Presentation is loading. Please wait.

Presentation is loading. Please wait.

Managing Risk Chapter 7.

Similar presentations


Presentation on theme: "Managing Risk Chapter 7."— Presentation transcript:

1 Managing Risk Chapter 7

2 Objectives Risk Management Probability of completion Change Management

3 Risk Management A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a project’s success. Risk event. Consequences. Anticipation. Contingency plans. Risk event – what can go wrong ID consequences – how to minimize the impact of event Anticipation plan - what can be done before an event occurs Contingency Plans – what to do when an event occurs

4 Risk Event

5 Risk Process

6 ( ) St. Adolf’s Hospital te = 2 = Probabilistic Time Estimates Mean
G Finish D E H B J K Start te = a + 4m + b 6 Mean 2 = ( ) b – a 6 2 Variance Often referred to as the PERT technique, the use of probabilistic time estimates allows for additional analysis of the project network. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 75

7 St. Adolf’s Hospital Critical Path Start Finish C 10 G 35 E 24 I 15 F
B 9 D H 40 J 4 K 6 A 12 Finish Start Critical Path 69

8 St. Adolf’s Hospital Time Estimates (wk) Activity Statistics
Optimistic Likely Pessimistic Expected Variance Activity (a) (m) (b) Time (te ) (2 ) Time Estimates (wk) Activity Statistics A B C D E F G H I J K 5 6 7 This table shows all the expected task times and variances for use in the probabilistic calculations. Example 8.6 79

9 St. Adolf’s Hospital Activity B Most Optimistic Likely Pessimistic
Probabilistic Time Estimates A F I C G Finish D E H B J K Start Activity B Most Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 Often referred to as the PERT technique, the use of probabilistic time estimates allows for additional analysis of the project network. Example 8.6 75

10 ( ) St. Adolf’s Hospital te = 6 2 = Activity B Most
Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 A F I C G Finish D E H B J K Start te = 7 + 4(8) + 15 2 = ( ) 15 - 7 6 2 Example 8.6 77

11 St. Adolf’s Hospital Ts – TE 2 =  (variances of activities) 2
Probabilities Critical Path = B - D - H - J - K T = 72 days TE = 69 days 2 =  (variances of activities) z = Ts – TE 2 This slide advances automatically. 2 = = 11.89 z = 72 – 69 11.89 83

12 St. Adolf’s Hospital Project duration (weeks) 69 72
Probability of meeting the schedule is Length of critical path Normal distribution: Mean = 69 weeks;  = 3.45 weeks Probability of exceeding 72 weeks is Here Figure 18.9 is overlaid to illustrate the current analysis. 86

13 Any Questions?


Download ppt "Managing Risk Chapter 7."

Similar presentations


Ads by Google