Project Overall Status – June 10 to 21, 2019
Y Program is on track, per timeline, scope and budget Security Mapping activities impacting completion of UAT Current DG2 Schedule has no “float” remaining in timeline Scope Requirements Traceability Matrix (RTM) needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Schedule Monitoring scope and timing of: Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Budget G Currently tracking under budget New Technology Budget required by OFM/OCIO, Work in progress before new allotment for Gate 4 can be requested Executive Summary The project is tracking per schedule and under budget. Scope review and definition for each deployment continues due to rework of key solutions. Each Deployment Group (DG) is engaged and all colleges now have an Initiation or Implementation Work Plan: DG2 is in the Construct Phase. Colleges and SBCTC are engaged in User Acceptance Testing sprints. ctcLink Steering Committee approved the DG2 Chart of Accounts go-live for July. ctcLink will be offline for the upgrade Oct and again for cutover activities Oct DG3 is in the Structure Phase and recently completed Business Process Fit/Gap sessions. Preparing for DG3 Testing/Training road show in July. DG4 is in the Initiation Phase, with most colleges just past the halfway mark on deliverables. Gate 1 Initiation Phase Peer Review will be July at Highline College. DG5 colleges are in the Initiation Phase and have begun Initiation Deliverables public status reporting. PMO team visited colleges for Initiation road show in June. DG6 in in the Initiation Phase and will start public status reporting this fall. The Initiation Phase Road Show will be in Oct Planning meetings have begun with technical colleges to capture differences between technical and community college business practices. The new Chart of Accounts will be implemented for Spokane and Tacoma in July, following a “go” decision (with conditions) by the Steering Committee. Final contract negotiations continue for a new Continuing Education solution. The Online Admissions Application (OAA) work group is actively pursuing an OAA replacement. The Budget Planning Tool work group is reconvening in late June/early July to finalize business and technical requirements for a solution. Many college PMs will participate in the Prosci 3-day training opportunities in August in Centralia and Wenatchee to learn organizational change management principles. Overall Status Summary per Deployment Group DG# PMO- Reported Status Comments College/ Agency Self-Reported Status DG2 Y Security Production Mapping is in progress and production security must be tested to complete UAT Clark G SBCTC Spokane N/A Tacoma DG3 College Configuration in progress Conversion cycles have begun Cascadia LCC Olympic Peninsula Pierce DG4 College teams working on Initiation Phase activities Implementation begins Nov. 2019 DG5 Implementation begins March 2020 DG6 Implementation begins Nov 2020 1
2
Top Risks Reported – as of June 21, 2019
LEGEND: Critical High Moderate Low C H L M Risk Level Risk Description Mitigating Actions Submitted by (name, org/college), Deployment Group & Date Risk Owner (s) H Chart of Accounts (CoA): User adoption and successful deployment (scheduled for July 1, 2019) is critical for Deployment Group 2 (DG2) timeline. Update: On June 18, Steering Committee approved a July implementation of the new Chart of Accounts for TCC and CCS. Phase 1 cutover activities completed last weekend. Phase 2 technical cutover tasks will begin the weekend of June 22/23. Final configuration drop is slated for July 5. SBCTC will coordinate with the colleges on additional staff resources. Emmett Folk, ctcLink PM for FIN & HCM Team DG2 Impacted, Risk Date:10/12/2018 *also Risk submitted by Matt Connelly, Spokane District PM on 10/23/18 Emmett Folk C SBCTC: Risk of resource diversion due to CoA adoption. Combination editing rules will be revised in tandem with additional chartfield use. Impacts FirstLink Colleges’ (FLCs) ability to post many transactions prior to effective date. Cutover is planned to complete on 7/22/2019. If this happens, requires manual or automated workarounds to correct issues as they occur; will require SBCTC staff resources to support. Update: SBCTC, ctcLink FIN leads, ERP FIN lead will continue to meet to clarify roles for year-end close and their role in old chart of accounts. Next round -- when SBCTC is on the new chart of accounts -- their resources will be