DOE Review of the LCLS Project 7-9 February 2006
Quality Assurance Darren S. Marsh Stanford Linear Accelerator Center
2
Quality Assurance Activities
Major Areas of Quality Assurance Quality Program Management and Support Planning Design Reviews Risk Management Procurement and Subcontractor Control Manufacturing, Inspection and Test Control Problem Identification and Corrective Action Assessment
3
Quality Assurance Program
LCLS QA Program will be conducted in accordance with LCLS Quality Implementation Plan Lessons learned from other programs will be utilized The implementation relies upon the controlled application of plans, procedures, and requirements Objectives Design it to specifications the first time Build it correctly the first time Procure quality compliant components & services Test it completely the first time
4
LCLS Total Management System
DOE Orders/Guides SLAC ISMS/EMS LCLS PMP, PEP, QIP, ES&HP LCLS Procedures/Plans Lessons Learned Best Practices Objectives/Goals Ensure requirements & expectations are met Provide confidence in achieved results Comply with applicable regulations & requirements
5
Integration of LCLS ISM and QA
Core functions and principles of both programs substantially overlap, with no principles in opposition ISM and QA programs are together part of the total LCLS management system and processes for getting work done with safety, quality, and efficiency
6
ANL & LLNL Quality Assurance
From LCLS QIP Quality standards at ANL/LLNL/SLAC are comparable
7
Technical Specifications
8
Technical Baseline – Design Definition Requirements Summary
9
Requirement Documents Tracking
Requirement documents status reviewed at LCLS CCB Meetings Applicable requirements document updated based on CCB action or requirement change
10
Design Review Program Design reviews are essential to good engineering practice and will be used as a quality assurance metric to ensure the successful construction of the LCLS. ESD establishes guidelines for design reviews conducted by the LCLS Subsystems. It describes the material to be covered, the documentation requirement and the process for closure of all action items. Reviews based upon the appropriate selection from the following reviews: System Concept Review (SCR) Preliminary Design Review (PDR) Final Design Review (FDR) Readiness Review (RR)
11
Technical Design Reviews
12
LCLS Risk Management Continuous risk management performed in accordance with the LCLS Risk Management Plan Project execution risk involves the ability to deliver the desired product meeting requirements, on time and within cost. To quantify risk, we look at the likelihood and consequence of an event Risk Management will include: What can go wrong? How likely is it to go wrong? What would be the consequences if something does go wrong? What can we do to prevent things from going wrong, or as least reduce the probability or severity of the consequences? How soon do we need to act? EXPECT THE UNEXPECTED SO THAT THAT UNEXPECTED BECOMES EXPECTED
13
LCLS Risk Registry Risk Registry (RR) monitors list of known risks to be managed until retired 56 total risks identified - 32 Technical - 18 Programmatic - 6 Retired Managed and updated monthly
14
Procurement & Subcontractor Control
PMD establishes processes to ensure that suppliers provide items and services that meet requirements Procured items and services must perform as specified and meet requirements Suppliers are evaluated and selected based on specified criteria Acceptance of procure items and services in accordance with specified methodology Advance Procurement Plan key for critical procurements
15
Manufacturing, Inspection and Test Control
Manufacturing, Assembly and Installation Activities Work processes are planned and controlled Activities are performed in accordance with prescribed instructions, procedures and drawings Items are designed and changes controlled using sound engineering practices, analyses and configuration management Inspection and Test Items are inspected and tested to verify conformance to specified requirements
16
Problem Identification & Corrective Action
LCLS QA Report identifies major systems and components that do not meet established requirements Conditions adverse to quality are identified, controlled and corrected to prevent recurrence, and reviewed for lessons learned QA Reports (2 total) from 2005 installation activities Sector Waveguide Penetration Vacuum Leaks Injector RF Waveguide contamination
17
Management Assessment
Management processes assessed to identify and correct problems that may hinder the project from achieving its objectives Assessments conducted to evaluate work performance and to promote improvement October 2005 Installation Feedback and Improvement Meeting
18
Summary Quality Assurance processes are in place to plan, perform, assess, and improve work Based on the development and maintenance of the integrated LCLS Total Management System Performance oriented Minimizes environment, safety, and health risks and impacts while maximizing reliability and performance Need to ensure QA Requirements are understood by all LCLS personnel