Scenario Framework for the Gas Network Development Plan 2020-2030
Market area merger Holger Sippel, GASCADE
2
Agenda Introduction New capacity model ("NewCap")
Market-based instruments NewCap integration into network development plans
3
Introduction Amendment of sec
Introduction Amendment of sec. 21 of the Gas Network Access Ordinance (GasNZV) Core task: Merger of the NCG and GASPOOL market areas VTP access will be upgraded Deadline: 1 April 2022 TSOs: To be implemented by 1 October 2021 Goal: Increase gas market liquidity TSOs: Keep capacity levels & quality unchanged from Gas NDP , if possible Investment measures or use of other instruments, taking account of ‘safety’ and ‘cost-effectiveness’ as two key criteria -
4
New capacity model ("NewCap") in a nutshell
5
New capacity model ("NewCap") Scenarios
Redistribution options Transit options
6
New capacity model ("NewCap") Redistribution example – Reduction of imports from western Europe (LNG) compensated by higher imports from Russia
7
Market-based instruments Example: Wheeling
8
Market-based instruments Example: Third-party network use
9
Market-based instruments Example: Exchange-based spread product
10
"NewCap" + network planning Integration into the modelling via…
2. Adjustment of TSOs’ own networks expansion costs 1. Input variables 4. Overall optimisation of expansion vs. MBI - 3. Recalculation with the TSO-specific capacities MBI costs
11
Thank you for your attention.
Vereinigung der Fernleitungsnetzbetreiber Gas e.V. Georgenstraße 23 / D Berlin Tel Fax