impacted. Discussions also occurred for how ERP will support the new chart of account issues. Evelyn Williams, SBCTC PM DG2 Impacted, Risk Date: 5/3/2019 Emmett Folk & Christyanna Dawson Clark: Student Financials – Clark submitted three risks. Update: Items related to Student Financials, Financial Aid, General Ledger and coordination between Student Financials and Finance. These items have been discussed with Clark. Cycle 4B is planned to mitigate these risks. A follow-up will be scheduled with Clark’s PM after Cycle 4B. Susan Maxwell, Clark College PM DG2 Impacted, Risk Date: 2/1/2019 Risks #50, #51, #52 John Henry Whatley, Emmett Folk, Chandan Goel Top Issues Reported – as of June 21, 2019 LEGEND: High Moderate Low H M L Issue Level Issue Description Status Update Submitted by (name, org/college), Deployment Group & Date Issue Owner (s) H Security Mapping activities to mitigate UAT timeline, have not addressed the new Security Design Production user access. Update: The ctcLink team is highly concerned about the Production Security Mapping for DG2 Colleges and entering new Security into one of the UAT cycles. Although there are no other options due to the schedule, this will be a challenge for the DG Colleges and SB as well as potential impact to the remaining UAT cycles. ctcLink PMO submitted for ctcLink CS, HCM, FIN Team DG2 Impacted, Issue Date: 4/16/2019 Tara Keen, Security Team ctcLink HCM Team & Clark: Timesheet (Classic & Enter Time) not up to accessibility standards. The Timesheet (Classic and Enter Time) are not up to accessibility standards. To mitigate this, HCM team will be opening up another timesheet in Fluid (Report Time) which is compatible with screen readers, but the long term solution should be to log an SR with Oracle so they create a bug and hopefully address this in a future Image so that Report Time can be removed from Self Service. Brian Lanier, HCM Pillar Lead Susan Maxwell, Clark College PM DG2 Impacted, Issue Date: 6/20/19 HCM Team 2
3
ctcLink Quality Assurance Scorecard / Moran Technology Consulting Report May 2019
Overall Status Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 STATUS PROJECT AREA DESCRIPTION / NOTES G SBCTC/Governance Go-No Go Decision for FLC implementation of new Chart of Accounts set for June 18, 2019. Project Management Project Management Office (PMO) is fully staffed, working well together and continuing to address improvements in project management processes. PMO has interviewed candidates to replace Open position for a qualified PM to manage Schedules. Y Phase Scope QA remains concerned about the number of solutions to be re-implemented to replace/augment current PS functionality. Based on the May status of replacement solutions, it does not seem possible that these will be decided upon and readied for DG2 scope inclusion. Schedule Status DG2/DG3/DG4 schedule overlap and resource constraints directly impact all deployment groups. Schedule compression and key project resources are heavily allocated to multiple DG2 workstreams and supporting DG3 tasks. DG2 schedule is dependent on CoA implementation at CCS and TCC colleges. Training Training materials to support Sprints 1 and 2 were completed in time for use. Sprint 3 materials were being completed. Considerable work still remains to develop the 60 courses to support end-user training. For DG2 success, training focus still requires active end-user participation, effectiveness assessments and college follow-up. Testing The DG2 User Acceptance Testing (UAT) Sprints, supported with Training materials was underway in May. Sprint 1 completed and Sprint 2 was starting in end of May. The DG2 Testing workstream is now a major QA concern since it requires active FLC college end-user participation. Configurations / Data Conversion ctcLink project technical staff are planning at least one additional conversion cycle to support Clark College during data review of Student Financials. Parallel testing conversions for Payroll were underway in May. DG2 production cutover planning sessions to begin at the end of May. Month-end and Year-end CoA data conversions were being run in May to determine differences in Gross Calculations. QA views this as a Critical Go-No Go supporting activity for FLC colleges implementation of the new CoA. Organizational Change Management PMO/OCM is actively engaged with all colleges now involved with their Deployment Groups. QA concerned that PMO focus remains on the DG2 schedule. PM Summit was held