Undulator Assembly and Installation Planning
Rodd Pope, SLAC
2
By Scott Doran, ANL UNDULATOR CELL ASSEMBLY
NEXT CELL UNDULATOR SHOWN FOR CLARITY
3
By Scott Doran, ANL UNDULATOR CELL ASSEMBLY
NEXT CELL UNDULATOR SHOWN FOR CLARITY
4
Collaboration Roles and Responsibilities (abridged)
ANL – Stephen Milton Geoff Pile Design the System and Sub-assemblies minus WPM/HLS Supply Designed Sub-assemblies Provide Expertise SLAC Metrology – Robert Ruland Design and Supply WPM/HLS System Undulator Tuning & Quadrupole Measurement Develop and Test Fiducialization Procedures SLAC Assembly & Installation – Ben Poling Girder Assembly System Installation Material Handling and Storage
5
Assembly, Installation, and Maintenance Group
Undulator Assembly, Installation and Maintenance Group (U-AIM) Supervisor – Ben Poling Principal Technician – Ed Akerstrom Principal Technician – Nick Horton Material Handling, Assembly Preparation, Installation Planning Three Engineering Assistants Michelle Chan, William Rowan, Austin Schuh Summer Support of Design, Engineering, Production Activities
6
Assembly – Installation Outline
Receive Assemblies, Sub-assemblies, and Kits Inspect, Modify, Store Girder Rough Assembly Girder Precision Assembly Anchor Installation (Davis-Bacon) Pedestal Installation (Davis-Bacon) Girder Installation (Davis-Bacon) and Mover Startup Vacuum System Completion WPM/HLS Installation and Startup Undulator Magnet Installation
7
Assembly, Install, & Storage Space
Undulator Tunnel B081 – MMF Tuning/Fiducialization - B033 GLAST: Limited space, other groups vying for space - B006 SSRL/ILC: More limited space than B033, requires ~$30k to cleanout - B750: Much space, dirtiest, access may be limited by construction B750 – Storage/Assembly
8
Undulator System Girder Assembly
Precise/Vacuum Assembly performed in a control environment Field Installation
9
SLAC Magnetic Measurement Facility Wolf, Zachary, LCLS Management Presentation, April 11, 2006, Slide 3 Floor plan divided into three functional areas Magnetic Measurements (± 0.1º C) Fiducialization and Assembly (± 1º C) Storage (± 2.5º C) Assembly Area Storage and Queuing LCLS-TN-04-1
10
Schedule, Summary
11
Component Delivery Schedule – 7/10/07
Actual Plan
12
Component Deliveries by 1/10/2007 (+6 Months from Now)
13
Next Six Months WPM and HLS Hardware Delivered Undulators RFI
Component Deliveries Minus RF BPMs and Vacuum Chambers Cable Plant Design Review Complete Procurements Placed for Materials and Labor Early Occupancy of Undulator Hall Pedestal Installation Contract Let Girder Installation Contract Out for Bid
14
End of Presentation
15
Component Delivery Schedule – 2/10/07
16
By Scott Doran, ANL SHORT BREAK
17
SHORT BREAK CROSS SECTIONS
By Scott Doran, ANL SHORT BREAK CROSS SECTIONS
18
By Scott Doran, ANL LONG BREAK
19
LONG BREAK CROSS SECTIONS
By Scott Doran, ANL LONG BREAK CROSS SECTIONS
20
Component Delivery Schedule
21
Girder Assembly Flow ANL Supplied ANL Supplied