1 ctcLink Steering Committee
May 21, 2019 Choi Halladay - ctcLink Steering Committee Chair, Vice President for Administrative Services, Pierce College District Christy Campbell – ctcLink Project Director

2 AGENDA Item Description Duration Facilitator 1. Welcome Christy 2.
Christy 2. Approval of Minutes 1 Minute Choi 3. Steering Committee Charter Subgroup Update 10 Minutes All 4. Campus Solutions Global Design Review (GDR) – Discussion, Approval John Henry 5. Project Manager (PM) Summit – Outcomes 5 Minutes Reuth 6. Remediation Update (including Replacement Solutions) Remediation Overview (CCS, TCC Updates) Chart of Accounts Security Redesign – Mapping Online Admissions Application (OAA)– Tentative recommendation from WSSC to ctcLink Governance Continuing Education – Update from 5/20 vendor meeting Accessibility RFP Update Budgeting Tool 30 Minutes 7. Risks / Moran QA Report – April 2019 Reuth/Paul 8. ctcLink Program Status Deployment Group 2 (Training, Testing, Deployment) Deployment Group 3 (BPFG, Data Validation) Deployment Group 4 (Initiation) Deployment Group 5 (Half Day PM Summit/Early Visits) 20 Minutes 9.  Action Items Review and Agenda Items for Future Meetings 4 Minutes 10. Meeting Closure

3 Meeting Minutes – Approval
May 7, 2019

4 Steering Committee Charter Review
SC Charter – Subgroup Update for progress Executive Sponsor Role Project Manager Role Alignment of all Governance Charters to include verbiage to not allow individuals to be voting members of two governance groups

5 Campus Solutions Global Design
Overview Summary Discussion Approval

6 Spring PM summit Held May 6-8 at Wenatchee Valley College Outcomes
May 6-7: All Colleges (implementation activities) May 8: DG5 & DG6 (DG4 optional) focused on Getting Ready for Implementation (Initiation Activities) Outcomes All colleges now have an implementation schedule. All colleges have a clear understanding of all work packages required to complete prior to implementation. Some colleges do not have a dedicated Project Manager, but this does not mean they are on hold.

7 Pilot remediation overview & status
Date Total Open Items Open Items With a Plan to Complete (Appendix A) Open Items Needing a Replacement Solution (Appendix A) Open Items That Were Closed, but Reopened in Remediation Agreement (Appendix B) 2016, 2017, 2018 Financial Books Close and Reconciliation Framework Continuing Education Online Admissions Budget Planning Financial Aid Customizations 11/29/17 195 101 10 84 12/13/18 41 29 2 4/01/19* 22 11 1 *FirstLink (pilot) colleges are validating open and closed items/numbers

8 ctcLink Remediation Status Reports – April 29 to May 10, 2019
Solution Status Due Date Campus Solutions 10 of 45 remain open DG3 Financial Management 5 of 39 remain open DG2 Human Capital Management 6 of 25 remain open Faculty Workload Complete March 2019 DRS Redistribution May 2019 Absence Management April 2019 Security Audit Controls Security Redesign Mapping Framework FLC / DG2 Student Billing/Third-Party Billing In UAT May 2019 Budget Planning Form Work Group Jan 2020 Online Admissions App Governance Continuing Education Vendor Negotiations Chart of Accounts (revised) Due/Finish Status Tacoma CC Chart of Accounts Adoption Kickoff Dec. 12, 2018 Complete CCs of Spokane Chart of Accounts Adoption Kickoff Feb. 1, 2019 Foundational Chartfield Configuration March 22, 2019 College Configuration Review and Updates May 3, 2019 In Progress Functional and System Integration Testing May 10, 2019 User Acceptance Testing May 10 - June 3, 2019 Not Started Readiness Gate / Go-No Go Decision June 10, 2019 Production Cutover July 2019 Community Colleges of Spokane R Remediation Items progress this period Student Statements – Pending second SIT/UAT – scheduled for 5/21. Security Audit Controls – In progress. CCS to review/validate users/security roles for new query tree design for non-sensitive data. Accurate Reporting for DRS & PEBB – Pending SIT/UAT, scheduled for 5/13. Third-Party billing – Pending SIT/UAT – scheduled for 5/21. FY Close – see previous slides. Book to Bank - Cash Reconciliation. Focus now is on reconciling the three cash accounts making up our $18 million variance (same accounts for TCC). Pending reports/workflow of behind the scenes ctcLink processing of the transactions going into these accounts. Can’t close FY 16,17,18 without reconciling cash accounts. *If status is yellow or red, describe why. FY Close Can’t close FY 16, 17, 18 without reconciling cash accounts , , & Still waiting for SBCTC on reports/workflow into these the 3 cash accounts. High level T-Account flow presented last week inadequate. This work is critical to CCS closing FY. Security Role Redesign - Waiting on final documents to assist with role mapping and cutover/implementation process for from SBCTC. Waiting on process documentation and rollout of audit reporting and separation of duties. Tacoma Community College G Remediation Items progress this period See SBCTC status update for Remediation items, tickets, and worklist. Planned for next period Receive detail for open and closed remediation tickets from Christy and team. 1st requested March 27, follow-up April 12; second follow-up May 10

