Rail Program Management Services Review Grade Separation Recommended Ideas
Palo Alto Rail Committee Meeting ……..
2
From Presentation to City Council on May 29, 2018
3
Ideas to Review Churchill Avenue Hybrid (CAH)
A "hybrid" option that would partially lower the road and partially elevate the tracks Churchill Avenue Reverse Hybrid (CAR) The “reverse hybrid" option with a partially elevated road and partially lowered tracks Palo Alto Hybrid (PAH)
4
Churchill Avenue Hybrid (CAH)
Embarcadero Rd Churchill Ave N California Ave Oregon Expy +0.6% Grade Length = 3800 ft -1% Grade Rail Embankment Fill at Churchill = 10 ft Roadway Excavation at Churchill = 15 ft Constraints: California Ave Caltrain Station Platform Caltrain Operating Envelop for Construction Limits Construction Limits based on Caltrain Operating Envelop No Impact to California Ave Caltrain Station Platform
5
Impacts: Removal of existing trees in the buffer between Alma St and the mainline tracks to construct shoofly and maintain Caltrain service Alma St will be temporarily reduced from 45 ft to 25 ft during construction resulting in loss of traffic lanes and/or parking 14 residential properties impacted with an additional 8 residential driveways impacts – approximately 22 residential properties Major utility relocations required along Churchill and Alma Visual impact of raised railroad
6
Churchill Avenue Reverse Hybrid (CAR)
Embarcadero Rd Churchill Ave N California Ave Oregon Expy -1.0% Grade Length = 3600 ft +0.5% Grade Rail Excavation at Churchill = 6 ft Roadway Embankment Fill at Churchill = 22 ft Constraints: California Ave Caltrain Station Platform Caltrain Operating Envelop for Construction Limits Construction Limits based on Caltrain Operating Envelop No Impact to California Ave Caltrain Station Platform
7
Impacts: Removal of existing trees between Alma and mainline tracks for construction of shoofly and to maintain Caltrain service during construction Reduced width of Alma from 45 feet to 25 – loss of traffic lane and/or parking Approximately 46 residential impacts Major utility relocations along Churchill and Alma Visual impact with elevated roadway
8
Palo Alto Hybrid (PAH) +1.0% Grade -1.0% Grade Constraints:
Length = 3500 ft +1.0% Grade -1.0% Grade El Palo Alto Heritage Tree Historic RR Bridge Palo Alto Ave No Impact to Palo Alto Caltrain Station Platform Rail Embankment Fill at Palo Alto = 7 ft Roadway Excavation at Palo Alto = 15 ft Constraints: Palo Alto Caltrain Station Platform Historic Bridge over San Francisquito Creek El Palo Alto Heritage Tree in El Palo Alto Park Caltrain Operating Envelop for Construction Limits
9
New Track Alignment New Rail Bridges Existing Track Impacts:
Removal of trees between Alma and mainline tracks Reduce width of Alma Street Impact to El Palo Alto Park but misses heritage tree in park – needs to be confirmed Major utility relocations in Palo Alto Visual impact with raised rail Existing Track