTL-EL Assembly Positioning, alignment strategy and assembly steps Maciej Matkowski Project Manager
2
Supports bolting We expect to have drilled holes in the tunel and CTL Gallery. When the holes are ready we will put supports on place and we will bolt them with proper anchors.
3
Unloading with overhead crane by ESS rigging team.
VB unloading CDS-EL: Unloading with overhead crane by ESS rigging team. All material related to lifting >1 year must be inspected and documented before use according to AFS 2003:6. Valve box: Traverse for lifting VB is attached to one hook so it is possible to rotate them while hanging in the overhead crane.
4
VB transport
5
VB transport
6
VB transport
7
Transport route
8
Supports assembly
9
CTL-EL Line positioning and alignment
CTL-EL Line positioning and alignment Lowest point in tunnel – 3,17m Highest point on VB – 3,04 m
10
CTL-EL valve box positioning and alignment
CTL-EL valve box positioning and alignment
11
CTL-EL valve box positioning and alignment
CTL-EL valve box positioning and alignment
12
CTL-EL Line positioning and alignment
CTL-EL Line positioning and alignment
13
VT, pressure and helium leak tests
Welding process pipes VT, pressure and helium leak tests MLI wrapping
14
VT, pressure and helium leak tests
Welding process pipes VT, pressure and helium leak tests MLI wrapping
15
Thermal shield assembly and MLI wrapping
Thermal shield assembly and MLI wrapping
16
OJ assembly Tests
17
Aux Supports assembly
18
Assembly and welding aux lines
Assembly and welding aux lines Tests of aux lines
19
Assembly and welding aux lines
Assembly and welding aux lines Tests of aux lines