1 Santa Teresa Landfill and Remediation Project
lgant 2019

2 Commence landfill construction
OVERVIEW Approvals Design & compliance Stakeholders Commence landfill construction Remediation Project

3 INTRODUCTION MacDonnell Regional Council is part of the CAWMWG which was formed in 2012 BRC, CDRC, Dept. of Environmental Health, NTEPA, DLGHCD, NT Worksafe and LGANT). 33 remote communities and their stakeholders working to develop sustainable Waste Management “Best Practice”

4 Santa Teresa Landfill design and closure 2016/2019
Lease application submitted 2016 Sacred site clearance submitted 2016 Approvals received Dec 2018 Work commenced by MRC Dec 2018 Work completed June 2019

5 Time frame for construction of new facility 4 (working) months

6 Central Australia landfill Operations Manual

7 Guidelines for the Closure Legacy Waste Sites
Identify Key Stakeholders Complying with Regulatory & Statutory requirements Recording of the sites History Planning for site Remediation Establishing budgets for the remediation Implementing the Closure plan Post closure maintenance Identification and audit of legacy waste sites

8 Infrastructure involved for the new site
Construction of: Council Compound to bury and stockpile items Fire breaks, sediment ponds, ground water channels Public Drop off Area (Transfer Station) for Public use 24 hours All weather entry road All weather public drop off pad

9 Project planning

10 Following Compliance and Legislative requirements

11 Project Stakeholders LA Santa Teresa CLC (who consult with TO’s)
Santa Teresa School Catholic Care (CDP provider) AAAC Catholic Church Santa Teresa store MRC

12 Stakeholders meeting held Dec 2018
Final meeting discussed; Timeline for construct Remediation of the old WMF site What infrastructure will be involved What land clearing/fencing/firebreaks etc. Compliances and legislative requirements to be followed

13 From the meeting the site was amended

14 Site Identified

15 Identifying boundaries

16 Redesign to fit site

17 Clean and clearing of the Site

18 Marking the site

19 First General waste pit
Compound construction

20 Welcome to Santa Teresa Landfill prior to JUNE 2019

21

22 Drop Off Bay Signage Stockpile & Pit Signage

23 The Old landfill March 2019 General Waste Pit Septic and Animal Pit

24 Metal Stockpile Vehicle Stockpile

25 C & D and Green Stockpiles
Tyre Stockpile

26 1 2

27 3 4

28 5 6

29 7 8

30 9 10

31 11 12

32 13 14

33 Remediation works commence

34 JOB DONE !

35

36

37 Thanks Graeme, Mervin & Paul

38 THANK YOU