Director of Water Engineering

Similar presentations


Presentation on theme: "Director of Water Engineering"— Presentation transcript:

1 Windsor Utilities Commission Capital Plan 2018 Presented by Norbert Poggio

2 Director of Water Engineering
Norbert Poggio, P.Eng Director of Water Engineering

3 CAPITAL BREAKOUT 2018 2018 Capital Breakout New Reservoir Project
New Reservoir Project $5,088,000 Watermain Projects $16,206,000 Metering Projects $2,592,000 Water Treatment Facilities $2,023,000 Transmission and Distribution Projects $571,000 Engineering Projects $28,000 Vehicles $339,000 Water Capital Subtotal $26,847,000 District Energy Projects $50,000 Total WUC Capital $26,897,000

4 WUC CAPITAL SPEND

5 SYSTEM RENEWAL PROGRAM
PROPOSED 2018 WATERMAIN SYSTEM RENEWAL PROGRAM GRAND TOTAL $ Million 2018 WATERMAIN RENEWAL PROGRAM TOTAL SEWER / ROAD PROJECTS $ Million TOTAL ROAD OPERATIONS PROJECTS $ Million TOTAL WUC PRIORITY PROJECTS $ Million TOTAL MAJOR ROAD PROJECTS $ 0.0 Million

6 WINDSOR UTILITIES COMMISSION WT/DEW/DISTRIBUTION/METERING
Water Treatment - $2.023M Intake screens, intake macerator, flow meters, heat pump , chlorine header, ozone generator, high lift pump rehab, replace chemical systems, LL pump vacuum system, asbestos remediation. District Energy Windsor - $50K Replace heat exchangers and control valves (aging ETS equipment) Valve replacement Water Distribution - $571K Maintenance of hydrants, valves and services Water Metering – $2.309M Continuing to replace/install water meters Water Engineering - $28K Miscellaneous software and equipment upgrades / repairs.

7 WINDSOR UTILITIES COMMISSION NEW RESERVOIR
$5,088,000

8 WINDSOR UTILITIES COMMISSION SCHEDULE - NEW RESERVOIR
Winter 2017/Spring 2018 Continued construction. Summer 2018 Commissioning of New Reservoir Winter 2019 Rehabilitation of Existing Reservoir

9 Questions??