Presentation is loading. Please wait.

Presentation is loading. Please wait.

May 9, 2019.

Similar presentations


Presentation on theme: "May 9, 2019."— Presentation transcript:

1 May 9, 2019

2

3 Updates Phase 1.1 Phase 1.2 Phases 1.3 and 2 Remaining items
Construction activities Partner coordination Phases 1.3 and 2 Design Activities

4 Phase 1.1 Remaining Items Additional railing at Travis Gatehouse
Installation completed Inlet lighting Trash screen at inlet pump station Work postponed until late 2019 Santa Rosa Pedestrian Crossing

5

6

7 Phase 1.2 Construction Houston to Commerce Commerce to Dolorosa
Concrete pours for channel bottom and walls Penner’s parking deck Infrastructure for water wall Commerce to Dolorosa Channel slab excavation Dolorosa to Nueva Pier cap installation Excavation of east bank

8 Phase 1.2 Construction Commerce Street Bridge Dolorosa Street Bridge
Construction of south half completed South lane reopened Full closure still planned from mid-June through July Dolorosa Street Bridge Demolition of north half of bridge started Traffic will be reduced to one lane until April 2020

9

10

11

12 Phases 1.3 and 2 Design

13 Phase 1.3 and Phase 2 Design Second series of charrettes conducted
Design concepts presented to Judge Wolff and Commissioner Justin Rodriguez Design team developing design concepts Request Commissioner Court approval in June

14 Partner Coordination SAISD administration building
SARA/SAISD coordination Camaron Street construction Travis to Houston block to be completed in May Remainder to begin in late 2019 Alameda Theater Project team coordination Texas Public Radio Coordination ongoing

15 Partner Coordination Commerce Street UTSA downtown campus expansion
Value engineering/scope reduction ongoing Construction to begin late August UTSA downtown campus expansion Coordination meeting held Federal Courthouse (GSA) Design and construction coordination ongoing

16

17 Partner Coordination Executive Committee Next Meeting – TBD
David Smith, County Manager, Bexar County Lori Houston, Assistant City Manager, City of San Antonio Razi Hosseini, Interim Director, Transportation and Capital Improvements, City of San Antonio Suzanne Scott, General Manager, San Antonio River Authority Next Meeting – TBD

18 QUESTIONS & COMMENTS


Download ppt "May 9, 2019."

Similar presentations


Ads by Google