1 Southwood/Fargo Country Club Flood Risk Management Project
Neighborhood Meetings July 20, 2011

2 Southwood/Fargo Country Club
HOW WE GOT HERE PETITION RECEIVED THIS PAST WINTER FROM NEIGHBORHOOD REQUESTING A LEVEE PROJECT IN REAR YARDS EMERGENCY LEVEE CONSTRUCTED PRIOR TO THIS PAST SPRING’S FLOOD

3 Southwood/Fargo Country Club Emergency Levee – As Built
BUILT TO AN ELEVATION OF 44-FEET

4 Southwood/Fargo Country Club – Across Course Levee
ALIGNMENT DESIGNED BY FARGO COUNTRY CLUB’S ARCHITECT ONLY POSSIBLE ALIGNMENT ACROSS THE COURSE THAT WILL NOT RESULT IN SAFETY ISSUES FOR THE COURSE PORTION OF SOUTHERN END WITHIN THE FLOODWAY

5 Southwood/Fargo Country Club – Across the Course Levee
GEOTECHNICAL STUDY COMPLETED STUDY SHOWED THAT THE FACTOR OF SAFETY FOR THE LONG TERM STABILITY WOULD NOT BE MET ANALYSIS DID NOT FACTOR IRRIGATION OF DRIVING RANGE INTO IT

6 Southwood/Fargo Country Club – Permanent Levee Option
CLOSELY FOLLOWS EMERGENCY LEVEE ALIGNMENT ACTUAL ALIGNMENT WILL BE REVIEWED FURTHER CENTERED ON PROPERTY LINES FROM 521 TO APPROXIMATELY 909 SOUTHWOOD DRIVE BUILT TO AN ELEVATION OF 42.5-FEET PLUS 1-FOOT

7 Southwood/Fargo Country Club – Schedule
JULY 20, 2011 – PUBLIC MEETING JULY 27, 2011 – BACKYARD WALKTHROUGH AUGUST 22, 2011 – CALL FOR BIDS SEPTEMBER 14, 2011 – OPEN BIDS SEPTEMBER 19, 2011 – AWARD BIDS OCTOBER 3, 2011 – CONTRACT AWARD, CONSTRUCTION BEGINS SHORTLY AFTER SPRING 2012 – FINAL COMPLETION FALL 2012 – PHASE 2 CONSTRUCTION FUTURE NEIGHBORHOOD MEETINGS WILL BE HELD

8 Questions?


Download ppt "Southwood/Fargo Country Club Flood Risk Management Project"