in early May with all deployment groups represented. Project Staffing Project staffing is adequate at this time and continues to make staffing adjustments as appropriate. PMO is recruiting for open positions. QA and the PMO remains concerned that the overlap of DG2/DG3/DG4 may require additional project and contractor resources. Technical Environment The IT division continues addressing processes and critical staffing. Draft of Service Level Agreement has been distributed to colleges. IT is reviewing staffing models at other PeopleSoft ERP community college systems for staff and budget sizing. The development of security roles for the colleges has been taking longer than expected. The security setup has impacted the start of the UAT Sprints. Security changes are not considered a show stopper since colleges can implement changes after Go-live with PeopleSoft ERP. LEGEND GREEN YELLOW RED Risk Description: Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost. 3
4
WA State Office of the Chief Information Officer (OCIO) Oversight
WA State Office of the Chief Information Officer (OCIO) Oversight as of June 2019 Overall Status Y WA State Office of the Chief Information Officer (OCIO) Oversight WA State Office of the Chief Information Officer (OCIO) Oversight OCIO Conditions to new ctcLink Investment Plan Approval Status G 1 Project must remain in line with SBCTC and OCIO policies Ongoing 2 QA (Moran) to report to ctcLink executive sponsor and State CIO Complete 3 Follow pre-determined OFM funding gates and approvals 4 Monthly status reporting 5 Continue reporting on Remediation items in Integrated Work Plan Y 6 OCIO approval of the 4 remediation solutions: Budgeting tool, Continuing Education Application, Online Admissions Application In Progress 7 OCIO must be notified prior to use of contingency funds N/A 8 Perform a post-implementation review (lessons learned) after each deployment and post on the OCIO dashboard within 30 days of go-live Planned as Activities in Project Work Plans 9 Process and timeline for filling the SBCTC CIO position by 1/31/2018 ctcLink Technology Pool Status and Gate # Status G N/A Pre-IT Pool Implementation, Stability & Remediation Approved 1 Planning & Remediation 1/1/2018 2 DG2 – Initiation & Structure Phase 3 DG2 – Construct Phase DG3 – Initiation & Structure Phase 1/1/2019 New Technology Budget required and being developed for ctcLink Project In Progress Note: New ctcLink Investment Plan approved by OCIO, with above conditions, on Jan. 19, 2018. 4
5
Budget Status – as of May 31, 2019
6
Human Capital Management
Pillar Status – June 10 to 21, 2019 Campus Solutions G Accomplished this period Hold DG3 Cycle 2 data validation workshops Support DG3 Cycle 2 data validation Clark Transfer Credit Rule Go Live Workshop Prep Clark Dual Processing SIT end to end (45% complete) Request DG3 Cycle 3 College Optional Files DG2 Sprint 3 CS UAT Continue DG3 FIT Continue DG2 SIT Continue UAT material planning/build Review DG3 assignment submissions for configuration DG3 Draft FA local configuration guides DG2 and DG3 Highpoint Mobile test scripts completed Clark Mobile Local Configuration Guide (draft) Planned for next period Gather DG3 Cycle 3 College Optional Files Hand-Off DG3 Cycle 3 College Optional Files to Legacy Team Prep for a possible 4b conversion Support UAT for DG2 Colleges Prep for Parallel Testing – Dual Processing Prep for Parallel Testing – Tuition Calculation Planned, but not completed Clark Dual Processing SIT end-to-end (45% complete) Human Capital Management Y Accomplished this period Completed DG3 Cycle 2 Validation Material Development Held DG3 Cycle 2 Validation Workshops Began review of Security Redesign Role/Permission List Definitions Continued Payroll Parallel Testing Activities Continued UAT support activities Continued DG2 UAT diagram/scenario updates Continued DG2 UAT supporting content build Continued review of DG2 Training content structure and materials Continued DG2 and DG3 configuration build-out in FNC environment Planned for next period Collect DG3 Cycle 3 Data Files Begin DG3 Cycle 3 Prep Activities Continue review of Security Redesign Role/Permission List Definition. Continue Payroll Parallel Testing Activities Continue UAT support activities Continue DG2 UAT diagram/scenario updates Continue DG2 UAT supporting content build Continue review of DG2 Training content structure and materials Continue DG2 and DG3 configuration build-out in FNC environment *If status