1
Current Issues and Concerns For Capital Programming Guide Input
NDIA PMSC Current Issues and Concerns For Capital Programming Guide Input
2
Recommendations OMB should consider
Need to figure how to raise to acquisition community Need companies to flow to subcontract managers
3
Contractual/Application Issues
Undefinitized Actions Delays Contractual direction to ignore scope and plan work Format 1 by NRE/Rec Format 2 with PM by Subc Timely incorporate (<60) required for meaningful baselines Scope/Schedule/Budget integration key EVM principle Manage by scope How to manage versus principles
4
Contractual/Application Issues
Duplication of requirements C/SSR and CPR Risk 3-point estimates every task Not recognizing existing independent certifications Non-value added, increases cost Non-value added Costly – non value added. Base on surveillance and cause
5
Contractual/Application Issues
Initial Compliance Reviews (ICR)– Delay in final reports ICR – Findings not tied to intent guide or ANSI Application below thresholds Approaching half-year Form over function, non-value added Costly
6
Incentives Incentives of CPI or SPI
Get what you measure. From management system to reporting one.
7
Application Weekly EV and slips of one day reportable and not tied with critical path Prohibition of rebaselines/OTB MR Ownership issues Costly and not consistent with schedule principles. May slip non-critical work in favor of critical. Adequate baseline required for EVMS Encourage hiding in planning packages
8
Application 30 day IBR Required to do IBR before scope identified
Application of CPR/IMS DIDs retroactively Encourages inadequately planned baselines Adequate baseline required for EVMS Same DID number confusing