1 Run Coordinator Report for PVDIS (E08-011)
Yi Qiang Duke University Nov 11, 2009 Good day, everyone… My name is Yi Qiang. I’m from Duke University … Today, I will talk about the Transverse momentum-dependent structure of the nucleon. 11/10/2009 Hall A RC Report

2 Current status Detectors and DAQ are pretty much ready
Took some production data with R-HRS Cryogenic works ongoing Compton suffers high background rates Left dipole magnet is down 11/10/2009 Hall A RC Report

3 Daily Report Nov 3, Tue, 2009 Nov 4, Wed, 2009
Finished detector installation Beam tuning to the Hall Nov 4, Wed, 2009 Compton tuning PITA scan Moller commissioning Target cool down and detector/DAQ work Beam to the Hall 11/10/2009 Hall A RC Report

4 Daily Report Nov 5, Thu, 2009 Bull’s eye scan and raster adjustment
Left detector gain-matching Work on right HRS Q2 Commissioned cryo-target, 85uA on target LUMI HV adjustment for high current 11/10/2009 Hall A RC Report

5 Daily Report Nov 6, Fri, 2009 Q2 measurement with L-HRS
Boiling test on LD2 target Access to fix HRS Q2 Moller measurement: 87.4% 11/10/2009 Hall A RC Report

6 Daily Report Nov 7, Sat, 2009 Optics runs Access to PVDIS DAQ work
Target position scan: found bottom wall Magnet Tripped due to cryo fluctuation then recovered Continue PVDIS DAQ tune, ready for production 11/10/2009 Hall A RC Report

7 Daily Report Nov 8, Sun, 2009 Another sets of Optics run
Magnet tripped again, right HRS recovered First production with R-HRS and 100 uA beam An access to fix R-HRS helicity signal Continue production Compton tuning Magnet tripped … Access for more R-HRS DAQ works 11/10/2009 Hall A RC Report

8 Daily Report Nov 9, Mon, 2009 Nov 10, Tue 2009
Production with R-HRS only Access to Magnet and Cryo works Compton tuning, background still high Target aperture scan, pretty well centered Nov 10, Tue 2009 Production with 90 uA and R-HRS Magnets down one more time … Null vertical spin in injector Magnet/Cryo works ongoing … 11/10/2009 Hall A RC Report

9 Pending works Compton tuning tomorrow (Wednesday) Moller measurement
Inject study for future Moller systematic measurement. Needs to be arranged with Hall B since it’s destructive to Hall B. More tuning of detectors and DAQ Cryo and magnets Production!!!!! 11/10/2009 Hall A RC Report