is yellow or red, describe why. DG2 UAT and pre-UAT training supporting materials are being provided on a just in time basis. concurrent DG2 and DG3 activities are causing the team to prioritize externally-/client-facing activities and deadlines/starts for certain internal tasks continue to get missed. Financial Services Y Accomplished this period Completed DG3 Cycle 2 Validation Material Development Held DG3 Cycle 2 Validation Workshops Began review of Security Redesign Role/Permission List Definition Continued DG2 UAT support activities Continued DG2 SIT Test Execution Continued DG2 UAT supporting content build Continued review of DG2 Training content structure and materials Continued DG2 and DG3 configuration build-out in FNC environment Planned for next period Collect DG3 Cycle 3 Data Files Begin DG3 Cycle 3 Prep Activities Continue review of Security Redesign Role/Permission List Definitions. Continue DG2 UAT support activities Continue DG2 SIT Test Execution Continue DG2 UAT supporting content build Continue review of DG2 Training content structure and materials Continue DG2 and DG3 configuration build-out in FNC environment *If status is yellow or red, describe why. DG2 UAT and pre-UAT training supporting materials are being provided on a just in time basis. concurrent DG2 and DG3 activities are causing the team to prioritize externally-/client-facing activities and deadlines/starts for certain internal tasks continue to get missed. Pillar Status – as of 6/8/2018
7
Workstream Status – June 10 to 21, 2019
Communications G Accomplished this period Communications Advisory Committee planning ctcLink reps for Commissions/Councils meetings - develop spreadsheet, website and process Chart of Accounts Go/No-Go Decision communications Post-PM meeting Chart of Accounts status and decision process clarification Organized the Chart of Accounts decision package materials for Post-CoA decision communications to stakeholder groups Planned for next period Continue Comms Advisory Committee planning Communications Office scope/activities Templates work (including Critical Communications Template) Technical G CONVERSION Accomplished this period DG2: Conversion Issues review/ resolution. DG3: Cycle 2, Conversion Issues review/ resolution. Planned for next period DG2: Conversion Issues resolution– In Progress DG2: SF Parallel Test activities. DG2: Cycle 4 B Conversion activities. DG3: Cycle 3 Conversion Activities. DEVELOPMENT Support and work on Service Desk, SIT & UAT tickets for CS, HCM & FS pillars. Migrated the retrofit projects (for FSCM PUM 32) to SIT & GDR environments. Testing support on HCM for CEMLI SE-235, SE-234 & I-024. Continue to support on Service Desk, SIT & UAT tickets for CS, HCM & FS pillars. OAA Application Fee changes ENVIRONMENTS Coordinated PUM Image Update in Project environments. Coordinated Load Testing Project work. DG3 cycle 2 environment refresh. Validate STAT Workflow for Project environments. STAT Project gather questions and feedback from team DG3 cycle 3 environment support. Load Testing Project support. Testing Y Accomplished this period Continued system integration testing (SIT) Began Sprint 3 UAT Provided metrics on SIT status Continued to build UAT materials Supported Sprint 1 and 2 UAT Began completing data sheets for CS automation Completed COA UAT Provided metrics on UAT status Planned for next period Begin UAT sprint 4 execution Continue to build UAT materials Continue system integration testing *If status is yellow or red, describe why. Overlapping project tasks that utilize the same resources may impact testing. Organizational Change Management G Accomplished this period Continued DG5 Initiation Deliverables road show Meet with DG2 PMs to discuss how change management activities are going with their teams Continued planning DG4 Peer Review Continued planning DG3 Road Show around upcoming Testing/Training Assisted in onboarding new college PMs Planned for next period Continue to work with CPW Facilitators and Functional Teams to determine scope for upcoming sessions Continue College Relations/OCM Check-ins with DG3, DG4, DG5 and DG6 Continue development on schedule of events with PMO and all Deployment Groups Training Y Accomplished this period Finalized and distributed schedules for all remaining sprints (4 through 6) Made modifications on training delivery via lessons learned Currently at 40% with content for Sprint 4 Started working in all pillars on development of End User Training Courses Continue to work with vendor on HCM and CS UAT training deliverables Planned for next period Continue to work on Pre-UAT Training materials Continue to work on End User Training courses *If status is yellow or red, describe why. Large amount of materials needed with upcoming timelines
