ASTRON EMBRACE Project status G.W. Kant.

Similar presentations


Presentation on theme: "ASTRON EMBRACE Project status G.W. Kant."— Presentation transcript:

1 ASTRON EMBRACE Project status G.W. Kant

2 EMBRACE concept ‘analogue’ tiles
RF transport to central processing facility antenna elements

3 Tile Baseline architecture

4 EMBRACE Embrace is a development/production project, given the size and the time frame Use currently available technology If possible enhance EMBRACE with DSX outputs

5 Work Breakdown Structure

6 EMBRACE DS5 Tasks

7 EMBRACE DS5 Tasks

8 EMBRACE DS5 Tasks

9 EMBRACE DS5 Tasks Original estimates DS5 – Coordination (48mm/4fte)
DS5 – T1 Design and development of (382mm/32fte) DS5 – T2 Production of EMBRACE (244mm/20fte) DS5 – T3 Test the EMBRACE systems (190mm/16fte)

10 EMBRACE DS5 Tasks Astron UK OPAR CSIRO U-CAM OMMIC / IRA Jive / MPIfR
NRF (S.A) Jive / MPIfR Totals DS5 48 DS5-T1 240 32 10 12 18/0 16 308 (382) DS5-T2 84 12/0 160 (244) DS5-T3 44 0/12 32/12 184 (190)

11 EMBRACE DS5 Deliverables
Discuss/define DS5 – T3 deliverables first at SKADS level T3 deliverables are now detailed to a sufficient level to proceed T3 deliverables have to be enhanced further (parallel to T1/T2 activities)