Lafayette New Terminal Program Update
May 8, 2019
3
Terminal Program Update - Funding
FAA Currently managing grants White paper sent requesting funds for 2019 LA DOTD 2019 Program reviewed by State Legislature Joint Transportation Committee LA FP&C Coordinating with FP&C on eligible items for terminal construction Preparing individual FP&C packages for terminal construction 2019 Capital Outlay Application submitted Applying for $10 million towards terminal construction to be available in the Fall Terminal Program Update - Funding
4
Terminal Program Update - Funding
EDA Grant Application Funding Approved Coordinating additional information TSA OTA Application Submitted Grant Application, unfunded in 2019 Airlines Working with airlines to discuss leasable space and an agreement to buildout space QTA/Ready Return Concessions Terminal Program Update - Funding
5
Terminal Program Update – Projects
Enabling Demo Construction Complete. Final Acceptance upcoming Rental Car Quick Turn Around Facility (QTA) Construction: Notice to Proceed (NTP) 4/15/19; Scheduled Completion Q1 2020 Upcoming Construction Activities Earthwork, demo existing utilities, tie in new utilities Terminal Program Update – Projects
6
Terminal Program Update – Projects
Program Package 1: RTR, Enabling Projects and Terminal Foundations Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update – Projects Description Actual Start Planned Sub. Comp. Project 1 - RTR Cable Relocation Nov. 2018 Apr (actual) Project 2 – RTR Facility Jun. 2019 Project 3 – Terminal Foundations Jan. 2019 Jul. 2019 Project 4 – Airside Improvements TBD Project 5 – Enabling Parking May. 2019 Project 6 – Terminal Landside Program Package 2: Structural Steel, Elevators and Escalators Approved 1/15/19, Notice to Proceed 1/15/19 Description Planned Start Planned Sub. Comp. Construction Jul. 2019 Nov. 2019 Program Package 3: Terminal Building Shell, MEP and Finishes Terminal Building Shell, MEP and Finishes - Bid and Award March – June 2019 Description Projected Start Planned Sub. Comp. Construction Nov. 2019 2022
7
New Terminal Program Progress: Day 1 Progress: Day 176
8
GMP 1 – Project 2 RTR Facility
Final interior finishes (VCT floor, paint, testing/commissioning equipment) Seeding laydown areas May/June completion GMP 1 – Project 2 RTR Facility
9
GMP 1 : Project 3 Terminal Foundations
Construction piers, grade beam, pilasters and anchor bolts – ongoing Underground utilities – ongoing GMP 1 : Project 3 Terminal Foundations
10
GMP 1 : Project 3 Terminal Foundations
Completion July 2019 GMP 1 : Project 3 Terminal Foundations
11
GMP 1 – Project 5 Enabling Parking
Phase 3B - Substantial completion short term parking lot Phase 3A Soil Stabilization – under engineer/PM review Asphalt and fencing – ongoing GMP 1 – Project 5 Enabling Parking