Download presentation
Presentation is loading. Please wait.
1
South Ulverston Mapping and Modelling Study
Ulverston Flood Alleviation South Ulverston Mapping and Modelling Study November 2018
2
South Ulverston Mapping and Modelling Study
November 2018
3
Progress Update Tidal, fluvial and surface water flood risk
M&M Phase 1 Feb 2016 – October 2018 Phase 2- March 2019 Partnership working with CCC/UU Min 200 affected residential properties and numerous commercial
4
Progress Update Economic assessment
All models complete Engagement with LLFA (CCC) & UU underway Initial Assessment complete Economic assessment Tidal risk not feasible to solve right now 100 year fluvial flood risk- various climate change epochs
5
Surface Water flood risk -1 in 30 years
6
100 year fluvial flood risk- various climate change epochs
7
Initial Appraisal Completed First step Caveats Assumptions
To understand fundamentally what is feasible and what is affordable Initial ‘what can we do?’ Not final May change Working with CCC/ UU extensively No funding to deliver currently
8
What could a scheme look like?
No funding in this current period from any partners currently Strong partnership working with UU/ LLFA/ EA Will need to involve other stakeholders Raising embankments and storage areas Linear defences Diverting existing surface water flow paths Culvert upsizing Pumping station Surface water & River flooding
9
What next? Strategic Outline Case- March 2019 Funding future -20/21
Delivery of outcome measures
10
What do we need from you? Engagement of residents
Circulation of newsletter/ resources Continue support
11
Any Questions If you would like further information, please contact us: Queries to Jayne Kendall Write: Ghyll Mount, Gillan Way, Penrith 40 Business Park, Penrith, Cumbria, CA11 9BP Follow on