1 Microsoft Project 2010 Demo Part 3

2 Problem 1.2 Enter tasks, times, and sequence requirements for problem Be sure to click Project/Project Information to set project starting date. Calculate mean task times by hand, using a spreadsheet, or using Find critical path.

3 Insert Rows for More Tasks
To insert rows for summary tasks or subtasks, hold cursor on task that will go below new task and right click Insert Task.

4 Indenting Tasks To create subtasks or summary tasks click Task and then the green arrow icons. This will create indented tasks.

5 Cost and Material Resources
To add costs, material resources, or additional labor resources, you can go to View/Resource Sheet. You can define resources and fill in information as seen below.

6 Add Cost Column(s) To add a column of data go to a blank column (labeled Add New Column), scroll down the menu and choose the appropriate item such as Cost.

7 Printing Results First be sure results show on computer screen nicely. Then go to File/Print. See print screen below. Please conserve on pages printed. Be green!

8 Beware of Indicator Icon
To remove indicator, double click task with icon. Open the Advanced tab. Set constraint type to “as soon as possible”.

9 Beware of Indicator Icon
Completed removal step is shown below.