Download presentation
Presentation is loading. Please wait.
Published byHaven Booty Modified over 10 years ago
1
1.040/1.401 Project Management Spring 2007 Lecture 9 Deterministic Planning Part II Dr. SangHyun Lee lsh@mit.edu Department of Civil and Environmental Engineering Massachusetts Institute of Technology
2
Project Management Phase FEASIBILITY CLOSEOUT DEVELOPMENT OPERATIONS Fin.&Eval. Risk Estimating Planning & Scheduling DESIGNPLANNING Organization
3
Outline Network Techniques Network Techniques CPM CPM PDM PDM Linear Scheduling Method Linear Scheduling Method
4
Precedence Diagram Method (PDM) A (10) B (10) A 10 B 10 Gantt chart CPM (AON) Activity B will start right after Activity A finishes A (10) B (10) Activity B will start right after Activity A starts
5
Precedence Diagram Method (PDM) PDM Extends CPM to include PDM Extends CPM to include Multiple relationships beyond Finish-to-Start Multiple relationships beyond Finish-to-Start Finish-to-Finish Finish-to-Finish Start-to-Start Start-to-Start Start-to-Finish Start-to-Finish
6
PDM – Types of Relationships FS Finish-to-start FS Finish-to-start SS Start-to-start SS Start-to-start FF Finish-to-finish FF Finish-to-finish SF Start-to-finish SF Start-to-finish A B A B A B A B
7
Precedence Diagram Method (PDM) A (10) B (10) A 10 B 10 Gantt chart CPM (AON) Activity B will start after Activity A finishes A (10) B (10) (5) Activity B will start 5 days later after Activity A finishes A 10 A5A5 B 10
8
Precedence Diagram Method (PDM) PDM Extends CPM to include PDM Extends CPM to include Lag (+) & Lead (-) Lag (+) & Lead (-) A (10) B (10) FS (+5) A (10) B (10) FS (-5)
9
PDM Relationships w/ Lag & Lead Finish-to-Start Lead Finish-to-Start Lag Start-to-Start Lead Start-to-Start Lag FS +14 FS -1 SS -1 SS +1 Lay-Out & Excavate Install Fuel Tanks Pour 4th-Floor Slab Remove 4th Floor Shoring Backfill Pipe Install Pipe Install Fuel Tanks Install Exterior Conduits Adapted from: Callahan et al., 1992
10
Finish-to-Finish Lead Finish-to-Finish Lag Start-to-Finish Lead Start-to-Finish Lag FF -1 Form Slab on Grade Reinforce Slab on Grade SF +10 Install Wood Paneling & Base Install Carpeting FF +3 Excavate Trench Lay Pipe SF -1 Prepare Wall Shop Drawings Approve Adapted from: Callahan et al., 1992 PDM Relationships w/ Lag & Lead
11
Slack or Float in PDM n Total Float (TF) TF(k) = LF(k) - ES(k) - D k n Start Float (SF) SF(k) = LS(k) - ES(k) n Finish Float (FNF) FNF(k) = LF(k) - EF(k)
12
PDM Example Source: Callahan et al., 1992 TF D ES LS EF LF SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30
13
Forward Pass Source: Callahan et al., 1992 TF D 0 LS 0 LF SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 30s ES = 10s EF + Lag (FS)
14
Forward Pass Source: Callahan et al., 1992 TF D 0 LS 0 LF SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 7 9 4 8 6 12 15 9 17 100s ES = 90S EF 100s ES = 70s EF MAX
15
Backward Pass Source: Callahan et al., 1992 TF D 0 0 SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 7 9 4 8 6 12 15 9 17 15 17 14 17 9 15 70s LF = 100S LS 70s LS = 80s LF - 1 MIN
16
Backward Pass Source: Callahan et al., 1992 TF D 0 0 0 0 SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 7 9 4 8 6 12 15 9 17 15 17 14 17 9 15 7 9 8 14 5 9 4 6 1 5 0 3 1s LF = 10S LS 1s LF = 20s LS MIN
17
Total Slack or Float Source: Callahan et al., 1992 0 D 0 0 0 0 SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 7 9 4 8 6 12 15 9 17 15 17 14 17 9 15 7 9 8 14 5 9 4 6 1 5 0 3 0 0 0 0 0 0 22 11 TS or TF = LF - ES - D
18
Critical Path Source: Callahan et al., 1992 0 D 0 0 0 0 SF FNF START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 7 9 4 8 6 12 15 9 17 15 17 14 17 9 15 7 9 8 14 5 9 4 6 1 5 0 3 0 0 0 0 0 0 22 11
19
Start & Finish Slack or Float Source: Callahan et al., 1992 0 D 0 0 0 0 0 0 START 1 3 4 B GC 20 2 D EL 40 4 E ME 50 6 F GC 60 6 H ME 80 3 G EL 70 0 FINISH 100 2 K ME 90 1 3 2 1 A GC 10 2 C GC 30 0 3 4 6 0 4 7 9 4 8 6 12 15 9 17 15 17 14 17 9 15 7 9 8 14 5 9 4 6 1 5 0 3 0 0 0 0 0 0 22 11 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 1 1 1 1
20
PDM Caveat: Vanishing Critical Path Tracing critical path can be difficult Tracing critical path can be difficult Finish-finish constraints with leads can lead to vanishing critical path Finish-finish constraints with leads can lead to vanishing critical path FF -5 Total float Duration
21
PDM Caveat - Counter-Intuitive A30 A20 FF 2 A10 SS 0 Tracing critical path can be difficult Tracing critical path can be difficult Can be counter-intuitive Can be counter-intuitive The longer A20 is, the smaller the critical path duration and quicker can complete!
22
Slack or Float Ownership Tension between owner and contractor Tension between owner and contractor Significant legal implications Significant legal implications Problem: Problem: Owners seek to push contractors on tight schedule Owners seek to push contractors on tight schedule Too many late starts risk overall project duration Too many late starts risk overall project duration Contractors seek flexibility Contractors seek flexibility Flexibility has value Flexibility has value
23
Outline Network Techniques Network Techniques CPM CPM PDM PDM Linear Scheduling Method Linear Scheduling Method
24
Linear Scheduling Method (LOM) Line-of-Balance Line-of-Balance Time + Location Time + Location Repetitive Linear Activities Repetitive Linear Activities Rate of Progress (production rate) Rate of Progress (production rate)
25
LSM Diagram Source: Callahan et al., 1992
26
Plotting Activity Progress Lines Source: Callahan et al., 1992
27
Use of Restraint on LSM Diagram Source: Callahan et al., 1992
28
Activity Interference Source: Callahan et al., 1992
29
Use of Activity Buffers in LSM Schedules Source: Callahan et al., 1992
30
LSM – Example LinearPlus
31
LSM – Example Tilos
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.