8
Deployment Group 2 Timeline (High Level Phases)
9
Deployment Group 2 Self-Reported Status – June 10 to 21, 2019
SBCTC Agency Y Accomplished this period Risk Management Team added the following: #60 Grant conversion meeting held with next steps determined 6/20 Teri Sexton supported CS Chart of Accounts UAT Executive Sponsor John Boesenberg voted in support of the Chart of Accounts Go/No-go approved on 6/18 Planned for next period Risk Management Team to meet and review additional risk and or issue adds. Planned, but not completed Status is needed regarding completing a list of all supplemental systems. As of the DG2 meeting, 5/23/2019, SBCTC has until the end of UAT Sprint 4, (7/15/2019) to complete all UAT. 6/7/2019 update: UAT still in progress. *If status is yellow or red, describe why. The agency has confidence in the project team’s and agency SMEs’ ability to succeed. At this time, the following risk items or concerns in scope are the reason for “yellow” status: #65 - Security Mapping #60 - Chart of Accounts Accurate Approval Workflow Engine (AWE) #42 WAPAY: SBCTC requires this separate WAPAY payroll account up and running in production to go-live in October Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in ctcLink Security redesign activities Participated Chart of Accounts meetings. Participate in UAT Started OCM planning and execution for DG2 project Monitor UAT status Planned for next period Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Local SME attend Chart of Accounts meetings Work with SMEs, Pillar Leads, TCC Leadership to get better participation in the project Plan and execute OCM for DG2 project Clark College G Accomplished this period Completed Sprint 3 UAT. Positive feedback from financial aid who appreciate the changes made by SBCTC. Conversation with a representative from Oracle regarding their conformance to WCAG 2.0 AA standards. Held our first summer open lab. Planned for next period Query training for query developers by 6/11 QDLC online – then Paula McDonald will come to Clark for PS Query 101 training in July. Refine Training plan and schedule Sprint 4 Planned, but not completed More progress on AARs and documentation Community Colleges of Spokane N/A No report for this time period.
10
Deployment Group 3 Timeline (High Level Phases)
11
Deployment Group 3 Self-Reported Status – June 10 to 21, 2019
Cascadia College G Accomplished this period Participated in several BPFG homework follow-up WebEx sessions Participated in Cycle 2 Data Validation Workshops Initiated Cycle 2 Data Validation Completed data error file cleanup for cycle 3 Initiate optional/homework assignments due June 28th Planned for next period Continuing data validation Cycle #3 Complete optional/homework assignments by June 28 Pierce College District G Accomplished this period SMEs participated in Cycle 2 data validation sessions. SMEs completed/submitted homework assignments. Identified next steps and established plan with Reporting Lead and query developers. Planned for next period SMEs complete Cycle 2 data validation. Planning for SBCTC follow-up session on July 10 OCM activity – plan appreciation lunch for SMEs on July 10 Identify Training Lead Planned, but not completed Review applicants for project positions. Review and update Communications Plan Review and update internal Training Plan with college Training Team. Identify/establish training space. Peninsula College G Accomplished this period Attended Validation workshops Completed data clean up HCM SMEs completed data validation by June 19 to ensure correct data in UAT/SIT processing. Planned for next period Continue to work on validation Submit optional files Complete any remaining CE and FWL assignments Lower Columbia College G Accomplished this period Work in Cycle 2 conversion validation. Review legacy reports for future remapping to ctcLink Work through transition activities for new PM and Alignment Team Start campus messaging and communication around fall training requirements for faculty and staff. Planned for next period Continue on campus messaging and communication about ctcLink Continue to develop forecasting tools to track staff workload and project hours. Select new project manager and work to transition activities and responsibilities into that new structure. Planned, but not completed Train a replacement PM, LCC is still without an effective replacement though temporary arrangements are being discussed. Olympic College G Accomplished this period Continued training third Project Analyst Continued work on ATD/ctcLink Teams for Residency, Choosing Academic Plan, Changing Academic Plan Started Data Cycle 2 Validation Completed Data Cycle 3 Cleansing Planned for next period Files due 6/28 Cycle 2 Data Validation Restart Change Impact Analysis Workshops Planned, but not completed Additional CIA Workshops