9 Other ctcLink Project Activities – Status as of May 10, 2019
New Solution Status RFP Publish Solution Decision Continuing Education RFP was developed and approved by Governance RFP proposals due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Governance approved procurement and decision of Vendor Vendor has been contacted to begin negotiations to contract 10/15/2018 Negotiations subgroup assisting with final negotiations Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft universities and colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions on 2/12/2019 Work Group to review feedback from college discussions to provide recommendation Commission (WSSSC) to provide recommendation to Governance TBD Waiting for recommendation to Governance for Decision Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution If needed, develop RFP January Waiting on Budget work group to meet and vet requirements Physical Inventory (Asset Tracking) Vendor Solutions being evaluated Evaluate new PS Functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/2018 DG3 (February 2020) Accessibility Continued discussions with Appsian (formerly Grey Heller) Identify accessibility vendor to assist with testing of ctcLink Develop RFP / Publish RFP Work Group will be engaged post publish to allow for feedback and amendment 5/10/2019 Testing Prior to DG2 (October 2019)

10 Top Risks Reported – as of May 10, 2019
LEGEND: Critical High Moderate Low C H L M Risk Level Risk Description Mitigating Actions Submitted by (name, org/college), Deployment Group & Date Risk Owner (s) H Chart of Accounts (CoA) – User adoption and successful deployment (scheduled for July 1, 2019) is critical for Deployment Group 2 (DG2) timeline. Update: In progress for college configuration review and updates, functional and system integration testing. *Refer to CoA milestones tracking in this report. Emmett Folk, ctcLink PM for FIN & HCM Team DG2 Impacted, Risk Date: 10/12/2018 *also Risk submitted by Matt Connelly, Spokane District PM on 10/23/18 Emmett Folk Clark: Financial Aid (FA) Data Validation – not well validated. First time seeing FA data is in cycle #4.   Clark requested to test and validate data in cycle# 4B. ctcLink team has discussed this with FA SMEs, this will be taken care of in cycle #4B.   Susan Maxwell, Clark PM DG2 Impacted, Risk Date: 4/17/19 John Henry Whatley, Chandan Goel C Clark: Impact to college Continuing Education (CE) program - seems likely Clark will start with OSECE and possibly move to CampusCE. Decisions are dependent on cost for CampusCE, support for OSECE and impact to students. Update: ctcLink team has met to discuss options for OSECE and CampusCE. We are preparing to deploy OSECE and waiting on contract negotiations for CampusCE RFP. CampusCE group is meeting next week.   DG2 Impacted, Risk Date: 3/15/2019 John Henry Whatley, Dennis Colgan Top Issues Reported – as of May 10, 2019 LEGEND: High Moderate Low H M L Issue Level Issue Description Status Update Submitted by (name, org/college), Deployment Group & Date Issue Owner (s) H Security Mapping activities to mitigate UAT timeline, have not addressed the new Security Design Production user  access  Update: The ctcLink team is highly concerned about the Production Security Mapping for DG2 Colleges and entering new Security into one of the UAT cycles.  Although there are no other options due to the schedule, this will be a challenge for the DG Colleges and SB as well as potential impact to the remaining UAT cycles.  ctcLink PMO submitted for ctcLink CS, HCM, FIN Team DG2 Impacted, Issue Date: 4/16/2019 Tara Keen, Security Team L CS GDR (Global Design Review) Items – Six items listed in status update. Items were approved by Working Group and will go to Steering Committee next week for approval. These items need additional work. Tracking GDR items: (statewide accounts, shared HCM/CS ethnicity codes, academic careers, academic program structure, student self-service & student self-service (instructor contact display). John Henry Whatley DG2 Impacted, Issue Dates: 5/15/19 CS Team & Further Analysis/Decisions with Commissions & Councils

