Group 5 – ECE 4006: Week 6 Nihar Patel 7/17/2019
2
Progress made Finalized Optical Link Budget Working on Monetary Budget
Finished Transmitter Circuit Design Finished Receiver Circuit Design Ordered passives and PD Initial Layout completed 7/17/2019
3
Updated Schedule 7/17/2019
4
Optical Link Budget View OLB in Excel Parts and Parameters 7/17/2019
5
Optical Link Budget Continued
View OLB in Excel 7/17/2019
6
Monetary Budget View Monetary Budget in Excel 7/17/2019
7
Transmitter Schematics
7/17/2019
8
Receiver Schematics 7/17/2019
9
First Attempt at Layout
View Layout in Express PCB 7/17/2019
10
Some Bad Luck Managed to get 8 VCSEL samples
Received unconnectorized Have to order VCSEL again Found place to get PCB done for free Company uses different layout tool Going to try the new tool in Run #2 7/17/2019
11
Anticipated Progress for Week 7
Review and finalize layout Check back with vendors on orders Finish ordering components 7/17/2019