School Capital Programme Update Michael Coleman Head of Education Property
Example of need for façade works programme
2
Contents The issues we face Prioritisation How we deliver AMP works
Future plans School vs. LA capital responsibilities
3
The Issues We Face Government funding lags further and further behind need:£2.4m annual funding. We spend £3.5m+ through the Asset Management Plan programme. More could always be spent if available… Victorian schools estate: ageing relatively well, but in need of TLC, hence the Façade Programme Basic Need: no further primary expansions planned, given change in pupil projections Need to resurvey the estate to plan strategically for immediate future: revenue costs are considerable but aiming for 2020 No obvious end to austerity…
4
Prioritisation Health and safety issues – major risks, such as materials falling from the façade Major issues that will cause school closure if not addressed: Boilers & heating distribution Roofs Structural issues Fire safety Etc.
5
How we deliver works Prioritise works on an annual basis
Bid for funds from central Council funding Programme is delivered by the Local Education Partnership (Keith Winter & Alex Kaitsis) – they undertake procurement This model has been in place for 3 years and has performed better than the previous regime Non-AMP works are put out to tender, e.g. façade programme and managed in Education Property Team Previous incidents addressed individually, not as symptoms of a wider issue, either on that site or across the estate, so no systematic analysis of all susceptible sites
6
Future Plans Façade programme C has been procured
Façade programmes D & E will be out to procurement soon Façade programme F to follow AMP works programmed for delivery this summer (in the main) City of London Academy Shoreditch Park is the one new school project in train – works commenced New Regent’s College will open on new site at Nile Street shortly (joining new Nightingale Primary at Tiger Way) Aim to complete new condition surveys in 2020
7
School vs. LA responsibilities
As set out in Scheme for Financing Schools (Annex C) £6000 de minimus on value of works