CO2 progress and issues on the control systems
Lukasz Zwalinski – PH/DT
2
L.Zwalinski – PH/DT CO2 test stand control system 11.05.2011
CO2 – 100W Electrical schematics completed in 99% details Electrical control components ordered 100% (overall cost chf) details Delivery status LHCb 69%, ATLAS 36% Mechanical integration in CATIA model Mechanical + electrical assembly of the first unit has already started All documents available on the workspace with versioning functionality activated L.Zwalinski – PH/DT CO2 test stand control system
3
L.Zwalinski – PH/DT CO2 test stand control system 11.05.2011
CO2 – cryolab User accumulator SP changed from AIC to Analog Parameter L.Zwalinski – PH/DT CO2 test stand control system
4
L.Zwalinski – PH/DT CO2 test stand control system 11.05.2011
CO2 – cryolab The electrical distribution box is 90% completed (missing dif block ordered ) …. :00Pos. 14 Expected delivery date: 09/04/2011 :00Pos. 14 Expected delivery date: 17/04/2011 :00Pos. 14 Expected delivery date: 08/05/2011 :00Pos. 14 Expected delivery date: 18/05/2011 L.Zwalinski – PH/DT CO2 test stand control system