Download presentation
Presentation is loading. Please wait.
1
Managing Risk Chapter 7
2
Objectives Risk Management Probability of completion Change Management
3
Risk Management A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a project’s success. Risk event. Consequences. Anticipation. Contingency plans. Risk event – what can go wrong ID consequences – how to minimize the impact of event Anticipation plan - what can be done before an event occurs Contingency Plans – what to do when an event occurs
4
Risk Event
5
Risk Process
6
( ) St. Adolf’s Hospital te = 2 = Probabilistic Time Estimates Mean
G Finish D E H B J K Start te = a + 4m + b 6 Mean 2 = ( ) b – a 6 2 Variance Often referred to as the PERT technique, the use of probabilistic time estimates allows for additional analysis of the project network. To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. 75
7
St. Adolf’s Hospital Critical Path Start Finish C 10 G 35 E 24 I 15 F
B 9 D H 40 J 4 K 6 A 12 Finish Start Critical Path 69
8
St. Adolf’s Hospital Time Estimates (wk) Activity Statistics
Optimistic Likely Pessimistic Expected Variance Activity (a) (m) (b) Time (te ) (2 ) Time Estimates (wk) Activity Statistics A B C D E F G H I J K 5 6 7 This table shows all the expected task times and variances for use in the probabilistic calculations. Example 8.6 79
9
St. Adolf’s Hospital Activity B Most Optimistic Likely Pessimistic
Probabilistic Time Estimates A F I C G Finish D E H B J K Start Activity B Most Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 Often referred to as the PERT technique, the use of probabilistic time estimates allows for additional analysis of the project network. Example 8.6 75
10
( ) St. Adolf’s Hospital te = 6 2 = Activity B Most
Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 A F I C G Finish D E H B J K Start te = 7 + 4(8) + 15 2 = ( ) 15 - 7 6 2 Example 8.6 77
11
St. Adolf’s Hospital Ts – TE 2 = (variances of activities) 2
Probabilities Critical Path = B - D - H - J - K T = 72 days TE = 69 days 2 = (variances of activities) z = Ts – TE 2 This slide advances automatically. 2 = = 11.89 z = 72 – 69 11.89 83
12
St. Adolf’s Hospital Project duration (weeks) 69 72
Probability of meeting the schedule is Length of critical path Normal distribution: Mean = 69 weeks; = 3.45 weeks Probability of exceeding 72 weeks is Here Figure 18.9 is overlaid to illustrate the current analysis. 86
13
Any Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.