Globus-M2 will be constructed by the end of 2015
The detailed design of tokamak upgrade was fully completed in the beginning of 2014 All special conductors for the TF rod, TF coil outer limbs, PF coils and central solenoid have been manufactured and delivered to the Ioffe Institute Prototypes of all critical parts have been successfully tested. A full scale CS prototype was winded with a 1 mm gap in situ over the TF rod mockup The manufacturing of a new magnetic system was successfully started Technical schedule for Globus-M2 electromagnetic system construction 2013 2014 2015 2016 Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Detailed Design Delivery First criticality Procurement of materials Basic materials Additional materials Manufacturing Assembly