Presentation is loading. Please wait.

Presentation is loading. Please wait.

PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.

Similar presentations


Presentation on theme: "PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams."— Presentation transcript:

1 PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams

2 Agenda Dependencies Milestones The Network –Early/Late Start/End dates –Slack/Float –Critical Path

3 To Create a Plan You Need… Work Breakdown Structure Dependencies Milestones The Network Early/Late Start/End dates Slack/Float Critical Path

4 Task Dependencies Task A is said to be dependent on task B if task B must precede task A (task B must be finished before task A can start) Task B is called a predecessor of task A Task A can have many predecessors Only immediate predecessors are referred to as predecessors

5 Agenda Dependencies Milestones The Network –Early/Late Start/End dates –Slack/Float –Critical Path

6 Milestone A task with zero time allocated to it. It is used as a marker; documentation. It is not assigned to anyone. Tasks can be dependent on milestones.

7 Agenda Dependencies Milestones The Network –Early/Late Start/End dates –Slack/Float –Critical Path

8 Network Diagram A pictorial representation of the sequence in which the project work can be done Shows the relationships (dependencies!) between tasks MS Project creates network diagrams for you (=Gantt chart in MS Project)

9 Network Diagram What order do I do these tasks in?

10 Network Diagram 1.1 Measure Room 1.2 Choose colors 1.3 Create Materials List 1.4 Create Estimate Sheet 1.5 Review with client 2 Purchase Materials 3.1 Move Furniture 3.2 Wash Walls 3.3 Cover Floors 4 Paint Room 5.1 Clean up 5.2 Remove Floor Covers

11 Network Diagram = Gantt Chart 1.1 1.2 1.31.41.5 2 3.13.23.3 4 5.15.2

12 Why are they important? You can plan more effectively--you can see the relationship between activities Easier to reschedule--you can see impact of changes Allows you to monitor and control the project--compare it against baseline

13 Identifying Dependencies Dependencies are caused by constraints: Technical constraints –Discretionary –Best practices –Logical –Unique situations

14 Identifying Dependencies Dependencies are caused by constraints: Management Inter-Project

15 Calculating Slack/Float What is the earliest/latest possible start of each task?

16 Late and Early Start/Finish Early start/finish--earliest possible time that a task can start/finish without causing delay Late start/finish--latest possible time that a task can start/finish without causing delay

17 Early Start/Finish ES = latest finish of predecessors + 1 EF = (ES + duration) - 1

18 Early Start/Finish 1.1 1 1.2 2 1.3 1 1.4 3 1.5 1 2.1 2 2.2 1 2.3 1 2.4 2 581 2 2 2 6 6 6 3 2 4 15 7 6 6 9

19 Late Start/Finish LF = earliest start of successors - 1 LS = (LF - duration) + 1

20 Late Start/Finish 1.1 1 1.2 2 1.3 1 1.4 3 1.5 1 2.1 2 2.2 1 2.3 1 2.4 2 581 2 2 2 6 6 6 3 2 4 15 7 6 6 9 98 6 7 7 7 7 7 55 4 4 4 4 3 2 11

21 Agenda Dependencies Milestones The Network –Early/Late Start/End dates –Slack/Float –Critical Path

22 Slack/Float time The delay (in units of time) that could be tolerated in starting or completion time of a task without causing a delay in the project. Slack time for a task = LF - EF

23 Slack Time = LF - EF 1.1 1 1.2 2 1.3 1 1.4 3 1.5 1 2.1 2 2.2 1 2.3 1 2.4 2 581 2 2 2 6 6 6 3 2 4 15 7 6 6 9 98 6 7 7 7 7 7 55 4 4 4 4 3 2 11 0 1 2 0 0 0 1 1 0

24 Agenda Dependencies Milestones The Network –Early/Late Start/End dates –Slack/Float –Critical Path

25 Critical Path Longest duration path in network diagram Sequence of tasks whose early and late dates are the same Sequence of tasks with zero slack

26 Critical Path 1.1 1 1.2 2 1.3 1 1.4 3 1.5 1 2.1 2 2.2 1 2.3 1 2.4 2 581 2 2 2 6 6 6 3 2 4 15 7 6 6 9 98 6 7 7 7 7 7 55 4 4 4 4 3 2 11 0 1 2 0 0 0 1 1 0

27 Why care about Critical Path? Tasks on this path need to be on time! If you know what they are you can track them! You can compress, adjust for maximum benefit

28 Critical Path MS Project automates this! Lets look at an example

29

30 Critical Path 1.1 1 1.2 2 1.3 1 1.4 3 1.5 1 2.1 2 2.2 1 2.3 1 2.4 2 3.1 13.2 24 2 2.4 2

31 Critical Path


Download ppt "PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams."

Similar presentations


Ads by Google