Presentation is loading. Please wait.

Presentation is loading. Please wait.

C2 Follow the Capital Risks

Similar presentations


Presentation on theme: "C2 Follow the Capital Risks"— Presentation transcript:

1

2 C2 Follow the Capital Risks
Adam Rouse Managing Consultant

3 Agenda Understand why capital projects are often left out of annual audit plans How to determine which capital projects to audit How to audit capital projects Lessons learned

4 Why Capital Projects are Often Left Out of Annual Audit Plans

5 How organizations develop annual audit plans…
Risk-based approach (risk assessment) Changes within organization Key initiatives Financial exposure/risks IT / Cyber security focus

6 IA risk assessment methodology is risk based
Capital spending budgets are increasing Infrastructure spending is increasing

7 Biggest reason why…… The unknowns / status quo
“We have a GMP or not-to-exceed contract, therefore we have no risk of cost overruns.” “We hire a construction management firm to monitor and manage the project.” “We have worked with the same GC and no issues or cost overruns have occurred in the past.”

8 Common reasons why capital projects not audited
Ignorance Fear/ uncertainty Territories Budgets were smaller False sense of protections Legal Contract language Contract type (lump sum) How to overcome Training Awareness Utilize 3rd party expert

9 Which Projects to Audit?

10 Risk assessment How to evaluate risks: Size of project in $
Dollar volume of owner change orders Number of sub contractor change orders Type of construction agreement (lump sum-low vs cost plus-high) Over or under budget Fast track vs non-fast track

11 Higher Risk for Contractor
Contract Type Firm Fixed Price Fixed Price w/ Price Adjustment Cost plus Incentive Fee Cost Plus Fixed Fee Time & Materials Cost Reimbursement Cost Plus a Percentage of Cost Higher Risk for Contractor Higher Risk for Owner

12 Don’t forget to consider
Political risk Economic risks Designers risk Stakeholder risks Document and information risk Other risks: Weather risks Resource risks Construction site risks Supplier risks Contractor risk Past experience with contractor Public relations risk (public project?) Organizational initiatives

13 How to Audit Capital Projects

14 Why audit? Transparency Recover overcharges Lower capital cost
Reduce project risk Control capital expenditures Hold parties accountable

15 Identify any contradictory language
Phase 1: Contract Review Make sure all essential terms & conditions are in contract to protect owner Contracts are typically written in the contractors’ favor, not the owner Identify any contradictory language AIA contract templates are written by architects IDEALLY GET INVOLVED BEFORE CONTRACT IS SIGNED Phase 2: Pay Application Review Reviewing the project in close to real time Review monthly pay applications (labor, equipment, rental, overheads, etc.) Review any & all change orders Independently track the projects progress & budget Phase 3: Closeout Review Performed at the end of a project The idea is to recheck all figures before retention is paid out Review the project checklists, obtain all lien waivers, post-project checklist/punch list

16 Auditing steps Obtain & understand contract(s)
Learn roles/responsibilities of each contractor on the job Obtain all payment applications & change orders Obtain support for all charges (equipment rental agreement, time sheets, etc.) Compare data within invoices and support to contract & other support as necessary

17 Other Items Often change orders increase project budget
Contractors do not frequently account for deductions, only additions Supporting documentation is often not provided or is very vague Look for: lump sum change orders, higher costs (premium charges), scope overlap, excessive profit, using contingency money

18 Documents to request electronically
Job cost ledger from contractor Owner and sub contractor change orders Allowance log from contractor Architect’s design change order log

19 Allowances Allowances are customary; however, they need to be reconciled at the end of project Purpose: put in contract for items that cannot be specifically identified, e.g., kitchen appliances in an office building

20 Labor & labor burdens Often holidays & vacations are included in profit rate or in labor burdens & get double billed Burdens should not include: union dues, tool allowances Sometimes labor burden charges are included in general conditions Example If an employee works overtime (1.5x), labor burdens would increase 1.5x. The contractor is not paying more health insurance or payroll taxes for salaried employee, yet would charge you extra

21 Lessons Learned

22 #1 Insurance sub guard Sub defaulted & claim was submitted Has to hire another sub to re-work the task (framing) Ended up costing owner additional $775,000

23 #2 Medical office building: $350m Questionable costs, fee corrections, sub contractor change orders overages, final pay app overbilling - Amounted to $7.9m

24 #3 Lump sum contract Contractor running out of funds $1m lump sum contract CO submitted for $1m

25 #4 Fast tracked project Over 1 million labor hours $3/hr tool allowance

26 #5 Lump sum contractor paid too early 18 month contract duration Owner engaged several construction firms to perform same scope of work Contractor was bonded Progress payments

27 Adam Rouse // acrouse@bkd.com

28

29 BKD Thoughtware®


Download ppt "C2 Follow the Capital Risks"

Similar presentations


Ads by Google