11 Y ctcLink Quality Assurance Scorecard Overall Status
Moran Technology Consulting Report: April 2019 Overall Status Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 STATUS PROJECT AREA DESCRIPTION / NOTES G SBCTC/Governance Governance framework continues to work as expected. Meetings are held according to schedule, with materials distributed beforehand, and decisions made at the appropriate level. Project Management Project Management Office (PMO) is fully staffed, working well together and continuing to address improvements in project management processes. Y Phase Scope QA remains concerned about the number of solutions to be re-implemented to replace/augment current PS functionality and that timing and resource availability could negatively impact DG2/DG3 scope and schedule.  Schedule Status DG2/DG3/DG4 schedule overlap and resource constraints directly impact all deployment groups. Schedule compression and key project resources are heavily allocated to multiple DG2 workstreams and supporting DG3 tasks.  Training This work stream is yellow, but is trending green due to the decisions and actions taken by PMO have enabled recovery of this key workstream. DG2 success dependent on active end-user participation, assessments and college follow-up. Testing This work stream is yellow, but trending green due to changes made by the PMO.  DG2 UAT Sprints supported by training materials began in April and run through August.  DG2 testing workstream remains a concerns since it relies heavily on availability and expertise of functional project staff. Configurations / Data Conversion Technical work for DG2 System Configurations and Data Conversion Cycle 4 continues with good results reported. QA considers it an important achievement that Clark College is now live in the ctcLink Production Environment with user maintenance of their course catalog. Organizational Change Management (OCM) PMO/OCM is actively engaged with all colleges now involved with their Deployment Groups. QA concerned that PMO focus remains on the DG2 schedule. Project Staffing Project staffing is adequate at this time and continues to make staffing adjustments as appropriate. QA and the PMO remain concerned that the overlap of DG2/DG3/DG4 may require additional project and contractor resources. Project leadership and staff morale is positive given schedule pressures.  PMO is recruiting for seven open positions.  Technical Environment Future PS updates/bundles and third-party software installation and support work is being managed by the IT Division outside of the project responsibility. Overall planning of these changes needs to be tightly integrated with the ctcLink DG2/DG3/DG4 schedules. This becomes more challenging with the overlap in implementation schedules. Draft SLA agreement has been distributed to the colleges. LEGEND GREEN YELLOW RED Risk Description: Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost.

12 Ctclink program status
Deployment Group 2 (Training, Testing, Deployment) Deployment Group 3 (BPFG Homework, Data Validation) Deployment Group 4 (Initiation/Reporting) Deployment Group 5 (July Visits/Reporting/Initiation) Deployment Group 6 (Fall Visits, Initiation Schedule)

13 Project Status – April 29 to May 10, 2019
Overall Project Status Summary Category Status Comments Overall Y Program is on track, per timeline, scope and budget Security Mapping activities impacting UAT Current DG2 Schedule has no “Float” remaining in timeline Schedule Monitoring scope and timing of: Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Scope Requirements Traceability Matrix (RTM) needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Budget G Currently tracking under budget New Technology Plan approved as well as Stage Gate #3 for OFM/OCIO Technology Pool funding Executive Summary The project is tracking per schedule and under budget. Review and definition of scope for each deployment continues due to the rework of key solutions. Each Deployment Group (DG) is now engaged: DG2 is in the Construct Phase and colleges and SBCTC have begun User Acceptance Testing. ctcLink governance approved the DG2 Go-Live schedule. ctcLink will be offline for the upgrade Oct and again for cutover activities Oct   DG3 is in the Structure Phase, focused on Business Process Fit/Gap sessions (BPFG) through May. DG4 is in the Initiation Phase, with most colleges just past the halfway mark on deliverables. Gate 1 Peer Review will be in late July. DG5 colleges have begun Initiation Phase and are learning the public status reporting process. DG6 has begun the initiation phase and will start the public reporting process this fall. The spring 2019 Project Managers Summit was held May 6-8 at Wenatchee Valley College, with May 6-7 focused on overall Implementation Phase activities for all colleges and May 8 focused on DG5 and DG6 Initiation Phase. All Colleges now have an Initiation Work Plan or Implementation Work Plan. Contract negotiations are underway for a new Continuing Education solution. The Online Admissions Application (OAA) work group is actively pursuing an OAA replacement. The Budget Planning Tool work group is reviewing and finalizing business and technical requirements. Overall Status Summary per Deployment Group DG# Status Comments DG2 Y Security Production Mapping is still pending DG3 G BPFG Workshops Complete Conversion cycles have begun DG4 College teams working on Initiation Phase activities DG5 8 Colleges have downloaded Initiation Plan DG6 9 Colleges have downloaded Initiation Plan Overall Timeline (All Deployments)

14 Additional Discussion

15 Questions?

16 Remediation Open – Finance
# Item # Description Status Planned Date Adjusted Date 1 19057 Ability for each organizational unit to develop and modify a budget at any level of the organizational structure and at any level of the program structure, throughout the budget development process. Open DG3 2/1/2020 Needs RFP 2 19297 Distribute and report labor costs based on user-defined criteria, with full integration and reconciliation of data between GL, Payroll, and Student. Closed 8/1/2018 Updated Training Content 3 19299 Provide a journal entry toolset, including but not limited to a standardize spreadsheet template, to facilitate streamlined journal entry and upload. 4 19304 Standardize sub-objects and mapping to a system-wide structure for each unique GL created at the college-level. 1/1/2018 7/1/2019 New COA Design 5 19323 Supports GL account verification across applications. 2/1/2018 TBD FY Deliverable 6 19342 Support vendor payment advance process based on user-defined criteria (e.g., each college is authorized to draw an advance against the State Treasurer, with the amount equal to 17% of preceding biennium's monthly allocation). 12/1/2017 SB Process Provided 7 19382 Integrate seamlessly with receivables processes to collect funds from vendors and recover overpayments.

