1 AE Title III Status Introduction
Jacobs’ full time, on-site Representative (since 26 July’06), Co-located with CF Group. Function is to represent the Designer and work as part of the LCLS Conventional Facilities Team. Recent DOE project experience was as one of two full-time on-site design team representatives on SNS project.

2 AE Title III Status Background
Jacobs was responsible for the Title I and II design of the Conventional Facilities including the CLOC. Jacobs is currently performing Title III Services during construction as described in AIA Document B141 and as amended by letter of agreement between SLAC & Jacobs

3 Title III services include the following:
AE Title III Status Title III services include the following: Response to design related requests for information (RFIs) during the Bidding process. Response to CM/GC and subcontractor generated RFIs. Review of subcontractor Submittals and Requests for Substitution.

4 AE Title III Status Site Visits by the design leads at appropriate times during construction All Scope Changes are handled through the previously established DCN process Completed VE redesign on 16 October 2006 SLAC/Jacobs currently evaluating impact of CLOC deletion on remaining scope. .

5 Jacobs On-site CA Manager
AE Title III Status Jacobs Off-Site Organization LCLS Dave McDonough Jacobs MOP Jim Cranston Jacobs On-site CA Manager Turner Construction Cypress Project Management Boston Portland Walnut Creek

6 Bid RFI’s -180 (15days) Contractor RFI’s - 58 (9days)
AE Title III Status RFI’s Reviewed Bid RFI’s -180 (15days) Contractor RFI’s - 58 (9days) Projected turn- around time = 5 Days Jacobs SLAC Turner Total Type 176 54 8 238 A (20 hrs) 18 B (10 hrs) 106 C (6 hrs) 52

7 Submittals Status: AE Title III Status Forecast (Line Items) 1437
Projected turn-around time = 10 days Current Average Turn-around time = 12 days* * After removal of several anomalies. Forecast (Line Items) 1437 Received 35 Processed 20 Under Review 15

8 AE Title III Status Management Goals
Reduce turn-around time for review of RFI’s and Submittals Improve response time to Design Modification requests Continue improvement of communications between SLAC, Turner and Jacobs

9 AE Title III Status Questions?