12
Deployment Group 4 Dashboard Reports – June 10 to 21, 2019
DG4 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis DG4 target percentages will be added in August 2019. College/District As of June 21, 2019 Centralia College 60% Edmonds Community College Highline College 59% Seattle Colleges (3) 52% Wenatchee Valley College 65% DG4 Pre-Implementation and General Timeline G
13
Deployment Group 5 Dashboard Reports – June 10 to 21, 2019
DG5 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis College/District As of June 21, 2019 Target Percentage for June 2019 Bellevue College 10% 25% Bellingham Technical College 18% Big Bend Community College 21% Everett Community College 20% Grays Harbor College 29% Green River College 26% Skagit Valley College 13% Whatcom Community College 27% DG5 Pre-Implementation and General Timeline G
14
ctcLink Remediation Status Reports – June 10 to 21, 2019
Solution Status Due Date Campus Solutions 10 of 45 remain open DG3 Financial Management 5 of 39 remain open DG2 Human Capital Management 6 of 25 remain open Faculty Workload Complete March 2019 DRS Redistribution May 2019 Absence Management April 2019 Security Audit Controls Security Redesign Mapping Framework FLC / DG2 Student Billing/Third-Party Billing Budget Planning Work Group Review RFP Jan 2020 Online Admissions App RFI Being Developed Continuing Education Vendor Negotiations Chart of Accounts (revised) Due/Finish Status Tacoma CC Chart of Accounts Adoption Kickoff Dec. 12, 2018 Complete CCs of Spokane Chart of Accounts Adoption Kickoff Feb. 1, 2019 Foundational Chartfield Configuration March 22, 2019 College Configuration Review and Updates May 3, 2019 Functional and System Integration Testing May 10, 2019 User Acceptance Testing May 10 - June 3, 2019 May 28 – June 14, 2019 College Readiness Gate / Go-No Go Discussions June 12-14, 2019 Readiness Gate / Go-No Go Decision June 18, 2019 Production Cutover July 2019 In Progress Community Colleges of Spokane N/A No report for this time period. Tacoma Community College G Remediation Items progress this period See SBCTC status update for Remediation items, tickets, and worklist. Planned for next period Receive remediation detail with responses based on December 2018 feedback
15
Other ctcLink Project Activities – Status as of June 21, 2019
New Solution Status RFP Publish Solution Decision Continuing Education RFP was developed and approved by Governance RFP proposals were due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Governance approved procurement and decision of Vendor Vendor Contract being finalized for scope and cost 10/15/2018 Contract Draft Complete Overall Pricing in Negotiations Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft universities and colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions on 2/12/2019 RFI to understand possible solutions and costs before final decision on RFP or custom solution Continue to enhance current OAA based on requirements for RFI TBD RFI requested Current ctcLink OAA requirements being prioritized prior to continue improvements Budget Planning Committee to be formed to review, finalize and approve Budgeting requirements Review requirements against Oracle PBCS Solution If needed, develop RFP Work Group Kick Off Members reviewing Original RFP Budget Requirements Physical Inventory (Asset Tracking) Vendor Solutions being evaluated Evaluate new PS Functionality that will provide integration for asset tracking scanners directly with ctcLink 5/21/2018 DG3 (February 2020) Accessibility Continued discussions with Appsian (formerly Grey Heller) Identify accessibility vendor to assist with testing of ctcLink Develop and published RFP Work Group engaged to evaluate RFP Responses Final Decision on Vendors to be awarded 5/10/2019 Testing Prior to DG2 (October 2019)