Muon Installation Status
Geoff Tappern 7/22/2019 Muon Plenary Meeting
2
Muon Installation Phases
Phased installation:- Phase 1 all 12 BMF, 6 BOG, and 4 BOF - completed. Phase 2a BMS chambers in sector 10 – completed. Phase 2b BMS chambers in sector 16 – completed. Phase 3a 6 BML (completed), and 3 BOL (1 installed) in sector 13. Phase 3b will be installation of EIL4 at end A. Phase 4 is muon installation after the release of the jacks of the BT coil. Also muon rails and brackets will be checked at this stage, and adjusted to position. 7/22/2019 September 2005 Muon Week
3
Sector 13 7/22/2019 September 2005 Muon Week
4
BML & BOL Installation sector 13
7/22/2019 September 2005 Muon Week
5
Preparations for BML 7/22/2019 September 2005 Muon Week
6
BML Installation 7/22/2019 September 2005 Muon Week
7
Survey rails BOL sector 13 end A
7/22/2019 September 2005 Muon Week
8
BOL Installation through truck
7/22/2019 September 2005 Muon Week
9
BML Installation 7/22/2019 September 2005 Muon Week
10
BOL Installation through truck
7/22/2019 September 2005 Muon Week
11
Barrel Muon Layout 7/22/2019 September 2005 Muon Week
12
Muon rail & Bracket Positions
7/22/2019 September 2005 Muon Week
13
Bracket and rail manufacture
7/22/2019 September 2005 Muon Week
14
Phase 4:-Now Brackets and rails
7/22/2019 September 2005 Muon Week
15
BOS & BOL Bracket Installation
7/22/2019 September 2005 Muon Week
16
BOS & BOL 7/22/2019 September 2005 Muon Week
17
Monday Sept 5th 7/22/2019 September 2005 Muon Week
18
BMS Installed chambers sector 16
7/22/2019 September 2005 Muon Week
19
BMS Sector 2 & 8 7/22/2019 September 2005 Muon Week
20
BMS Sector 2 & 8 7/22/2019 September 2005 Muon Week
21
BMS Sectors 2 & 8 7/22/2019 September 2005 Muon Week
22
BMS Sectors 4 & 6 7/22/2019 September 2005 Muon Week
23
BMS Sector 4 7/22/2019 September 2005 Muon Week
24
Mast climbing platform and frame
7/22/2019 September 2005 Muon Week
25
Phase 4 – Part of rails & access installation
7/22/2019 September 2005 Muon Week
26
Muon layout 7/22/2019 September 2005 Muon Week
27
Muon Summary In all cases of installation to date there have been problems in achieving the positional accuracy required. Typically play in brackets and bow of rails. Rail alignment, survey and adjusting is very time consuming. Rail & bracket delivery just in time!!!!! Services installation concerns. Connection to installation frame – watch pitch and “Z”. Lifting beams inc TIS approval will be dealt with at Work-package and PPSPS meeting in future. Also to include procedure. BML & BOL rail installation hit by many small clashes with bolt heads, feet, brackets. All relatively trivial items but each takes many hours to fix. “Z” survey target required on all rails. 7/22/2019 September 2005 Muon Week