1 CDM Activity Cycle under the Marrakech Accords

2 1. Project Design A document with the information needed about the proposed CDM project. Project participants

3 2. Validation and Registration
Validation is the process of independent evaluation of a CDM project. Registration is the formal acceptance of a validated project. Operational entity Executive Board

4 3. Monitoring The collection and archiving of all relevant data necessary for establishing GHG emissions by sources occurring within the project boundary during the crediting period. Project participants

5 4. Verification and certification
Verification is the periodic independent review and determination that GHG reductions have occurred as a result of a registered CDM project activity during the verification period. Operational entity

6 Certification is the written assurance that a project activity achieved the GHG reductions stated during the specified time period. Operational entity