17 Remediation Open – Finance, cont’d
# Item # Description Status Planned Date Adjusted Date 8 19454 Create and maintain as many payment forms and templates, including remittance detail, as required to meet institutional needs and local needs of individual colleges. Closed 8/1/2018 Updated Training Content 9 19633 Enable reconciliation process based on user-defined business rules (e.g., able to identify transaction source). Open 1/1/2018 TBD FY Deliverables 10 19747 Calculate and report indirect costs based on user-defined criteria. 2/1/2019 ERP Support 11 19968 Track grants separately from G/L Chart of Accounts and reconcile the two. 12 20212 Comparison of Actual to Budget (Revenues/Receipts and Expenditures) 12/29/2017 2/1/2020 Need RFP 13 N/A - 39 Must configure system to utilize correspondence to vendors for all PO’s. 1/1/2019 14 N/A - 41 College needs a budget development system that allows for adequate budget building process. DG3 15 19713 Dispose of financial and non-financial assets. DG2

18 Remediation Open – Human Resources
# Item # Description Status Plan Date Adjusted Date 1 20596 Faculty Workload to generate and modify documents and pay for adjunct faculty based on user-defined criteria (4 Phases to resolve / 2 Phases remaining) Closed 3/1/2018 Package /31/2018 Package 2 – 3/1/2019 2 29976 Develop and Re-run the ESD report 12/1/2017 TBD - TCC to Test 3 37532 Bio-Demo data values not aligned with CS and HCM 12/31/2018 4 20753 Establish contract pay based on user-defined criteria. Open 1/1/2019 TBD - Needs CPW 5 20573 Need ability to report on department budgets TBD Needs Budget Tool 6 N/A - 0 DRS Redistribution 4/30/2019 5/10/2019 7 N/A - 27 Step Movement / Needs CEMLI DG2 - 10/24/2019 In Development 8 N/A - 29 Spokane would like to participate in UAT process for upcoming DGs implementing the Recruitment module. DG2 4/29/2019 9 N/A - 31 Migrate ctcLink framework to Wave 1 framework (related to Absence Management) 10 N/A - 32 Create “day” definition / Absence Management and Time & Labor issue 11 N/A - 34 Provide list of employees missing area codes / Legacy Data Issue 9/14/2018

19 Remediation Open – Campus Solutions
# Item # Description Status Planned Date Adjusted Date 1 20797 Support continuing education registration process where student can browse courses without logging on Open DG3 2/1/2020 In Negotiations 2 20901 Provide the ability for continuing education students to enroll directly in classes (i.e., application is not required). 3 21359 Allow payment online for continuing education based on user name and password. 4 21505 Perform third-party billing based on user-defined criteria (e.g., by student, consolidated) . Closed 5/1/2018 10/24/2019 GDR Approved 5 20814 6 21293 Support streamlined admissions processing and user interface. (Online Admissions Application) Evaluation 7 N/A - 13 Effective Dating: FA Term, FA Budget and other areas have defective Effective Dating 12/1/2017 TBD 8 N/A - 15 Reconciliation queries haven’t worked correctly or accurately since Go Live. 3/1/2018 5/30/2019 FY Deliverable 9 N/A - 22 Error/exception report identifying discrepancies between financial aid system and the general ledger (2nd Journal Set)

20 Remediation Open – Campus Solutions, cont’d
# Item # Description Status Planned Date Adjusted Date 10 N/A – 12 SAP Setup Effective Dating doesn’t work (Oracle Bug ID ) Open 6/1/2018 TBD Waiting on fix from Oracle Workaround in place 11 N/A – 17 Converted student account balances must be completely audited / corrected to reflect the ending balances from Legacy. 5/30/2019 FY Deliverable 12 N/A – 18 Reports to reconcile student financial transactions for a given day to the general ledger by item type, chartstring and fund. 5/1/2018 13 N/A – 19 Need accurate reports in the CS pillar for Student Financials to summarize data such as insurance, fees, waivers, etc. 9/30/2018 14 21451 Maintain academic standing for financial aid eligibility, based on multiple, user-defined criteria Closed N/A 15 21338 Track satisfactory academic progress (SAP).